Project overview

Western Park is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700004620. Western Park is located at 154. This is a Ongoing being developed by Western Real Estate Pvt. Ltd..

Western Park has 1 BHK & Shop Apartments with carpet areas ranging from 146 to 412 Sq.ft. Carpet. The Project has total 395 of which 73 are currently available for sale.

Western Park is being developed on a total land area of 28578 Sq.ft. Western Park has 2 Wings / Towers Al- Farooque Apartment,Al- Siddique Apartment

ProjectDeveloperLocationPossession
Lodha Mira Road Project 1Macrotech Developers Limited90/3, 91/2, 98/228-11-2022 00:00:00
Medtiya RavirajS.N. BuildersOld Sno 316/2 New Sno 40/230-12-2022 00:00:00
Salasar GreensSalasar Estate Developers LlpOld 299 New 180 H.No 425-12-2022 00:00:00
N G BavenoRna Builders (Ng)Survey No 336 Hissa No 215-12-2019 00:00:00
Raj FlorenzaRaj Realtors166/7 Old, 37/7 New30-12-2023 00:00:00
N G AvenueRna Builders (Ng)40110131-12-2023 00:00:00
N G Silver Spring Phase IiiRna Builders (Ng)Old S No 310 New S No 56 H No 2P Old S No 311 New S No 43 H No 131-12-2024 00:00:00
Rishita ApartmentShanti EnterpriseOld Survey No 308/9 New Survey No 54/931-12-2018 00:00:00
Ramdev VillaRamdev VillaOld Survey No.376, Hissa No.231-01-2018 00:00:00
Balaji HeightBalaji BuildconThane01-05-2020 00:00:00
Raj Heritage 2Raj Realty Builders & Developers Private LimitedSn No 383 Old 61 New H No 1A S No 380 Old 67 New H No 6,10 S No 381 Old 66 New H No 3,5,6,831-03-2026 00:00:00
Asmita Grand MaisonAsmita India Limited91/3/1, 92/131-12-2026 00:00:00
Silver SpringM/S. Shri Venkatesh Ramdev HomesNew Survey No 11 Hissa No 2B30-03-2022 00:00:00
Sunder Angan Phase IiSunder Angan Developers167/8, 169/730-12-2021 00:00:00
Vimal Raj Wing A-1, Medityaraviraj ComplexRitesh Ramesh JainOld Sno 3162 New Sno 40231-12-2019 00:00:00
Unique Orbit IiUnique Shanti RealtorsS No 401 Hissa No 3A 3B 3C And S No 401 Hissa No 630-12-2020 00:00:00
Radha RegencyV.R. Construction Co.312/531-12-2018 00:00:00
Ambesh Tower-1 And 2Shalibhadra RealityBhayander East31-07-2021 00:00:00
Sagar AccordM/ S. S A RealtyThane30-12-2021 00:00:00
Usha Kiran HeightsSai Sparsh DevelopersNear Vinayak Temple30-12-2022 00:00:00
Devtara HeightsSavera Construction CoOld Sno 309 New 53 Hissa No 2 Part30-12-2022 00:00:00
Anjani RegencyGeeta DevelopersNew Survey No 35, Hissa No 3 Pt30-12-2020 00:00:00
Raj HomesRaj HomesSurvey No. 219/2, 219/330-12-2023 00:00:00
Raj Heritage 1Raj Realty Builders And Developers Private LimitedSurvey No 380/6,10 Old Survey No 67/630-12-2023 00:00:00
Project Details
  • Project:
    Western Park
  • Location:
  • 154
  • Const. Stage:
    Ongoing
  • Possession:
    30 Oct 2020
Developer Details

  • Developer:
    Western Real Estate Pvt. Ltd.
  • Phone:
  • Address:
  • Lily View Sra Chs Ltd,
Project RERA Details
MAHA REARA No: P51700004620
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Avinash D Mhatre
Funding Bank HDFC BANK
Proposed Possession 30 Oct 2020
Revised Possession 30 Oct 2020
Extended Possession 30 Mar 2025
Litigations No Litigations
Last Modified 17 Mar 2025
Last Retrived 26 Jul 2025
Western Park QR Code
Western Park
MahaRERA - P51700004620
Apartment Details & Configuration
TypeArea
1 BHK36.51 Sq.mts. ( 393 Sq.ft. )
1 BHK38.27 Sq.mts. ( 412 Sq.ft. )
Shop13.54 Sq.mts. ( 146 Sq.ft. )
Shop17.17 Sq.mts. ( 185 Sq.ft. )
Shop18.12 Sq.mts. ( 195 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Western Parklast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
As Per Approved Plan
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting90% completed
90% Complete
As Per Approved Plan
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains
As Per Approved Plan
Street Lighting90% completed
90% Complete
As Per Approved Plan
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply
Na
Buildings / Wings in Western Park
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Western Park by Western Real Estate Pvt. Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.

28578 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

395 apartments in total
Total
395
Booked
322
Available
73

Saleable Area Statistics (Sq. ft.)

146570 Total
Total
146570
Booked
125359
Available
21211
Total 395 apartments in project. 322 apartments booked. 81% apartments booked.
Total 146570 Sq.ft. saleable area. 125359 saleable area booked.
86% area booked.

Al- Farooque Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Al- Farooque ApartmentApr 202211101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.51 Sq.mts. ( 393 Sq.ft. )76
66 Booked86% Booked
86% Booked
1 BHK38.27 Sq.mts. ( 412 Sq.ft. )80
75 Booked93% Booked
93% Booked
Shop13.54 Sq.mts. ( 146 Sq.ft. )8
5 Booked62% Booked
62% Booked
Shop17.17 Sq.mts. ( 185 Sq.ft. )8
6 Booked75% Booked
75% Booked
Shop18.12 Sq.mts. ( 195 Sq.ft. )8
5 Booked62% Booked
62% Booked
180 total apartments / 157 apartments booked. 87% apartments booked.
Work Description in Building Al- Farooque ApartmentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Al- Siddique Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Al- Siddique ApartmentApr 202211101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.51 Sq.mts. ( 393 Sq.ft. )90
79 Booked87% Booked
87% Booked
1 BHK38.27 Sq.mts. ( 412 Sq.ft. )94
83 Booked88% Booked
88% Booked
Shop13.54 Sq.mts. ( 146 Sq.ft. )10
2 Booked20% Booked
20% Booked
Shop17.17 Sq.mts. ( 185 Sq.ft. )10
Shop18.12 Sq.mts. ( 195 Sq.ft. )11
None Booked0% Booked
0% Booked
215 total apartments / 165 apartments booked. 76% apartments booked.
Work Description in Building Al- Siddique ApartmentCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Western Real Estate Pvt. Ltd.
for Project
Western Park
last updated on 26 Jul 2025 as per information obtained from MARA RERA.