Project overview

Veena Dynasty Ph Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000007769. Veena Dynasty Ph Ii is located at 2 Pt Sr No 1 2 3 4. This is a Ongoing being developed by Nikunj Developers.

Veena Dynasty Ph Ii has 2 BHK Apartments with carpet areas ranging from 510 to 540 Sq.ft. Carpet. The Project has total 378 of which 5 are currently available for sale.

Veena Dynasty Ph Ii is being developed on a total land area of 87511 Sq.ft. out of which 28546 Sq.ft. i.e 33% is reserved for recreational purposes. Veena Dynasty Ph Ii has 11 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E,Wing F,Wing G,Wing H,Wing I,Wing J,Wing K

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Veena Dynasty Ph Ii
  • Location:
  • 2 Pt Sr No 1 2 3 4
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Nikunj Developers
  • Phone:
  • Address:
  • Nikunj Signature
Project RERA Details
MAHA REARA No: P99000007769
Project Type Others
RERA Project Status Ongoing
Architect Krutika Enterprises
Funding Bank RBL Bank Limited
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession
Litigations No Litigations
Last Modified 18 Aug 2017
Last Retrived 28 Jul 2025
Veena Dynasty Ph Ii QR Code
Veena Dynasty Ph Ii
MahaRERA - P99000007769
Apartment Details & Configuration
TypeArea
1 BHK33.89 Sq.mts. ( 365 Sq.ft. )
1 BHK34.2 Sq.mts. ( 368 Sq.ft. )
SHOP9.89 Sq.mts. ( 106 Sq.ft. )
SHOP9.9 Sq.mts. ( 107 Sq.ft. )
SHOP13.35 Sq.mts. ( 144 Sq.ft. )
SHOP13.36 Sq.mts. ( 144 Sq.ft. )
1 BHK31.45 Sq.mts. ( 339 Sq.ft. )
1 BHK34.18 Sq.mts. ( 368 Sq.ft. )
1 BHK34.19 Sq.mts. ( 368 Sq.ft. )
1 BHK34.21 Sq.mts. ( 368 Sq.ft. )
SHOP10.03 Sq.mts. ( 108 Sq.ft. )
1 BHK34.14 Sq.mts. ( 367 Sq.ft. )
1 BHK34.67 Sq.mts. ( 373 Sq.ft. )
1 BHK34.68 Sq.mts. ( 373 Sq.ft. )
1 BHK40.08 Sq.mts. ( 431 Sq.ft. )
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )
2 BHK49 Sq.mts. ( 527 Sq.ft. )
2 BHK50.47 Sq.mts. ( 543 Sq.ft. )
2 BHK50.53 Sq.mts. ( 544 Sq.ft. )
SHOP11.52 Sq.mts. ( 124 Sq.ft. )
SHOP12.52 Sq.mts. ( 135 Sq.ft. )
SHOP12.72 Sq.mts. ( 137 Sq.ft. )
SHOP13.68 Sq.mts. ( 147 Sq.ft. )
SHOP13.92 Sq.mts. ( 150 Sq.ft. )
SHOP15.9 Sq.mts. ( 171 Sq.ft. )
SHOP33.34 Sq.mts. ( 359 Sq.ft. )
1 BHK34.41 Sq.mts. ( 370 Sq.ft. )
1 BHK33.74 Sq.mts. ( 363 Sq.ft. )
1 BHK33.99 Sq.mts. ( 366 Sq.ft. )
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )
2 BHK51.6 Sq.mts. ( 555 Sq.ft. )
2 BHK50.17 Sq.mts. ( 540 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Veena Dynasty Ph Iilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space50% completed
50% Complete
-
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
-
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
-
Landscaping & Tree Planting100% completed
95% Complete
-
Open Parking50% completed
50% Complete
-
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
-
Solid Waste Management And Disposal40% completed
40% Complete
-
Storm Water Drains100% completed
95% Complete
-
Street Lighting100% completed
95% Complete
-
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
-
Water Conservation, Rain water Harvesting100% completed
95% Complete
-
Water Supply100% completed
95% Complete
-
Buildings / Wings in Veena Dynasty Ph Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Veena Dynasty Ph Ii by Nikunj Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

87511 Sq. ft.

Project Area

28546 Sq. ft.

Recreational Open Space

Total 11

Wings / Towers in Project

Apartments Statistics

378 apartments in total
Total
378
Booked
373
Available
5

Saleable Area Statistics (Sq. ft.)

