Project overview
Rizvi Utopia Project at Santacruz East by Rizvi Builders (P51800012249) a Sold Out Project with 2/3 BHK apartments / Flats starting from ₹ 2.35 Crs onwards

Rizvi Utopia is a premium project in Kalina-Santacruz (East). It vouches to provide you with an extremely benign regulatory environment for property ownership. Strategically located, this sophisticated enclave is at a distance of merely 5 minutes from BKC and surrounded by exceptional access to transportation links and infrastructure. UTOPIA is a part of a 12 acre development with all the luxuries, amenities and high standards a person would expect in an extensive Grade A premium development. Comprising of well designed 2 and 3 Bedroom Hall Kitchen apartments with an international standard fit and finish. It boasts of an aesthetically pleasing landscape consisting of a Swimming pool, Fitness centre and a Club House. Keeping up with the Rizvi Builders tradition, the apartments are offered along with free car parking facility and club membership to all its discerning buyers.
Rizvi Utopia QR Code
Rizvi Utopia
MahaRERA - P51800012249

Crescent Nexus Phase 2

₹ 1.34 Crs. onwards
Santacruz East
1/2 BHK apartments
View Details

Sanghvi Edge

₹ 81.2 Lacs. onwards
Santacruz East
1/2 BHK apartments
View Details

Alora

₹ 2.77 Crs. onwards
Santacruz East
2 BHK apartments
View Details

127 Upper East

₹ 6.43 Crs. onwards
Santacruz East
4 BHK apartments
View Details

Crescent Nexus Phase 1

₹ 1.94 Crs. onwards
Santacruz East
2 BHK apartments
View Details

Courtyard Maple

₹ 2.83 Crs. onwards
Santacruz East
2/3 BHK apartments
View Details

Prabhat Residency

₹ 1.49 Crs. onwards
Santacruz East
1 BHK apartments
View Details

Pratham

₹ 4.25 Crs. onwards
Santacruz East
3 BHK apartments
View Details
Project Details
Project details were last updated in Nov 2025
  • Project:
    Rizvi Utopia
  • Location:
  • Santacruz East, New Kalina, Behind Kalina Church
  • Const. Stage:
    Sold Out
  • Possession:
    Dec 2020
  • Floors:
    9
Developer Details

Rizvi Builders

  • Developer:
    Rizvi Builders
  • Phone:
    022 26426767
  • Website:
    www.rizvi.com
  • Address:
  • Rizvi House, 1st Floor, Junction of Hill Road & St. Martin Road, Bandra, Mumbai-400050. India
Project Ratings
Project Amenities
Amenities offred in Rizvi Utopia
LIFESTYLE AMENITIES
Grand entrance lobbyHigh speed elevatorsLandscaped gardenKid's play areaPower BackupGymnasiumSwimming PoolClub HousePOP finished wallsIntercom/CCTVVitrified flooringImported Sanitary FittingsGranite Platform
Project RERA Details
RERA Project Status Ongoing
Proposed Possession 30 Jun 2021
Revised Possession 30 Jun 2021
Extended Possession 31 Dec 2024
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51800012249
RERA Project Name Rizvi Utopia
RERA Location 7379A, 7381, 6421 To 6423, 6427, 7375, 6429A, 7364, 7374, 7377, 7376A, 6424 A To C, 7370, 7382, 6426
RERA Developer Rizvi Estates & Hotels Pvt Ltd
Architect M/S Essar Group
Project RERA Details
Project Type Others
Funding Bank
Last Modified 27 Mar 2023
Last Retrived 26 Jul 2025

Most active Channel Partners, Real Estate Agents in Santacruz East

Facilities & Amenities
Facilities, Amenities & Common areas details of Rizvi Utopialast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Club House35% completed
35% Complete
Amenities Will Be Provided As Per Approval Plans
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station55% completed
55% Complete
To Be Meet As Per Requirement
Energy management
As Per Igbc Requirements
Fire Protection And Fire Safety Requirements67% completed
67% Complete
As Per Cfo Requirement Shall Be Provided
Landscaping & Tree Planting35% completed
35% Complete
Provided As Per Landscape Design
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)55% completed
55% Complete
Stp Is Proposed
Solid Waste Management And Disposal
Provided As Per Requirements
Storm Water Drains40% completed
40% Complete
Strom Water Drain Lane Provided As Per Requirement
Street Lighting
Will Be Provided As Per Remark
Treatment And Disposal Of Sewage And Sullage Water
Stp Is Proposed
Water Conservation, Rain water Harvesting67% completed
67% Complete
Provided As Per Requirements
Water Supply67% completed
67% Complete
Will Be Given By Bmc After Oc
Buildings / Wings in Rizvi Utopia
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Rizvi Utopiaby Rizvi Builderslast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer

49675 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

102 apartments in total
Total
102
Booked
91
Available
11

Saleable Area Statistics (Sq. ft.)

