Project overview

Wadhwa Rhodesia is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700002499. Wadhwa Rhodesia is located at Survey No. 158/9 Part I. This is a Ongoing being developed by Wadhwa Buildcon Llp.

Wadhwa Rhodesia has 2 BHK, 3 BHK & 4 BHK Apartments with carpet areas ranging from 1134 to 905 Sq.ft. Carpet. The Project has total 312 of which 66 are currently available for sale.

Wadhwa Rhodesia is being developed on a total land area of 118940 Sq.ft. out of which 23518 Sq.ft. i.e 20% is reserved for recreational purposes. Wadhwa Rhodesia has 5 Wings / Towers Shiv Diamond,Shiv Emerald,Shiv Opal,Shiv Sapphire,Shiv Topaz

ProjectDeveloperLocationPossession
Atlanta Residency Phase IiSri Balaji Developer124/5/6/7/9/10, 125/8/10, 159/6. 161/5/8/1431-12-2019 00:00:00
DharmaviharMky Infrastructure108/231-07-2018 00:00:00
Adarsh NeelkanthSarvopari SaharaKamat Ghar01-04-2017 00:00:00
Project Details
  • Project:
    Wadhwa Rhodesia
  • Location:
  • Survey No. 158/9 Part I
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Wadhwa Buildcon Llp
  • Phone:
  • Address:
  • Wadhwa Regalia
Project RERA Details
MAHA REARA No: P51700002499
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Arc K K And Associates
Funding Bank BANK OF INDIA
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 31 Dec 2026
Litigations No Litigations
Last Modified 02 Apr 2024
Last Retrived 26 Jul 2025
Wadhwa Rhodesia QR Code
Wadhwa Rhodesia
MahaRERA - P51700002499
Apartment Details & Configuration
TypeArea
2 BHK58.31 Sq.mts. ( 628 Sq.ft. )
2 BHK64.04 Sq.mts. ( 689 Sq.ft. )
2 BHK67.02 Sq.mts. ( 721 Sq.ft. )
2 BHK67.09 Sq.mts. ( 722 Sq.ft. )
2 BHK74.31 Sq.mts. ( 800 Sq.ft. )
3 BHK82.59 Sq.mts. ( 889 Sq.ft. )
3 BHK84.54 Sq.mts. ( 910 Sq.ft. )
2 BHK65.64 Sq.mts. ( 707 Sq.ft. )
2 BHK65.67 Sq.mts. ( 707 Sq.ft. )
2 BHK66.11 Sq.mts. ( 712 Sq.ft. )
2 BHK76.91 Sq.mts. ( 828 Sq.ft. )
3 BHK81.05 Sq.mts. ( 872 Sq.ft. )
3 BHK83.24 Sq.mts. ( 896 Sq.ft. )
1 BHK32.68 Sq.mts. ( 352 Sq.ft. )
1 BHK32.69 Sq.mts. ( 352 Sq.ft. )
1 BHK36.76 Sq.mts. ( 396 Sq.ft. )
1 BHK40.46 Sq.mts. ( 436 Sq.ft. )
1 BHK41.83 Sq.mts. ( 450 Sq.ft. )
2 BHK46.17 Sq.mts. ( 497 Sq.ft. )
2 BHK49.7 Sq.mts. ( 535 Sq.ft. )
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )
3 BHK85.19 Sq.mts. ( 917 Sq.ft. )
3 BHK85.47 Sq.mts. ( 920 Sq.ft. )
2 BHK65.06 Sq.mts. ( 700 Sq.ft. )
3 BHK83.54 Sq.mts. ( 899 Sq.ft. )
3 BHK84.08 Sq.mts. ( 905 Sq.ft. )
4 BHK105.35 Sq.mts. ( 1134 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Wadhwa Rhodesialast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space30% completed
30% Complete
2184.83Sq.Mtrs
Community Buildings40% completed
40% Complete
Work In Progress
Electrical Meter Room, Sub-Station, Receiving Station20% completed
20% Complete
Work In Progress
Energy management15% completed
15% Complete
Work In Progress
Fire Protection And Fire Safety Requirements
Fire Noc Is Obtained
Landscaping & Tree Planting10% completed
10% Complete
Work In Progress
Open Parking
61 Open Parking Across All Building
Sewerage (Chamber, Lines, Septic Tank , STP)10% completed
10% Complete
Stp Will Be For Phase-I &Amp; Phase-Ii Wadhwa Rhodesia
Solid Waste Management And Disposal10% completed
10% Complete
Included In Sewerage
Storm Water Drains15% completed
15% Complete
Work In Progress
Street Lighting15% completed
15% Complete
Work In Progress
Treatment And Disposal Of Sewage And Sullage Water10% completed
10% Complete
Included In Sewerage
Water Conservation, Rain water Harvesting5% completed
5% Complete
Work In Progress
Water Supply10% completed
10% Complete
The Water Supply Will Be Provided By Bnmc
Buildings / Wings in Wadhwa Rhodesia
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Wadhwa Rhodesia by Wadhwa Buildcon Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.

118940 Sq. ft.

Project Area

23518 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

312 apartments in total
Total
312
Booked
246
Available
66

Saleable Area Statistics (Sq. ft.)

