Project overview

Vasant Oasis Carnation Bldg No 19 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800015981. Vasant Oasis Carnation Bldg No 19 is located at 345A/1 Part. This is a New being developed by Neepa Real Estates Private Limited.

Vasant Oasis Carnation Bldg No 19 has 1 BHK Apartments with carpet areas ranging from 432 to 438 Sq.ft. Carpet. The Project has total 12 of which 0 are currently available for sale.

Vasant Oasis Carnation Bldg No 19 is being developed on a total land area of 1816 Sq.ft. Vasant Oasis Carnation Bldg No 19 has 1 Wings / Towers Vasant Oasis Carnation Bldg No 19

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Vasant Oasis Carnation Bldg No 19
  • Location:
  • 345A/1 Part
  • Const. Stage:
    New
  • Possession:
    30 Dec 2021
Developer Details

  • Developer:
    Neepa Real Estates Private Limited
  • Phone:
  • Address:
  • Upper Basement
Project RERA Details
MAHA REARA No: P51800015981
Project Type Residential / Group Housing
RERA Project Status New
Architect Shashikant Jadhav
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2021
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 10 Apr 2018
Last Retrived 26 Jul 2025
Vasant Oasis Carnation Bldg No 19 QR Code
Vasant Oasis Carnation Bldg No 19
MahaRERA - P51800015981
Apartment Details & Configuration
TypeArea
1 BHK40.17 Sq.mts. ( 432 Sq.ft. )
1 BHK40.71 Sq.mts. ( 438 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Vasant Oasis Carnation Bldg No 19last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
14094.75 Sq.Mtr Rg To Be Handed Over To Apex Body
Barbeque Place100% completed
95% Complete
To Be Handed Over To Apex Body
Bedminton Hall100% completed
95% Complete
To Be Handed Over To Apex Body
Children Play Area100% completed
95% Complete
To Be Handed Over To Apex Body
Club House & Swimming Pool100% completed
95% Complete
To Be Handed Over To Apex Body
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Receiving Station -100% To Be Handed Over To Apex
Energy management
As Per Moef Requirement To Be Handed Over To Apex
Fire Protection And Fire Safety Requirements
As Per Cfo To Be Handed Over To Apex Body
Games Room100% completed
95% Complete
To Be Handed Over To Apex Body
Gymnesium100% completed
95% Complete
To Be Handed Over To Apex Body
Jacuzzi100% completed
95% Complete
To Be Handed Over To Apex Body
Jogging Trek80% completed
80% Complete
To Be Handed Over To Apex Body
Kids Pool100% completed
95% Complete
To Be Handed Over To Apex Body
Landscaping & Tree Planting75% completed
75% Complete
To Be Handed Over To Apex Body
Mini Theatre100% completed
95% Complete
To Be Handed Over To Apex Body
Multipurpose Hall100% completed
95% Complete
To Be Handed Over To Apex Body
Open Parking
Na
Party Terrace100% completed
95% Complete
To Be Handed Over To Apex Body
Podium RCC Structure for Bldg100% completed
95% Complete
To Be Handed Over To Apex Body
Pool side Deck90% completed
90% Complete
To Be Handed Over To Apex Body
Public Parking Scheme
To Be Handed Over To Mcgm
SAUNA100% completed
95% Complete
To Be Handed Over To Apex Body
Senior Resident Corner80% completed
80% Complete
To Be Handed Over To Apex Body
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Stp Structure Completed To Be Handed Over To Apex
Solid Waste Management And Disposal90% completed
90% Complete
To Be Handed Over To Apex Body
Squash Court100% completed
95% Complete
To Be Handed Over To Apex Body
STEAM100% completed
95% Complete
To Be Handed Over To Apex Body
Storm Water Drains90% completed
90% Complete
To Be Handed Over To Apex Body
Street Lighting75% completed
75% Complete
To Be Handed Over To Apex Body
Swimming Pool100% completed
95% Complete
To Be Handed Over To Apex Body
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
To Be Handed Over To Apex Body
Water Conservation, Rain water Harvesting90% completed
90% Complete
Rwh Only To Be Handed Over To Apex Body
Water Supply
Bmc Water Connection To Be Handed Over To Apexbody
Yoga or Multiutility Room100% completed
95% Complete
To Be Handed Over To Apex Body
Buildings / Wings in Vasant Oasis Carnation Bldg No 19
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Vasant Oasis Carnation Bldg No 19 by Neepa Real Estates Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

1816 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

12 apartments in total
Total
12
Booked
12
Available
0

Saleable Area Statistics (Sq. ft.)

5212 Total
Total
5212
Booked
5212
Available
0
Total 12 apartments in project. 12 apartments booked. 100% apartments booked.
Total 5212 Sq.ft. saleable area. 5212 saleable area booked.
100% area booked.

Vasant Oasis Carnation Bldg No 19

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Vasant Oasis Carnation Bldg No 19Dec 202061212012
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40.17 Sq.mts. ( 432 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK40.71 Sq.mts. ( 438 Sq.ft. )4
4 Booked100% Booked
100% Booked
12 total apartments / 12 apartments booked. 100% apartments booked.
Work Description in Building Vasant Oasis Carnation Bldg No 19Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Neepa Real Estates Private Limited
for Project
Vasant Oasis Carnation Bldg No 19