34 Park Estate Project at Goregaon West by Chandak Group (P51800006729)
  • Rating: 4.1
  • (24)

34 Park Estate - Goregaon West

Chandak Group
Project Details, Configuration & Prices
1 BHK391 Sq.ft. Carpet ₹ 1.25 Cr ++
2 BHK498 Sq.ft. Carpet ₹ 1.60 Cr ++- sold out
2 BHK605 Sq.ft. Carpet ₹ 1.94 Cr ++-sold out
3 BHK820 Sq.ft. Carpet ₹ 2.70 Cr ++
3 BHK846 Sq.ft. Carpet ₹ 2.80 Cr ++
Project overview
34 Park Estate Project at Goregaon West by Chandak Group (P51800006729) is a RERA approved Under Construction Project with RERA ID P51800006729 slated to be ready for possession by Dec 2026 with 1/2/3 BHK apartments / Flats starting from ₹ 1.25 Crs onwards

34 Park Estate is a Residential Project Developed by the Chandak Group. it is located at Goregaon West. Goregaon West is well-connected to other parts of Mumbai through local train services on the Western Line. 5 minutes drive to Goregaon Station and 2 minutes drive to S.V Road. Link Road & Link Road METRO 1.5 km - 8 mins Drive. Western Express Highway and Mrinal Tai Gore Flyover connecting to Western Express Highway takes are also in close proximity. Educational institutes, healthcare, malls, entertainment etc are easily accessible. G +2 Parking+ Amenities floor (E-deck level)+ 36 storey tower with rooftop amenities. It offers 1,2 and 3 BHK Residences. Planned Layout for Cross Ventilation. Ample Sunlight and well Ventilated Homes. A plethora of 34+ Luxury and Lifestyle amenities. Builder possession by June 2024.
34 Park Estate QR Code
34 Park Estate
MahaRERA - P51800006729

Kalpataru Radiance

₹ 3.79 Crs. onwards
Goregaon West
2/3 BHK apartments
View Details

Ekta Tripolis

₹ 3.86 Crs. onwards
Goregaon West
2½/3 BHK apartments
View Details

DGS Sheetal Kiara

₹ 99 Lacs. onwards
Goregaon West
1/2 BHK apartments
View Details

H. Rishabraj Jakalyan Society

₹ 2.27 Crs. onwards
Goregaon West
2/3 BHK apartments
View Details

Sanghvi Crystal

₹ 1.25 Crs. onwards
Goregaon West
1/2/3 BHK apartments
View Details

Riviera

₹ 1.08 Crs. onwards
Goregaon West
1/2 BHK apartments
View Details

H Rishabhraj Opulence

₹ 1.03 Crs. onwards
Goregaon West
1/2 BHK apartments
View Details

37 Avenue

₹ 1.6 Crs. onwards
Goregaon West
2/4 BHK apartments
View Details
Project Details
Project details were last updated in Oct 2025
  • Project:
    34 Park Estate
  • Location:
  • Goregaon West, Yashwant Nagar
  • Const. Stage:
    Under Construction
  • Possession:
    Dec 2026
  • Floors:
    36
Developer Details

Chandak Group

  • Developer:
    Chandak Group
  • Phone:
    022 26843911
  • Website:
    www.chandakgroup.com
  • Address:
  • Hubtown Solaris ,807/808, 8th floor N.S.phadke marg, opp Telli gully,Near Regency Hotel, Andheri East Mumbai 400069
Project Ratings
Project Brochures
Brochures of 34 Park Estateby Chandak Group
Project Brochures
  • MPE/Brochures/28638/34 Park Brochure.pdf
Project Amenities
Amenities offred in 34 Park Estate
LIFESTYLE AMENITIES
Outdoor GamesIndoor GamesKid's play areaJogging TrackHigh speed elevatorsGrand entrance lobbyGymnasiumHealth ClubPOP finished wallsImported Sanitary FittingsVitrified flooringKitchen CabinetsModular KitchenGranite PlatformReception Desk
Project RERA Details
RERA Project Status Ongoing
Proposed Possession 31 Jul 2028
Revised Possession 31 Jul 2028
Extended Possession
Litigations No Litigations
Project RERA Details
MAHA RERA No: P51800006729
RERA Project Name 34 Park Estate
RERA Location 50 A Part, 55 Part, 49 Part
RERA Developer M/S Reddy Builders & Developers
Project RERA Details
Project Type Residential / Group Housing
Funding Bank ICICI BANK LIMITED
Last Modified 02 Mar 2020
Last Retrived 26 Jul 2025