201101 Total
Total
201101
Booked
153138
Available
47963
Total 312 apartments in project. 246 apartments booked. 78% apartments booked.
Total 201101 Sq.ft. saleable area. 153138 saleable area booked.
76% area booked.

Shiv Diamond

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shiv DiamondDec 201913101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK58.31 Sq.mts. ( 628 Sq.ft. )20
15 Booked75% Booked
75% Booked
2 BHK64.04 Sq.mts. ( 689 Sq.ft. )24
19 Booked79% Booked
79% Booked
2 BHK67.02 Sq.mts. ( 721 Sq.ft. )12
7 Booked58% Booked
58% Booked
2 BHK67.09 Sq.mts. ( 722 Sq.ft. )12
8 Booked66% Booked
66% Booked
2 BHK74.31 Sq.mts. ( 800 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK82.59 Sq.mts. ( 889 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK84.54 Sq.mts. ( 910 Sq.ft. )1
1 Booked100% Booked
100% Booked
72 total apartments / 53 apartments booked. 73% apartments booked.
Work Description in Building Shiv DiamondCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress50% done
50% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked

Shiv Emerald

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shiv EmeraldDec 201910101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK65.64 Sq.mts. ( 707 Sq.ft. )10
6 Booked60% Booked
60% Booked
2 BHK65.67 Sq.mts. ( 707 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK66.11 Sq.mts. ( 712 Sq.ft. )10
10 Booked100% Booked
100% Booked
2 BHK76.91 Sq.mts. ( 828 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK81.05 Sq.mts. ( 872 Sq.ft. )12
3 Booked25% Booked
25% Booked
3 BHK82.59 Sq.mts. ( 889 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK83.24 Sq.mts. ( 896 Sq.ft. )1
1 Booked100% Booked
100% Booked
36 total apartments / 23 apartments booked. 63% apartments booked.
Work Description in Building Shiv EmeraldCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress60% done
60% Booked
Stilt Floor
Completed 100% done
100% Booked

Shiv Opal

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shiv OpalDec 201913101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.68 Sq.mts. ( 352 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK32.69 Sq.mts. ( 352 Sq.ft. )13
13 Booked100% Booked
100% Booked
1 BHK36.76 Sq.mts. ( 396 Sq.ft. )10
10 Booked100% Booked
100% Booked
1 BHK40.46 Sq.mts. ( 436 Sq.ft. )38
38 Booked100% Booked
100% Booked
1 BHK41.83 Sq.mts. ( 450 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK46.17 Sq.mts. ( 497 Sq.ft. )21
21 Booked100% Booked
100% Booked
2 BHK49.7 Sq.mts. ( 535 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK50.07 Sq.mts. ( 539 Sq.ft. )2
2 Booked100% Booked
100% Booked
96 total apartments / 96 apartments booked. 100% apartments booked.
Work Description in Building Shiv OpalCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress60% done
60% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress60% done
60% Booked
Stilt Floor
Completed 100% done
100% Booked

Shiv Sapphire

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shiv SapphireDec 201913101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK58.31 Sq.mts. ( 628 Sq.ft. )20
11 Booked55% Booked
55% Booked
2 BHK64.04 Sq.mts. ( 689 Sq.ft. )21
14 Booked66% Booked
66% Booked
2 BHK67.02 Sq.mts. ( 721 Sq.ft. )12
7 Booked58% Booked
58% Booked
2 BHK67.09 Sq.mts. ( 722 Sq.ft. )11
4 Booked36% Booked
36% Booked
2 BHK74.31 Sq.mts. ( 800 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK82.59 Sq.mts. ( 889 Sq.ft. )3
3 Booked100% Booked
100% Booked
3 BHK85.19 Sq.mts. ( 917 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK85.47 Sq.mts. ( 920 Sq.ft. )3
3 Booked100% Booked
100% Booked
72 total apartments / 44 apartments booked. 61% apartments booked.
Work Description in Building Shiv SapphireCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

Shiv Topaz

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shiv TopazDec 201910101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK65.06 Sq.mts. ( 700 Sq.ft. )3
3 Booked100% Booked
100% Booked
2 BHK65.64 Sq.mts. ( 707 Sq.ft. )4
3 Booked75% Booked
75% Booked
2 BHK66.11 Sq.mts. ( 712 Sq.ft. )4
4 Booked100% Booked
100% Booked
2 BHK76.91 Sq.mts. ( 828 Sq.ft. )7
7 Booked100% Booked
100% Booked
3 BHK81.05 Sq.mts. ( 872 Sq.ft. )10
5 Booked50% Booked
50% Booked
3 BHK82.59 Sq.mts. ( 889 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK83.54 Sq.mts. ( 899 Sq.ft. )3
3 Booked100% Booked
100% Booked
3 BHK84.08 Sq.mts. ( 905 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 BHK105.35 Sq.mts. ( 1134 Sq.ft. )2
2 Booked100% Booked
100% Booked
36 total apartments / 30 apartments booked. 83% apartments booked.
Work Description in Building Shiv TopazCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress60% done
60% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress60% done
60% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Wadhwa Buildcon Llp
for Project
Wadhwa Rhodesia
last updated on 26 Jul 2025 as per information obtained from MARA RERA.