155204 Total
Total
155204
Booked
152796
Available
2407
Total 378 apartments in project. 373 apartments booked. 98% apartments booked.
Total 155204 Sq.ft. saleable area. 152796 saleable area booked.
98% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ADec 20198101061
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.89 Sq.mts. ( 365 Sq.ft. )14
14 Booked100% Booked
100% Booked
1 BHK34.2 Sq.mts. ( 368 Sq.ft. )14
14 Booked100% Booked
100% Booked
SHOP9.89 Sq.mts. ( 106 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP9.9 Sq.mts. ( 107 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP13.35 Sq.mts. ( 144 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP13.36 Sq.mts. ( 144 Sq.ft. )3
3 Booked100% Booked
100% Booked
34 total apartments / 34 apartments booked. 100% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BDec 201981010131
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.45 Sq.mts. ( 339 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK34.18 Sq.mts. ( 368 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK34.19 Sq.mts. ( 368 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK34.21 Sq.mts. ( 368 Sq.ft. )6
6 Booked100% Booked
100% Booked
SHOP9.9 Sq.mts. ( 107 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP10.03 Sq.mts. ( 108 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP13.36 Sq.mts. ( 144 Sq.ft. )3
3 Booked100% Booked
100% Booked
33 total apartments / 32 apartments booked. 96% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 201981010141
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.14 Sq.mts. ( 367 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK34.67 Sq.mts. ( 373 Sq.ft. )14
14 Booked100% Booked
100% Booked
1 BHK34.68 Sq.mts. ( 373 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK40.08 Sq.mts. ( 431 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )8
6 Booked75% Booked
75% Booked
2 BHK49 Sq.mts. ( 527 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK50.47 Sq.mts. ( 543 Sq.ft. )6
5 Booked83% Booked
83% Booked
2 BHK50.53 Sq.mts. ( 544 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP11.52 Sq.mts. ( 124 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP12.52 Sq.mts. ( 135 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP12.72 Sq.mts. ( 137 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP13.68 Sq.mts. ( 147 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP13.92 Sq.mts. ( 150 Sq.ft. )2
2 Booked100% Booked
100% Booked
SHOP15.9 Sq.mts. ( 171 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP33.34 Sq.mts. ( 359 Sq.ft. )1
1 Booked100% Booked
100% Booked
53 total apartments / 50 apartments booked. 94% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DDec 201981010161
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.89 Sq.mts. ( 365 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK34.41 Sq.mts. ( 370 Sq.ft. )27
27 Booked100% Booked
100% Booked
30 total apartments / 30 apartments booked. 100% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EDec 201981010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.41 Sq.mts. ( 370 Sq.ft. )29
29 Booked100% Booked
100% Booked
29 total apartments / 29 apartments booked. 100% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FDec 201981010121
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )31
31 Booked100% Booked
100% Booked
31 total apartments / 31 apartments booked. 100% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing GDec 20198101091
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )31
31 Booked100% Booked
100% Booked
31 total apartments / 31 apartments booked. 100% apartments booked.
Work Description in Building Wing GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing HDec 20198101081
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK34.41 Sq.mts. ( 370 Sq.ft. )29
29 Booked100% Booked
100% Booked
29 total apartments / 29 apartments booked. 100% apartments booked.
Work Description in Building Wing HCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing I

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing IDec 201981010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.89 Sq.mts. ( 365 Sq.ft. )30
30 Booked100% Booked
100% Booked
30 total apartments / 30 apartments booked. 100% apartments booked.
Work Description in Building Wing ICompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing J

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing JDec 201981010151
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK33.74 Sq.mts. ( 363 Sq.ft. )15
15 Booked100% Booked
100% Booked
1 BHK33.99 Sq.mts. ( 366 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK46.87 Sq.mts. ( 505 Sq.ft. )16
15 Booked93% Booked
93% Booked
2 BHK51.6 Sq.mts. ( 555 Sq.ft. )8
8 Booked100% Booked
100% Booked
47 total apartments / 46 apartments booked. 97% apartments booked.
Work Description in Building Wing JCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing K

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing KDec 201981010141
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47.42 Sq.mts. ( 510 Sq.ft. )23
23 Booked100% Booked
100% Booked
2 BHK50.17 Sq.mts. ( 540 Sq.ft. )8
8 Booked100% Booked
100% Booked
31 total apartments / 31 apartments booked. 100% apartments booked.
Work Description in Building Wing KCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Nikunj Developers
for Project
Veena Dynasty Ph Ii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation