Tathastu Project at Thane West by Squarefeet Group (P51700017002)
  • Rating:
  • ()

Tathastu - Thane West

Squarefeet Group
Project Details, Configuration & Prices
2 BHK557 Sq.ft. Carpet ₹ 80.99 Lacs ++
Project overview
Tathastu Project at Thane West by Squarefeet Group (P51700017002) is a RERA approved Under Construction Project with RERA ID P51700017002 slated to be ready for possession by Mar 2028 with 2 BHK apartments / Flats starting from N/A onwards

Discover luxury living at Tathastu Thane, offering hill-view sun-deck 2 BHK flats in the tallest tower on Ghodbunder Road. Spread across 4 acres, this Vaastu-compliant project features 50+ amenities, a lavish clubhouse, high-speed lifts, ample parking, and multi-layered security. Located near top schools, malls, hospitals, and upcoming infrastructure like Metro Line 5 and Thane-Borivali Tunnel. Book your dream home in Deffodil Tower – a 36-storey landmark of elegance and comfort.
Tathastu QR Code
Tathastu
MahaRERA - P51700017002

Godrej Emerald

₹ 1.05 Crs. onwards
Thane West
1½/2/3 BHK apartments
View Details

Kalpataru Paramount

₹ 99 Lacs. onwards
Thane West
2 BHK apartments
View Details

Orovia-Commercials

₹ 2.16 Crs. onwards
Thane West
Office BHK apartments
View Details

Godrej Exquisite

₹ 1.15 Crs. onwards
Thane West
1/2/3 BHK apartments
View Details

Kalpataru Parkcity

₹ 84.89 Lacs. onwards
Thane West
2 BHK apartments
View Details

Sheth Cnergy

₹ 1.67 Crs. onwards
Thane West
Office BHK apartments
View Details

Godrej Upavan

₹ 67.07 Lacs. onwards
Thane West
2 BHK apartments
View Details

Victoria Towers

₹ 3.59 Crs. onwards
Thane West
3/4/5 BHK apartments
View Details
Project Details
Project details were last updated in Oct 2025
  • Project:
    Tathastu
  • Location:
  • Thane West, Ghodbunder Rd, opp. Sanghvi hills, behind D-Mart, Sanghavi Hills, Kavesar
  • Const. Stage:
    Under Construction
  • Possession:
    Mar 2028
  • Parking:
    Open;Open Reserved;
  • Floors:
    36
Developer Details

Squarefeet Group

  • Developer:
    Squarefeet Group
  • Phone:
    022 66543333
  • Website:
    www.squarefeetgroup.in
  • Address:
  • Satyam Building, 2nd Floor, Opp Navpada Telephone Exchange Above Punjab National Bank, M G Road, Thane - West , 400601
Project Ratings
Project Amenities
Amenities offred in Tathastu
Project RERA Details
RERA Project Status New
Proposed Possession 30 Mar 2023
Revised Possession 01 Jan 1900
Extended Possession
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51700017002
RERA Project Name Tathastu
RERA Location Survey No 166 Hissa No 3
RERA Developer Maharashtra Developers
Architect Arc Designers
Project RERA Details
Project Type Residential / Group Housing
Funding Bank INDIAN OVERSEAS BANK
Last Modified 28 Jun 2018
Last Retrived 26 Jul 2025

Most active Channel Partners, Real Estate Agents in Thane West

Facilities & Amenities
Facilities, Amenities & Common areas details of Tathastulast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking
As Per Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
-
Solid Waste Management And Disposal
Na
Storm Water Drains
-
Street Lighting
Existing
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply100% completed
95% Complete
Borewell
Buildings / Wings in Tathastu
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tathastuby Squarefeet Grouplast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer

29170 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

144 apartments in total
Total
144
Booked
0
Available
144

Saleable Area Statistics (Sq. ft.)

39808 Total
Total
39808
Booked
0
Available
39808
Total 144 apartments in project. 0 apartments booked. 0% apartments booked.
Total 3698.27 saleable area. 0 apartments booked.
0% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.71 Sq.mts. ( 255 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.26 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK28.72 Sq.mts. ( 309 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK29.1 Sq.mts. ( 313 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK37.71 Sq.mts. ( 406 Sq.ft. )4
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Excavation
work-in-progress50% done
50% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.89 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.38 Sq.mts. ( 273 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.46 Sq.mts. ( 274 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK29.13 Sq.mts. ( 314 Sq.ft. )4
None Booked0% Booked
0% Booked
1RK15.34 Sq.mts. ( 165 Sq.ft. )4
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Excavation
work-in-progress50% done
50% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.89 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.25 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK28.75 Sq.mts. ( 309 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.71 Sq.mts. ( 331 Sq.ft. )4
None Booked0% Booked
0% Booked
1 RK15.34 Sq.mts. ( 165 Sq.ft. )4
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.48 Sq.mts. ( 242 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK22.72 Sq.mts. ( 245 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.55 Sq.mts. ( 253 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK23.81 Sq.mts. ( 256 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.74 Sq.mts. ( 266 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK25.25 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK30.71 Sq.mts. ( 331 Sq.ft. )4
None Booked0% Booked
0% Booked
19 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.49 Sq.mts. ( 253 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.03 Sq.mts. ( 259 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK30.39 Sq.mts. ( 327 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
19 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.59 Sq.mts. ( 254 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing GMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.59 Sq.mts. ( 254 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing GCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing HMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.33 Sq.mts. ( 251 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.93 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )4
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing HCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Project Consultants
Channel Partners Registered by Developer
Squarefeet Group
for Project
Tathastu
last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Squarefeet Group

Squarefeet Group Trace our history & it will take you back to 1962. When a team of visionaries led by Shri. C.N. Mirani formed a construction company called Jyoti Land Agency. The goal of the company was to provide good quality affordable houses on a mass scale primarily in Thane. Later, some of the key people from Jyoti Land Agency along with a few highly established names from diverse streams decided to form a company that would dedicate itself to bringing high quality houses to the masses. They believed it was possible to offer luxury at reasonable prices & since it was all about offering people "quality space" in life, they named the company Squarefeet. The present day Squarefeet Group is an offshoot of Jyoti Land Agency & ever since its inception, it has been acknowledged as one of the most reputed & trustworthy developer in the construction industry. The Group is primarily associated with development, construction & execution of a large scale, ultra- modern & a very distinguished housing & commercial complexes in and around Thane.