82421 Total
Total
82421
Booked
74759
Available
7662
Total 102 apartments in project. 91 apartments booked. 89% apartments booked.
Total 7657.09 saleable area. 6945.25 apartments booked.
91% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJun 2021101101038
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK62.59 Sq.mts. ( 674 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK62.71 Sq.mts. ( 675 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK66.39 Sq.mts. ( 715 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK66.52 Sq.mts. ( 716 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK72.42 Sq.mts. ( 780 Sq.ft. )9
9 Booked100% Booked
100% Booked
3 BHK93.47 Sq.mts. ( 1006 Sq.ft. )8
8 Booked100% Booked
100% Booked
3 BHK113.5 Sq.mts. ( 1222 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 119.23 Sq.mts. ( 207 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 215.79 Sq.mts. ( 170 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 319.32 Sq.mts. ( 208 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 415.7 Sq.mts. ( 169 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop 59.75 Sq.mts. ( 105 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop 612.08 Sq.mts. ( 130 Sq.ft. )1
1 Booked100% Booked
100% Booked
41 total apartments / 37 apartments booked. 90% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJun 202110110100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK43.2 Sq.mts. ( 465 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK73.02 Sq.mts. ( 786 Sq.ft. )9
9 Booked100% Booked
100% Booked
2 BHK74.88 Sq.mts. ( 806 Sq.ft. )9
9 Booked100% Booked
100% Booked
3 BHK94.3 Sq.mts. ( 1015 Sq.ft. )9
8 Booked88% Booked
88% Booked
3 BHK96.15 Sq.mts. ( 1035 Sq.ft. )8
8 Booked100% Booked
100% Booked
36 total apartments / 35 apartments booked. 97% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 202210110100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK71.53 Sq.mts. ( 770 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK72.19 Sq.mts. ( 777 Sq.ft. )11
7 Booked63% Booked
63% Booked
2 BHK76.74 Sq.mts. ( 826 Sq.ft. )6
5 Booked83% Booked
83% Booked
3 BHK91.32 Sq.mts. ( 983 Sq.ft. )7
6 Booked85% Booked
85% Booked
25 total apartments / 19 apartments booked. 76% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
work-in-progress90% done
90% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress85% done
85% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress75% done
75% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress75% done
75% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress85% done
85% Booked
Plinth
work-in-progress90% done
90% Booked
Podiums (if any)
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress85% done
85% Booked
Sanitary Fittings within the flats / premises
work-in-progress85% done
85% Booked
Slabs of Super Structure
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress85% done
85% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress85% done
85% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress85% done
85% Booked
X number of Basement(s) and Plinth
work-in-progress90% done
90% Booked
X number of Podiums
work-in-progress80% done
80% Booked
X number of Slabs of Super Structure
work-in-progress90% done
90% Booked
Project Consultants
Channel Partners Registered by Developer
Rizvi Builders
for Project
Rizvi Utopia
last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Rizvi Builders

Rizvi Builders Rizvi Group began its foray in the field of business in the year 1975 with focus on the real estate development in Mumbai.In a short span of time Rizvi Builders the flagship brand’s real estate activities established strongly, with a reputation synonymous with quality construction and timely deliveries. After having being rooted in the grounds of construction for 40 years, Rizvi Builders is now a formidable brand in real estate and is undoubtedly considered one of the larger players in the business. Having constructed over 200 commercial and residential projects in Mumbai and Goa, Rizvi has an enviable landbank with several large projects in progress and many on the drawing boards. With underdeveloped land in Goa, Lonavala, Pune, and prime locations of Mumbai like Bandra, Juhu, Santacruz, Mahim, Malad, Kandivali as well as in Tardeo; Rizvi is poised for further dynamic growth in the next few years.