Most active Channel Partners, Real Estate Agents in Goregaon West

Facilities & Amenities
Facilities, Amenities & Common areas details of 34 Park Estatelast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings35% completed
35% Complete
-
Electrical Meter Room, Sub-Station, Receiving Station35% completed
35% Complete
-
Energy management
Na
Fire Protection And Fire Safety Requirements35% completed
35% Complete
-
Landscaping & Tree Planting35% completed
35% Complete
-
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)35% completed
35% Complete
-
society office
-
Solid Waste Management And Disposal35% completed
35% Complete
-
Storm Water Drains35% completed
35% Complete
-
Street Lighting35% completed
35% Complete
-
Treatment And Disposal Of Sewage And Sullage Water35% completed
35% Complete
-
Water Conservation, Rain water Harvesting35% completed
35% Complete
-
Water Supply35% completed
35% Complete
-
Buildings / Wings in 34 Park Estate
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of 34 Park Estateby Chandak Grouplast updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer

207311 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

1285 apartments in total
Total
1285
Booked
959
Available
326

Saleable Area Statistics (Sq. ft.)

674120 Total
Total
674120
Booked
501931
Available
172189
Total 1285 apartments in project. 959 apartments booked. 74% apartments booked.
Total 62627.27 saleable area. 46630.53 apartments booked.
74% area booked.

Rehab - 4 Yet To Be Approved

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Rehab - 4 Yet To Be ApprovedJan 19000000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
SRA UNIT25 Sq.mts. ( 269 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Rehab - 4 Yet To Be ApprovedCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AJun 20264010030130
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK57.32 Sq.mts. ( 617 Sq.ft. )72
62 Booked86% Booked
86% Booked
3 BHK76.18 Sq.mts. ( 820 Sq.ft. )66
48 Booked72% Booked
72% Booked
138 total apartments / 110 apartments booked. 79% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress65% done
65% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress65% done
65% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BJun 20264010030400
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.33 Sq.mts. ( 391 Sq.ft. )379
305 Booked80% Booked
80% Booked
2 BHK45.8 Sq.mts. ( 493 Sq.ft. )62
59 Booked95% Booked
95% Booked
2 BHK55.74 Sq.mts. ( 600 Sq.ft. )36
34 Booked94% Booked
94% Booked
477 total apartments / 398 apartments booked. 83% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress65% done
65% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress65% done
65% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CJun 20264010030204
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.33 Sq.mts. ( 391 Sq.ft. )108
68 Booked62% Booked
62% Booked
2 BHK55.74 Sq.mts. ( 600 Sq.ft. )144
135 Booked93% Booked
93% Booked
252 total apartments / 203 apartments booked. 80% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress65% done
65% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress65% done
65% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DJun 20274010030216
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.32 Sq.mts. ( 391 Sq.ft. )29
22 Booked75% Booked
75% Booked
2 BHK45.9 Sq.mts. ( 494 Sq.ft. )26
24 Booked92% Booked
92% Booked
2 BHK46.26 Sq.mts. ( 498 Sq.ft. )31
29 Booked93% Booked
93% Booked
2 BHK56.11 Sq.mts. ( 604 Sq.ft. )36
35 Booked97% Booked
97% Booked
2 BHK56.2 Sq.mts. ( 605 Sq.ft. )36
35 Booked97% Booked
97% Booked
2 BHK56.86 Sq.mts. ( 612 Sq.ft. )72
70 Booked97% Booked
97% Booked
3 BHK78.59 Sq.mts. ( 846 Sq.ft. )36
33 Booked91% Booked
91% Booked
266 total apartments / 248 apartments booked. 93% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress65% done
65% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress65% done
65% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress65% done
65% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress65% done
65% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress65% done
65% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EJul 20284010010104
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK57.32 Sq.mts. ( 617 Sq.ft. )54
None Booked0% Booked
0% Booked
3 BHK76.17 Sq.mts. ( 820 Sq.ft. )50
None Booked0% Booked
0% Booked
104 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FJul 2028301010015
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.25 Sq.mts. ( 304 Sq.ft. )48
None Booked0% Booked
0% Booked
48 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Project Consultants
Channel Partners Registered by Developer
Chandak Group
for Project
34 Park Estate
last updated on 26 Jul 2025 as per information obtained from MARA RERA. Disclaimer
Name Company Location Mobile Designation

About Chandak Group

Chandak Group Three decades have seen Chandak Group steadily grow in size and stature. Building resources, disbursing technologies, implementing processes. To deliver residential as well as commercial projects that speak of quality and excellence within the promised timelines. This has helped Chandak win the customer's trust and emerge as a developer of repute.Today, Chandak Group has developed over 2 million sq.ft, with another 2.5 million sq.ft. under development across the length and breadth of Mumbai.