Crystal Spires Project at Thane West by Soham Builders Ltd. (P51700009216)
  • Rating: 4.9
  • (23)

Crystal Spires - Thane West

Soham Builders Ltd.
Project Details, Configuration & Prices
2 BHK-1230 Sq.ft.
₹Call for Price
2½ BHK-1510 Sq.ft.
₹Call for Price
3 BHK-1970 Sq.ft.
₹Call for Price
3 BHK-2215 Sq.ft.
₹Call for Price
Project overview
Crystal Spires Project at Thane West by Soham Builders Ltd. (P51700009216) a Sold Out Project with 2/2½/3 BHK apartments / Flats starting from ₹ 1.5 Crs onwards

Crystal Spires is one of the project developed by Soham Builders Pvt.Ltd. and enjoys an exclusive surrounding.
Crystal Spires QR Code
Crystal Spires
MahaRERA - P51700009216

Godrej Emerald

₹ 1.05 Crs. onwards
Thane West
1½/2/3 BHK apartments
View Details

Kalpataru Paramount

₹ 99 Lacs. onwards
Thane West
2 BHK apartments
View Details

Orovia-Commercials

₹ 2.16 Crs. onwards
Thane West
Office BHK apartments
View Details

Godrej Exquisite

₹ 1.15 Crs. onwards
Thane West
1/2/3 BHK apartments
View Details

Kalpataru Parkcity

₹ 84.89 Lacs. onwards
Thane West
2 BHK apartments
View Details

Sheth Cnergy

₹ 1.67 Crs. onwards
Thane West
Office BHK apartments
View Details

Godrej Upavan

₹ 67.07 Lacs. onwards
Thane West
2 BHK apartments
View Details

Victoria Towers

₹ 3.59 Crs. onwards
Thane West
3/4/5 BHK apartments
View Details
Project Details
Project details were last updated in Oct 2025
  • Project:
    Crystal Spires
  • Location:
  • Thane West, Soham Gardens, Manpada Junction
  • Const. Stage:
    Sold Out
  • Possession:
    Jul 2020
  • Floors:
    27
Developer Details

Soham Builders Ltd.

  • Developer:
    Soham Builders Ltd.
  • Phone:
    022 25981000
  • Website:
    www.sohamrealestate.com
  • Address:
  • Soham House, Hari Om Nagar, Off.E.E.Highway, Mulund East, Mumbai - 400 081
Project Ratings
Project Amenities
Amenities offred in Crystal Spires
LIFESTYLE AMENITIES
Grand entrance lobbyKid's play areaClub HouseGymnasiumIndoor GamesHigh speed elevatorsSwimming PoolGymnasiumLandscaped gardenOutdoor GamesPOP finished wallsGranite PlatformModular Kitchen
Project RERA Details
RERA Project Status Ongoing
Proposed Possession 31 Jan 2021
Revised Possession 31 Jan 2021
Extended Possession 30 Jun 2023
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51700009216
RERA Project Name Crystal Spires
RERA Location 68/1 Part, 68/3A Part, 59/A/30/2/3 Part
RERA Developer Luxora Realtors Private Limited
Architect Arch Shashikant Deshmukh
Project RERA Details
Project Type Residential / Group Housing
Funding Bank IDFC First Bank Ltd
Last Modified 09 Sep 2021
Last Retrived 26 Jul 2025

Most active Channel Partners, Real Estate Agents in Thane West

Facilities & Amenities
Facilities, Amenities & Common areas details of Crystal Spireslast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
2537 Sq Mtr Of Rg As Per Municipal Approved Plan
Community Buildings100% completed
95% Complete
Club House On Podium Top
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Meter Room &Amp; Sub Station (Sub Stn Constructed)
Energy management100% completed
95% Complete
Solar Water Heater
Fire Protection And Fire Safety Requirements100% completed
95% Complete
In Common Areas As Per Cfo Guidelines
GYM100% completed
95% Complete
In Clubhouse
Landscaping & Tree Planting100% completed
95% Complete
In Rg Area
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
U/G Drain Line To Be Connected To Municipal Sewer
Solid Waste Management And Disposal100% completed
95% Complete
Ok
Storm Water Drains100% completed
95% Complete
As Per Municipal Guidelines
Street Lighting100% completed
95% Complete
Common Areas
SWIMMING POOL100% completed
95% Complete
Above Podium
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Through Stp Plant
Water Conservation, Rain water Harvesting100% completed
95% Complete
Rwh System
Water Supply100% completed
95% Complete
Municipal Water Plus Borewell
Buildings / Wings in Crystal Spires
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Crystal Spiresby Soham Builders Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer

78577 Sq. ft.

Project Area

27308 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

191 apartments in total
Total
191
Booked
191
Available
0

Saleable Area Statistics (Sq. ft.)

