Shri Upendra Nagar CHS Project at Dahisar East by Ssakash Developers (P51800013142)
  • Rating: 4.9
  • (21)

Shri Upendra Nagar CHS - Dahisar East

Ssakash Developers
Project Details, Configuration & Prices (Exclusive of Stamp Duty Charges, GST Charges, Registration Charges & Maintenance Charges)
Project overview
Shri Upendra Nagar CHS Project at Dahisar East by Ssakash Developers (P51800013142) a Sold Out Project with 2/3 BHK apartments / Flats starting from ₹ 0 onwards

Shri Upendra Nagar CHS is a project that brings to you homes with excellent location advantages blended with warmth and comfort. It has a beautiful surrounding.
Shri Upendra Nagar CHS QR Code
Shri Upendra Nagar CHS
MahaRERA - P51800013142

Ornate Solitaire

₹ 1.41 Crs. onwards
Dahisar East
Office BHK apartments
View Details

Northern Hills

₹ 1.74 Crs. onwards
Dahisar East
2 BHK apartments
View Details
Dahisar East
Office BHK apartments
View Details

Eminente

₹ 81 Lacs. onwards
Dahisar East
1 BHK apartments
View Details

Rang Rekha

₹ 97.9 Lacs. onwards
Dahisar East
1/2/3 BHK apartments
View Details

Muktangan Residency

₹ 1.05 Crs. onwards
Dahisar East
1/1½/2 BHK apartments
View Details

Dynamix Avanya

₹ 1.02 Crs. onwards
Dahisar East
1/2 BHK apartments
View Details

Celestial Living

₹ 65 Lacs. onwards
Dahisar East
1/2 BHK apartments
View Details
Project Details
Project details were last updated in Oct 2025
  • Project:
    Shri Upendra Nagar CHS
  • Location:
  • Dahisar East, V.T. Road,Y. R. Tawde Road.
  • Const. Stage:
    Sold Out
  • Possession:
    Dec 2018
  • Parking:
    Open;
  • Floors:
    22
Developer Details

Ssakash Developers

  • Developer:
    Ssakash Developers
  • Phone:
    022 28963926
  • Website:
    www.ssakashdevelopers.com
  • Address:
  • 101,Om Jagdish chsl. Devidas Lane. Borivali(W),Mumbai-400103, Maharshtra.
Project Ratings
Project Amenities
Amenities offred in Shri Upendra Nagar CHS
LIFESTYLE AMENITIES
Landscaped gardenClub HouseGymnasiumSwimming PoolHigh speed elevatorsPower BackupKid's play areaPOP finished wallsVitrified flooringVideo Door PhonesGranite PlatformIntercom/CCTV
Project RERA Details
RERA Project Status Ongoing
Proposed Possession 30 Dec 2026
Revised Possession 30 Dec 2026
Extended Possession
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51800013142
RERA Project Name Shri Upendra Chsl
RERA Location 974
RERA Developer Harshal Enterprises
Architect Space Vision
Project RERA Details
Project Type Residential / Group Housing
Funding Bank HDFC BANK
Last Modified 07 Feb 2023
Last Retrived 26 Jul 2025

Most active Channel Partners, Real Estate Agents in Dahisar East

Facilities & Amenities
Facilities, Amenities & Common areas details of Shri Upendra Nagar CHSlast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Work Not Yet Started
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Work Not Yet Started
Energy management
Na
Fire Protection And Fire Safety Requirements
Work Not Yet Started
Internal Roads & Footpaths
Na
Landscaping & Tree Planting
Work Not Yet Started
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Work Not Yet Started
Solid Waste Management And Disposal
Work Not Yet Started
Storm Water Drains
Work Not Yet Started
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Work Not Yet Started
Water Supply
Work Not Yet Started
Buildings / Wings in Shri Upendra Nagar CHS
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shri Upendra Nagar CHSby Ssakash Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer

50950 Sq. ft.

Project Area

7643 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

228 apartments in total
Total
228
Booked
197
Available
31

Saleable Area Statistics (Sq. ft.)

132186 Total
Total
132186
Booked
114150
Available
18036
Total 228 apartments in project. 197 apartments booked. 86% apartments booked.
Total 12280.39 saleable area. 10604.76 apartments booked.
86% area booked.

A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
ADec 202619101029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK50.17 Sq.mts. ( 540 Sq.ft. )19
19 Booked100% Booked
100% Booked
2 BHK53.42 Sq.mts. ( 575 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK53.44 Sq.mts. ( 575 Sq.ft. )37
36 Booked97% Booked
97% Booked
2 BHK57.13 Sq.mts. ( 615 Sq.ft. )16
16 Booked100% Booked
100% Booked
76 total apartments / 75 apartments booked. 98% apartments booked.
Work Description in Building ACompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress95% done
95% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BDec 202619101029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK39.02 Sq.mts. ( 420 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )22
18 Booked81% Booked
81% Booked
2 BHK50.14 Sq.mts. ( 540 Sq.ft. )10
8 Booked80% Booked
80% Booked
2 BHK50.31 Sq.mts. ( 542 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK53.44 Sq.mts. ( 575 Sq.ft. )10
8 Booked80% Booked
80% Booked
2 BHK57.13 Sq.mts. ( 615 Sq.ft. )5
5 Booked100% Booked
100% Booked
2 BHK58.05 Sq.mts. ( 625 Sq.ft. )10
10 Booked100% Booked
100% Booked
2 BHK58.66 Sq.mts. ( 631 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK59.47 Sq.mts. ( 640 Sq.ft. )11
11 Booked100% Booked
100% Booked
2 BHK60.5 Sq.mts. ( 651 Sq.ft. )5
5 Booked100% Booked
100% Booked
76 total apartments / 68 apartments booked. 89% apartments booked.
Work Description in Building BCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
CDec 2026121010111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK41.71 Sq.mts. ( 449 Sq.ft. )19
13 Booked68% Booked
68% Booked
2 BHK47.4 Sq.mts. ( 510 Sq.ft. )8
7 Booked87% Booked
87% Booked
2 BHK51.1 Sq.mts. ( 550 Sq.ft. )24
16 Booked66% Booked
66% Booked
2 BHK52.27 Sq.mts. ( 563 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK59.06 Sq.mts. ( 636 Sq.ft. )5
5 Booked100% Booked
100% Booked
3 BHK69.66 Sq.mts. ( 750 Sq.ft. )2
1 Booked50% Booked
50% Booked
3 BHK70.43 Sq.mts. ( 758 Sq.ft. )4
3 Booked75% Booked
75% Booked
3 BHK73.64 Sq.mts. ( 793 Sq.ft. )13
8 Booked61% Booked
61% Booked
76 total apartments / 54 apartments booked. 71% apartments booked.
Work Description in Building CCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress40% done
40% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress40% done
40% Booked
Project Consultants
Channel Partners Registered by Developer
Ssakash Developers
for Project
Shri Upendra Chsl
last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Ssakash Developers

Ssakash Developers Ssakash is an established group in the field of Construction since last more than a decade. Several completed construction projects at Vile Parle, Andheri area are to our credit. Quality construction is our hallmark. We shifted our base from Vile Parle to Borivali about 6 years ago due to diversification into redevelopment business. The Directors of the group are young enough to be receptive to modern construction trends & understand the life style of the present generation. The board comprises of technically qualified & financially sound people.