Project overview

Vasant Oasis Camelia Bldg 13 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800000921. Vasant Oasis Camelia Bldg 13 is located at 345A/1 Part. This is a Ongoing being developed by Neepa Real Estates Private Limited.

Vasant Oasis Camelia Bldg 13 has 2 AND HALF BHK & 2 BHK Apartments with carpet areas ranging from 675 to 853 Sq.ft. Carpet. The Project has total 170 of which 0 are currently available for sale.

Vasant Oasis Camelia Bldg 13 is being developed on a total land area of 8206 Sq.ft. Vasant Oasis Camelia Bldg 13 has 1 Wings / Towers Camelia A B Bldg 13

ProjectDeveloperLocationPossession
Vasant Oasis Petunia Bldg 8Neepa Real Estates Private Limited345A/1 Part30-12-2022 00:00:00
Vasant Oasis Bluebell Bldg 9Neepa Real Estates Private Limited345A/1 Part30-12-2022 00:00:00
Vasant Oasis Eliza Bldg 11Neepa Real Estates Private Limited345A/1 Part31-12-2019 00:00:00
Vasant Oasis Daffodil Bldg 7Neepa Real Estates Private Limited345A/1 Part30-12-2022 00:00:00
Vasant Oasis Hana Bldg 10Neepa Real Estates Private Limited345A/1 Part31-12-2019 00:00:00
Vasant Oasis Acacia Bldg 12Neepa Real Estates Private Limited345A/1 Part31-12-2019 00:00:00
Vasant Oasis Lillium Bldg 16Neepa Real Estates Private Limited345A/1 Part30-12-2023 00:00:00
Vasant Oasis Camelia Bldg 13Neepa Real Estates Private Limited345A/1 Part30-12-2023 00:00:00
Vasant Oasis Zinnia Bldg 17Neepa Real Estates Private Limited345A/1 Part30-12-2023 00:00:00
Akhand AnandSiv Reality Private Limited25331-12-2018 00:00:00
Al-Burhan Chs-Phase-IiRaj Romell RealtorsAndheri East, Mumbai30-12-2020 00:00:00
PareejatShanti Enterprise400059, Mumbai Suburban08-01-2018 00:00:00
Park Royale C D WingShivranjani Properties Llp125, 7, 830-12-2021 00:00:00
Park Royale Ab WingShivranjani Properties Llp125, 8, 731-12-2019 00:00:00
Srishti Harmony Iii- Phase 1Nathan Properties Pvt Ltd191A/B, New Cts No 191A/A, 191A/C/131-12-2019 00:00:00
Al-Burhan Chs-Phase-IRaj Romell RealtorsAndheri East, Plot No 25, Cts-12973 Village Marol30-12-2020 00:00:00
Safavi Chs LtdRaj Builders1209A/ Plot No. 1731-10-2018 00:00:00
TriveniShreenath Infraprojects30231-03-2018 00:00:00
Sky HeightsSkylink DevelopersNew Survey No. 11, 77A 1 To 49, 77A31-01-2021 00:00:00
Vasant Oasis Danica Bldg No 15Neepa Real Estates Private Limited345 A/1 Part30-12-2022 00:00:00
Vasant Oasis Carnation Bldg No 19Neepa Real Estates Private Limited345A/1 Part30-12-2021 00:00:00
Sharda HeightsNarendra Jagdishprasad Agarwal25931-12-2018 00:00:00
T SquareK T Sons683 1 And 2, 683A, 68331-07-2018 00:00:00
The HeightsDhruvi Properties Pvt Ltd179, 180, 207, 177, 181, 20530-06-2021 00:00:00
K Raheja PlatinumDimple Enterprises710G Part31-12-2018 00:00:00
Vkg EstatesGreenery Rock Llp116A30-12-2026 00:00:00
Royal GreenAdmire Revive Builder & DeveloperSuryey No. 148 Cts 1349 / 1 To 1430-12-2021 00:00:00
Times Square- C WingNtpl Developers,LlpD, Part 758/A31-03-2020 00:00:00
Ndw AltimaAviation Hotels Pvt Ltd1651A/130-12-2023 00:00:00
Lighthall E Wing Gamma Constructions Pvt LtdCts No 193 Part Village Tungwe And Cts No 2 Part Village Saki30-03-2023 00:00:00
Eco HeightsEtco Builders Private Limited726/16 To 40, Cts 72630-12-2023 00:00:00
Serenity HeightsAristocrat Marketing Ltd662/530-05-2019 00:00:00
Lighthall D WingGamma Constructions Pvt Ltd193 Part Village Tungwa 2 Part Village Saki31-12-2018 00:00:00
OptimaUnirock Developers40005931-12-2022 00:00:00
Times Square- D WingNilkanth Tech Park Pvt. Ltd.758A, B31-07-2019 00:00:00
Naman PremierShree Naman Developers Pvt LtdCts No 304, 317 And 322, 30531-03-2020 00:00:00
Project Details
  • Project:
    Vasant Oasis Camelia Bldg 13
  • Location:
  • 345A/1 Part
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Neepa Real Estates Private Limited
  • Phone:
  • Address:
  • Upper Basement
Project RERA Details
MAHA REARA No: P51800000921
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Shashikant Jadhav
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession
Litigations No Litigations
Last Modified 25 Jul 2017
Last Retrived 26 Jul 2025
Vasant Oasis Camelia Bldg 13 QR Code
Vasant Oasis Camelia Bldg 13
MahaRERA - P51800000921
Apartment Details & Configuration
TypeArea
2 AND HALF BHK79.25 Sq.mts. ( 853 Sq.ft. )
2 BHK62.69 Sq.mts. ( 675 Sq.ft. )
2 BHK62.93 Sq.mts. ( 677 Sq.ft. )
2 BHK63.03 Sq.mts. ( 678 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Vasant Oasis Camelia Bldg 13last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space50% completed
50% Complete
14094.75 Sq.Mtr Rg To Be Handed Over To Apex Body
Badminton Hall98% completed
98% Complete
To Be Handed Over To Apex Body
BBQ Space100% completed
95% Complete
To Be Handed Over To Apex Body
Children Play Area100% completed
95% Complete
To Be Handed Over To Apex Body
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Receiving Station -100% To Be Handed Over To Apex
Energy management
As Per Moef Requirement To Be Handed Over To Apex
Fire Protection And Fire Safety Requirements
As Per Cfo To Be Handed Over To Apex Body
Games Room100% completed
95% Complete
To Be Handed Over To Apex Body
Gymnasium100% completed
95% Complete
To Be Handed Over To Apex Body
Jacuzzi100% completed
95% Complete
To Be Handed Over To Apex Body
Kids Pool100% completed
95% Complete
To Be Handed Over To Apex Body
Landscaping & Tree Planting50% completed
50% Complete
. To Be Handed Over To Apex Body
Mini Theatre100% completed
95% Complete
To Be Handed Over To Apex Body
Multipurpose Hall100% completed
95% Complete
To Be Handed Over To Apex Body
Open Parking
Na
Party Terrace100% completed
95% Complete
To Be Handed Over To Apex Body
Podium RCC Structure for Building Camelia100% completed
95% Complete
To Be Handed Over To Apex Body
Pool Side Deck90% completed
90% Complete
To Be Handed Over To Apex Body
Public Parking Scheme
To Be Handed Over To Mcgm
Sauna100% completed
95% Complete
To Be Handed Over To Apex Body
Senior Resident Corner100% completed
95% Complete
To Be Handed Over To Apex Body
Sewerage (Chamber, Lines, Septic Tank , STP)75% completed
75% Complete
Stp Structure Completed To Be Handed Over To Apex
Solid Waste Management And Disposal
Owc To Be Handed Over To Apex Body
Squash Court100% completed
95% Complete
To Be Handed Over To Apex Body
Steam100% completed
95% Complete
To Be Handed Over To Apex Body
Storm Water Drains20% completed
20% Complete
. To Be Handed Over To Apex Body
Street Lighting95% completed
95% Complete
. To Be Handed Over To Apex Body
SWIMMING POOL100% completed
95% Complete
To Be Handed Over To Apex Body
Treatment And Disposal Of Sewage And Sullage Water
. To Be Handed Over To Apex Body
Water Conservation, Rain water Harvesting
Rwh Only To Be Handed Over To Apex Body
Water Supply
Bmc Water Connection To Be Handed Over To Apexbody
Yoga or Multiutility Room100% completed
95% Complete
To Be Handed Over To Apex Body
Buildings / Wings in Vasant Oasis Camelia Bldg 13
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Vasant Oasis Camelia Bldg 13 by Neepa Real Estates Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