218426 Total
Total
218426
Booked
218426
Available
0
Total 191 apartments in project. 191 apartments booked. 100% apartments booked.
Total 20292.3 saleable area. 20292.3 apartments booked.
100% area booked.

T4 Crystal Spires 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
T4 Crystal Spires 2Jul 20202611120162
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.87 Sq.mts. ( 408 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK37.95 Sq.mts. ( 408 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK36.3 Sq.mts. ( 391 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK36.62 Sq.mts. ( 394 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK72.12 Sq.mts. ( 776 Sq.ft. )14
14 Booked100% Booked
100% Booked
2 BHK73.26 Sq.mts. ( 789 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK73.35 Sq.mts. ( 790 Sq.ft. )14
14 Booked100% Booked
100% Booked
2.5 BHK80.93 Sq.mts. ( 871 Sq.ft. )14
14 Booked100% Booked
100% Booked
2.5 BHK82.38 Sq.mts. ( 887 Sq.ft. )17
17 Booked100% Booked
100% Booked
4 BHK127.96 Sq.mts. ( 1377 Sq.ft. )3
3 Booked100% Booked
100% Booked
4 BHK128.62 Sq.mts. ( 1384 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK173.17 Sq.mts. ( 1864 Sq.ft. )14
14 Booked100% Booked
100% Booked
4 BHK173.2 Sq.mts. ( 1864 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio36.93 Sq.mts. ( 398 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio22.66 Sq.mts. ( 244 Sq.ft. )1
1 Booked100% Booked
100% Booked
Studio33.37 Sq.mts. ( 359 Sq.ft. )2
2 Booked100% Booked
100% Booked
89 total apartments / 89 apartments booked. 100% apartments booked.
Work Description in Building T4 Crystal Spires 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

T5 Crystal Spires 1 From 19Th To 25Th Floors

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
T5 Crystal Spires 1 From 19Th To 25Th FloorsJul 202070000056
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK106.46 Sq.mts. ( 1146 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK110.74 Sq.mts. ( 1192 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK125.32 Sq.mts. ( 1349 Sq.ft. )14
14 Booked100% Booked
100% Booked
28 total apartments / 28 apartments booked. 100% apartments booked.
Work Description in Building T5 Crystal Spires 1 From 19Th To 25Th FloorsCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress60% done
60% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

T5 Crystal Spires 1 Upto 18Th Floors

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
T5 Crystal Spires 1 Upto 18Th FloorsJul 20201911120140
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK106.37 Sq.mts. ( 1145 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK106.46 Sq.mts. ( 1146 Sq.ft. )17
17 Booked100% Booked
100% Booked
3 BHK106.56 Sq.mts. ( 1147 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK110.64 Sq.mts. ( 1191 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK110.74 Sq.mts. ( 1192 Sq.ft. )18
18 Booked100% Booked
100% Booked
3 BHK125.32 Sq.mts. ( 1349 Sq.ft. )34
34 Booked100% Booked
100% Booked
DUPLEX227.42 Sq.mts. ( 2448 Sq.ft. )2
2 Booked100% Booked
100% Booked
74 total apartments / 74 apartments booked. 100% apartments booked.
Work Description in Building T5 Crystal Spires 1 Upto 18Th FloorsCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Project Consultants
Channel Partners Registered by Developer
Soham Builders Ltd.
for Project
Crystal Spires
last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Soham Builders Ltd.

Soham Builders Ltd. The Soham, founded in 1981, is based in Mumbai’s fastest growing satellite city -Thane. With operations that encompass all aspects of the real estate industry, from land acquisition, planning, execution and marketing through to development management; the Soham Group holds a commanding position in today’s competitive market. Showcasing a myriad of landmark projects expertly executed resulting in nearly 4 million sq ft. developed and over 4500 families housed, via almost 60 projects; each one being synonymous with product innovation and cutting edge design.