Project overview

Yes Central Galleria 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700049599. Yes Central Galleria 1 is located at Survey No 69/1. This is a New being developed by Yes Enterprises.

Yes Central Galleria 1 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 445 to 645 Sq.ft. Carpet. The Project has total 120 of which 77 are currently available for sale.

Yes Central Galleria 1 is being developed on a total land area of 35414 Sq.ft. Yes Central Galleria 1 has 5 Wings / Towers Building No 1 - Rose,Building No 2 - Lotus,Building No 3 - Jasmin,Building No 4 - Iris,Building No 5 - Aster

ProjectDeveloperLocationPossession
KoynaShree Shakti DevelopersSurvey No 125 Hissa No 5 And 630-06-2021 00:00:00
Magnus HeightSilver Line ConstructionsThane, 40061231-12-2019 00:00:00
Fortune HeightsSony Noorie RealitySurvey No 107 Hissa No 3 And Survey No 109 Hissa No 1 C31-12-2018 00:00:00
Marathon Nexworld Elara-2Matrix Enclaves Projects Dev. Pvt. Ltd22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/130-12-2024 00:00:00
Marathon Nexworld Elara-1Matrix Enclaves Projects Dev. Pvt. Ltd22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/130-06-2023 00:00:00
Nice World 1Nice BuildersSurvey No 55 Part, 56 Part And 58 Part31-12-2031 00:00:00
Dz City - Building No 1Maash Construction40A/1 And 4130-06-2026 00:00:00
Dz City - Building No 2Al Ameen Builders And Developers40A1, 40, 68A130-06-2026 00:00:00
M M Valley C1Alfa Enterprises55,56,57 P31-12-2018 00:00:00
Al-Quddus ResidencyAlliance Realty400612, Thane30-06-2020 00:00:00
Paradise HeightFriends GroupSurvey No 151/D/22 And Survey No 151/D/2331-12-2018 00:00:00
Marathon Nexworld Aura-2Matrix Enclaves Projects Dev. Pvt. Ltd22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/130-06-2023 00:00:00
Marathon Nexworld Aura-1Matrix Enclaves Projects Dev. Pvt. Ltd22/6, 23/1, 23/2, 23/3, 23/4, 24/4, 26/130-12-2022 00:00:00
Mountain ValleyGayasuddin Riyazuddin Khan87 130-10-2020 00:00:00
Siddiquee ComplexSiddiquee Construction Co.110 2 C 111 1 A 111 1 C30-06-2022 00:00:00
Archit JewelArchit Enterprises71/2A And 71/2B30-05-2022 00:00:00
Magnus MaryamShafi Syed400612, Thane31-03-2020 00:00:00
Sakaar ResidencyMohd Mukhtar Abdul Rauf KaziSurvey No 439, Plot No630-12-2021 00:00:00
Rameshwar Park - Daffodil ARameshawar Builders & Developers130-12-2022 00:00:00
Saffron EnclavesGreen Avenue Constructions11/B130-09-2020 00:00:00
Quality Heights IQuality Construction CoSurvey No 190 Hissa No 1/B31-12-2018 00:00:00
M M Valey A2Alfa Enterprises55,56,57 P30-12-2022 00:00:00
Elite Residence - AElite Realty53/1/B And 54/1/B31-12-2026 00:00:00
Elite Residence - BElite Realty51B/1/C And 118B/1/B31-12-2026 00:00:00
Elite Residence - CElite Realty51/B/1/A And 118/B/1/A31-12-2026 00:00:00
Project Details
  • Project:
    Yes Central Galleria 1
  • Location:
  • Survey No 69/1
  • Const. Stage:
    New
  • Possession:
    31 Oct 2026
Developer Details

  • Developer:
    Yes Enterprises
  • Phone:
  • Address:
  • H No 1
Project RERA Details
MAHA REARA No: P51700049599
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank INDIAN BANK
Proposed Possession 31 Oct 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 15 Feb 2023
Last Retrived 26 Jul 2025
Yes Central Galleria 1 QR Code
Yes Central Galleria 1
MahaRERA - P51700049599
Apartment Details & Configuration
TypeArea
1 BHK43.47 Sq.mts. ( 468 Sq.ft. )
2 BHK49.91 Sq.mts. ( 537 Sq.ft. )
2 BHK59.9 Sq.mts. ( 645 Sq.ft. )
1 BHK41.35 Sq.mts. ( 445 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Yes Central Galleria 1last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Water Supply
To Be Completed
Water Conservation, Rain water Harvesting
To Be Completed
Treatment And Disposal Of Sewage And Sullage Water
Na
Street Lighting
Na
Storm Water Drains
To Be Completed
Solid Waste Management And Disposal
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
To Be Completed
Open Parking
0
Landscaping & Tree Planting
Required No. Of Plants To Be Planted
Fire Protection And Fire Safety Requirements
Na
Energy management
Solar Water Heater To Be Completed
Electrical Meter Room, Sub-Station, Receiving Station
To Be Completed
Community Buildings
Na
Aggregate area of recreational Open Space
To Be Completed
Buildings / Wings in Yes Central Galleria 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Yes Central Galleria 1 by Yes Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

35414 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

120 apartments in total
Total
120
Booked
43
Available
77

Saleable Area Statistics (Sq. ft.)

68302 Total
Total
68302
Booked
23060
Available
45242
Total 120 apartments in project. 43 apartments booked. 35% apartments booked.
Total 68302 Sq.ft. saleable area. 23060 saleable area booked.
34% area booked.

Building No 1 - Rose

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1 - RoseOct 2026710104528
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK43.47 Sq.mts. ( 468 Sq.ft. )14
None Booked0% Booked
0% Booked
2 BHK49.91 Sq.mts. ( 537 Sq.ft. )14
28 total apartments / 2 apartments booked. 7% apartments booked.
Work Description in Building Building No 1 - RoseCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Building No 2 - Lotus

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 - LotusOct 2026710104425
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK43.47 Sq.mts. ( 468 Sq.ft. )14
11 Booked78% Booked
78% Booked
2 BHK49.91 Sq.mts. ( 537 Sq.ft. )14
13 Booked92% Booked
92% Booked
28 total apartments / 24 apartments booked. 85% apartments booked.
Work Description in Building Building No 2 - LotusCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Building No 3 - Jasmin

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3 - JasminOct 2026710104429
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.9 Sq.mts. ( 645 Sq.ft. )28
28 total apartments / 1 apartments booked. 3% apartments booked.
Work Description in Building Building No 3 - JasminCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Building No 4 - Iris

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4 - IrisOct 2026710104434
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.9 Sq.mts. ( 645 Sq.ft. )28
8 Booked28% Booked
28% Booked
28 total apartments / 8 apartments booked. 28% apartments booked.
Work Description in Building Building No 4 - IrisCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Building No 5 - Aster

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 5 - AsterOct 2026210104425
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK41.35 Sq.mts. ( 445 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK43.47 Sq.mts. ( 468 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK59.9 Sq.mts. ( 645 Sq.ft. )2
2 Booked100% Booked
100% Booked
8 total apartments / 8 apartments booked. 100% apartments booked.
Work Description in Building Building No 5 - AsterCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Yes Enterprises
for Project
Yes Central Galleria 1