Akshar River Gate Project at New Panvel by Akshar Developers (P52000032008)
  • Rating: 5.0
  • (273)

Akshar River Gate - New Panvel

Akshar Developers
Project Details, Configuration & Prices
1 BHK264 Sq.ft. Carpet ₹ 29 Lacs ++
1 BHK400 Sq.ft. Carpet ₹ 43.93 Lacs ++
2 BHK490 Sq.ft. Carpet ₹ 53.82 Lacs ++
2 BHK515 Sq.ft. Carpet ₹ 56.57 Lacs ++
Project overview
Akshar River Gate Project at New Panvel by Akshar Developers (P52000032008) is a Ready Possession Project with 1/2 BHK apartments / Flats starting from ₹ 29.04 Lakh onwards

Akshar River gate is a residential project by Akshare Developers. It is located at New Panvel. 20 min to Panvel Railway Station and 15 min to Mumbai-Pune Expressway. Close to all major transport hubs, school colleges, hospitals, hotels and bank. It is a 16 Acre Township has 29 towers of 7 storey each. Riverside location. Has all modern amenities, with river facing clubhouse, High-tech gym, business centre and many more. It is a RERA approved project.
Akshar River Gate QR Code
Akshar River Gate
MahaRERA - P52000032008

Hiranandani Fortune City

₹ 83.43 Lacs. onwards
New Panvel
2/3/4 BHK apartments
View Details

Wadhwa Wise City

₹ 49 Lacs. onwards
New Panvel
1/2/3 BHK apartments
View Details

Suncity

₹ 26.47 Lacs. onwards
New Panvel
1/2 BHK apartments
View Details

Rainbow County Defence Enclave

₹ 68 Lacs. onwards
New Panvel
2/3 BHK apartments
View Details

Saubhagyam

₹ 48.83 Lacs. onwards
New Panvel
1/2 BHK apartments
View Details
New Panvel
2/3 BHK apartments
View Details

Arihant Aspire - Galenia

₹ 52 Lacs. onwards
New Panvel
1/1 RK/2/3 BHK apartments
View Details

Sai World City - Phase I

₹ 1.5 Crs. onwards
New Panvel
2/3 BHK apartments
View Details
Project Details
Project details were last updated in Dec 2025
  • Project:
    Akshar River Gate
  • Location:
  • New Panvel, Chavne, Panvel
  • Const. Stage:
    Ready Possession
  • Possession:
    Dec 2025
  • Parking:
    Open Reserved
  • Floors:
    7
Developer Details

Akshar Developers

  • Developer:
    Akshar Developers
  • Phone:
    7666688788
  • Website:
    www.akshardevelopers.com
  • Address:
  • 225, 2nd Floor, Big Splash, Plot No.78 & 79, Sector 17, Vashi, Navi Mumbai - 400 705.
Project Ratings
Project Amenities
Amenities offred in Akshar River Gate
LIFESTYLE AMENITIES
Swimming PoolClub HouseGymnasiumGrand entrance lobbyHigh speed elevatorsJogging TrackLandscaped gardenKid's play areaIndoor GamesOutdoor GamesPower BackupVitrified flooringImported Sanitary FittingsPOP finished wallsIntercom/CCTVGranite Platform
Project RERA Details
RERA Project Status New
Proposed Possession 31 Dec 2025
Revised Possession 01 Jan 1900
Extended Possession
Litigations No Litigations
Project RERA Details
MAHA RERA No: P52000032008
RERA Project Name Akshar Rivergate Plot B
RERA Location Gut No 100/1/7, Chavane, Taluka Panvel
RERA Developer Emperia Realty
Architect Destination Architecture Interior Designs
Project RERA Details
Project Type Residential / Group Housing
Funding Bank IDBI BANK
Last Modified 03 Dec 2021
Last Retrived 28 Jul 2025

Most active Channel Partners, Real Estate Agents in New Panvel

Facilities & Amenities
Facilities, Amenities & Common areas details of Akshar River Gatelast updated on 28 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Not Commenced
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Not Commenced
Energy management
Na
Fire Protection And Fire Safety Requirements
Not Commenced
Landscaping & Tree Planting
Not Commenced
Open Parking
Not Commenced
Sewerage (Chamber, Lines, Septic Tank , STP)
Not Commenced
Solid Waste Management And Disposal
Not Commenced
Storm Water Drains
Not Commenced
Street Lighting
Not Commenced
Treatment And Disposal Of Sewage And Sullage Water
Not Commenced
Water Conservation, Rain water Harvesting
Not Commenced
Water Supply
Not Commenced
Buildings / Wings in Akshar River Gate
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Akshar River Gateby Akshar Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA. Disclaimer

62108 Sq. ft.

Project Area

248 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

204 apartments in total
Total
204
Booked
0
Available
204

Saleable Area Statistics (Sq. ft.)

73121 Total
Total
73121
Booked
0
Available
73121
Total 204 apartments in project. 0 apartments booked. 0% apartments booked.
Total 6793.134 saleable area. 0 apartments booked.
0% area booked.

B1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B1Dec 20258100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.446 Sq.mts. ( 317 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK31.84 Sq.mts. ( 343 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK32.178 Sq.mts. ( 346 Sq.ft. )14
None Booked0% Booked
0% Booked
2 BHK42.908 Sq.mts. ( 462 Sq.ft. )14
None Booked0% Booked
0% Booked
2 BHK45.662 Sq.mts. ( 492 Sq.ft. )7
None Booked0% Booked
0% Booked
49 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building B1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress50% done
50% Booked
Stilt Floor
Completed 100% done
100% Booked

B2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B2Dec 20258100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.367 Sq.mts. ( 316 Sq.ft. )14
None Booked0% Booked
0% Booked
1 BHK29.493 Sq.mts. ( 317 Sq.ft. )28
None Booked0% Booked
0% Booked
2 BHK42.908 Sq.mts. ( 462 Sq.ft. )14
None Booked0% Booked
0% Booked
56 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building B2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

B3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B3Dec 20258100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.446 Sq.mts. ( 317 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK31.178 Sq.mts. ( 336 Sq.ft. )14
None Booked0% Booked
0% Booked
1 BHK31.84 Sq.mts. ( 343 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK42.908 Sq.mts. ( 462 Sq.ft. )14
None Booked0% Booked
0% Booked
2 BHK45.662 Sq.mts. ( 492 Sq.ft. )7
None Booked0% Booked
0% Booked
49 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building B3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress50% done
50% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

B4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B4Dec 20256100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.367 Sq.mts. ( 316 Sq.ft. )20
None Booked0% Booked
0% Booked
1 BHK31.84 Sq.mts. ( 343 Sq.ft. )10
None Booked0% Booked
0% Booked
1RK23.203 Sq.mts. ( 250 Sq.ft. )20
None Booked0% Booked
0% Booked
50 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building B4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress60% done
60% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
Project Consultants
Channel Partners Registered by Developer
Akshar Developers
for Project
Akshar Rivergate Plot B
last updated on 28 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Akshar Developers

Akshar Developers Akshar Group is a trusted name in the Real Estate Industry that has successfully developed diverse residential, commercial and retail projects across the cities of Navi Mumbai, Pune and Ahmedabad. With 22 completed, 7 ongoing and many upcoming projects the kite of Akshar Developers is flying high on Navi Mumbai and Pune Real Estate Scene. We firmly believe on constructing keystones which inspires life in every way. With extended portfolio ongoing and completed projects at Pune & Ahmedabad; Akshar Group has broaden its horizon and will continue to do so.