Project overview

Veena Santoor Phase Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001482. Veena Santoor Phase Ii is located at 128/A/66/A/3/B. This is a Ongoing being developed by Veena Developers.

Veena Santoor Phase Ii has 1 BHK Apartments with carpet areas ranging from 421 to 422 Sq.ft. Carpet. The Project has total 80 of which 0 are currently available for sale.

Veena Santoor Phase Ii is being developed on a total land area of 4588 Sq.ft. Veena Santoor Phase Ii has 2 Wings / Towers H Wing,I Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Veena Santoor Phase Ii
  • Location:
  • 128/A/66/A/3/B
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Veena Developers
  • Phone:
  • Address:
  • Nikunj Signature
Project RERA Details
MAHA REARA No: P51800001482
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Manish Shah
Funding Bank RBL Bank Limited
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 28 Jul 2017
Last Retrived 26 Jul 2025
Veena Santoor Phase Ii QR Code
Veena Santoor Phase Ii
MahaRERA - P51800001482
Apartment Details & Configuration
TypeArea
1 BHK39.14 Sq.mts. ( 421 Sq.ft. )
1 BHK39.23 Sq.mts. ( 422 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Veena Santoor Phase Iilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
-
Energy management
Na
Fire Protection And Fire Safety Requirements90% completed
90% Complete
-
Landscaping & Tree Planting
-
Open Parking
-
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
-
Solid Waste Management And Disposal
-
Storm Water Drains75% completed
75% Complete
-
Street Lighting
-
Treatment And Disposal Of Sewage And Sullage Water
-
Water Conservation, Rain water Harvesting100% completed
95% Complete
-
Water Supply75% completed
75% Complete
-
Buildings / Wings in Veena Santoor Phase Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Veena Santoor Phase Ii by Veena Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

4588 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

80 apartments in total
Total
80
Booked
80
Available
0

Saleable Area Statistics (Sq. ft.)

33743 Total
Total
33743
Booked
33743
Available
0
Total 80 apartments in project. 80 apartments booked. 100% apartments booked.
Total 33743 Sq.ft. saleable area. 33743 saleable area booked.
100% area booked.

H Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
H WingDec 2019111010201
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK39.14 Sq.mts. ( 421 Sq.ft. )20
20 Booked100% Booked
100% Booked
1 BHK39.23 Sq.mts. ( 422 Sq.ft. )20
20 Booked100% Booked
100% Booked
40 total apartments / 40 apartments booked. 100% apartments booked.
Work Description in Building H WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
work-in-progress75% done
75% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

I Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
I WingDec 2019111010201
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK39.14 Sq.mts. ( 421 Sq.ft. )20
20 Booked100% Booked
100% Booked
1 BHK39.23 Sq.mts. ( 422 Sq.ft. )20
20 Booked100% Booked
100% Booked
40 total apartments / 40 apartments booked. 100% apartments booked.
Work Description in Building I WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
work-in-progress75% done
75% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Veena Developers
for Project
Veena Santoor Phase Ii
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation