Project overview

Veena Velocity Ph-Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000014147. Veena Velocity Ph-Ii is located at Vasai-West. This is a On-Going Project being developed by Nikunj Developers.

Veena Velocity Ph-Ii has 1 BHK Apartments with carpet areas ranging from 355 to 391 Sq.ft. Carpet. The Project has total 181 of which 51 are currently available for sale.

Veena Velocity Ph-Ii is being developed on a total land area of 36867 Sq.ft. Veena Velocity Ph-Ii has 5 Wings / Towers Wing - A,Wing - B,Wing - C,Wing - D,Wing - E

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Veena Velocity Ph-Ii
  • Location:
  • Vasai-West
  • Const. Stage:
    On-Going Project
  • Possession:
    31 Dec 2017
Developer Details

  • Developer:
    Nikunj Developers
  • Phone:
  • Address:
  • Shop No 2, Nikunj Signature, Manav Mandir Complex, Ambadi Road, Vasai, 401202
Project RERA Details
MAHA REARA No: P99000014147
Project Type Others
RERA Project Status On-Going Project
Architect Kaushik Patel
Funding Bank RBL Bank
Proposed Possession 31 Dec 2017
Revised Possession 31 Mar 2019
Extended Possession 30 Sep 2020
Litigations No Litigations
Last Modified 04 Jan 2022
Last Retrived 28 Jul 2025
Veena Velocity Ph-Ii QR Code
Veena Velocity Ph-Ii
MahaRERA - P99000014147
Apartment Details & Configuration
TypeArea
2 BHK54.94 Sq.mts. ( 591 Sq.ft. )
2 BHK55.93 Sq.mts. ( 602 Sq.ft. )
SHOP10.93 Sq.mts. ( 118 Sq.ft. )
SHOP12.23 Sq.mts. ( 132 Sq.ft. )
SHOP12.89 Sq.mts. ( 139 Sq.ft. )
1 BHK32.74 Sq.mts. ( 352 Sq.ft. )
1 BHK33.34 Sq.mts. ( 359 Sq.ft. )
1 BHK36.9 Sq.mts. ( 397 Sq.ft. )
1 BHK37.19 Sq.mts. ( 400 Sq.ft. )
1 BHK37.71 Sq.mts. ( 406 Sq.ft. )
Shop11.58 Sq.mts. ( 125 Sq.ft. )
1 BHK32.98 Sq.mts. ( 355 Sq.ft. )
1 BHK35.15 Sq.mts. ( 378 Sq.ft. )
1 BHK36.15 Sq.mts. ( 389 Sq.ft. )
1 BHK36.3 Sq.mts. ( 391 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Veena Velocity Ph-Iilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station50% completed
50% Complete
-
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
-
Landscaping & Tree Planting50% completed
50% Complete
-
Open Parking
-
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
-
Solid Waste Management And Disposal50% completed
50% Complete
-
Storm Water Drains50% completed
50% Complete
-
Street Lighting
-
Treatment And Disposal Of Sewage And Sullage Water50% completed
50% Complete
-
Water Conservation, Rain water Harvesting
-
Water Supply50% completed
50% Complete
-
Buildings / Wings in Veena Velocity Ph-Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Veena Velocity Ph-Ii by Nikunj Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

36867 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

181 apartments in total
Total
181
Booked
130
Available
51

Saleable Area Statistics (Sq. ft.)

80005 Total
Total
80005
Booked
62248
Available
17756
Total 181 apartments in project. 130 apartments booked. 71% apartments booked.
Total 80005 Sq.ft. saleable area. 62248 saleable area booked.
78% area booked.

Wing - A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - AMar 201981010127
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.94 Sq.mts. ( 591 Sq.ft. )26
19 Booked73% Booked
73% Booked
2 BHK55.93 Sq.mts. ( 602 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP10.93 Sq.mts. ( 118 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP12.23 Sq.mts. ( 132 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP12.89 Sq.mts. ( 139 Sq.ft. )4
None Booked0% Booked
0% Booked
36 total apartments / 21 apartments booked. 58% apartments booked.
Work Description in Building Wing - ACompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress88% done
88% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - BMar 201981010127
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.94 Sq.mts. ( 591 Sq.ft. )26
17 Booked65% Booked
65% Booked
2 BHK55.93 Sq.mts. ( 602 Sq.ft. )2
2 Booked100% Booked
100% Booked
Shop10.93 Sq.mts. ( 118 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop12.23 Sq.mts. ( 132 Sq.ft. )2
None Booked0% Booked
0% Booked
Shop12.89 Sq.mts. ( 139 Sq.ft. )4
None Booked0% Booked
0% Booked
36 total apartments / 19 apartments booked. 52% apartments booked.
Work Description in Building Wing - BCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress88% done
88% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing - C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - CMar 201981010127
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.94 Sq.mts. ( 591 Sq.ft. )26
20 Booked76% Booked
76% Booked
2 BHK55.93 Sq.mts. ( 602 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP10.93 Sq.mts. ( 118 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP12.23 Sq.mts. ( 132 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP12.89 Sq.mts. ( 139 Sq.ft. )4
None Booked0% Booked
0% Booked
36 total apartments / 20 apartments booked. 55% apartments booked.
Work Description in Building Wing - CCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress88% done
88% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing - D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - DMar 2019810101214
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.74 Sq.mts. ( 352 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK33.34 Sq.mts. ( 359 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK36.9 Sq.mts. ( 397 Sq.ft. )20
20 Booked100% Booked
100% Booked
1 BHK37.19 Sq.mts. ( 400 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK37.71 Sq.mts. ( 406 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop10.93 Sq.mts. ( 118 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop11.58 Sq.mts. ( 125 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.89 Sq.mts. ( 139 Sq.ft. )1
None Booked0% Booked
0% Booked
45 total apartments / 42 apartments booked. 93% apartments booked.
Work Description in Building Wing - DCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress88% done
88% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing - E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - EMar 2019810101111
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK32.98 Sq.mts. ( 355 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK35.15 Sq.mts. ( 378 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK36.15 Sq.mts. ( 389 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK36.3 Sq.mts. ( 391 Sq.ft. )7
7 Booked100% Booked
100% Booked
28 total apartments / 28 apartments booked. 100% apartments booked.
Work Description in Building Wing - ECompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress88% done
88% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Nikunj Developers
for Project
Veena Velocity Ph-Ii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.