8206 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

170 apartments in total
Total
170
Booked
170
Available
0

Saleable Area Statistics (Sq. ft.)

115518 Total
Total
115518
Booked
115518
Available
0
Total 170 apartments in project. 170 apartments booked. 100% apartments booked.
Total 115518 Sq.ft. saleable area. 115518 saleable area booked.
100% area booked.

Camelia A B Bldg 13

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Camelia A B Bldg 13Dec 20222412120256
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 AND HALF BHK79.25 Sq.mts. ( 853 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK62.69 Sq.mts. ( 675 Sq.ft. )22
22 Booked100% Booked
100% Booked
2 BHK62.93 Sq.mts. ( 677 Sq.ft. )82
82 Booked100% Booked
100% Booked
2 BHK63.03 Sq.mts. ( 678 Sq.ft. )64
64 Booked100% Booked
100% Booked
170 total apartments / 170 apartments booked. 100% apartments booked.
Work Description in Building Camelia A B Bldg 13Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress41% done
41% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress23% done
23% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
work-in-progress80% done
80% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
work-in-progress23% done
23% Booked
Channel Partners
Channel Partners Registered by Developer
Neepa Real Estates Private Limited
for Project
Vasant Oasis Camelia Bldg 13
last updated on 26 Jul 2025 as per information obtained from MARA RERA.