Project overview

Vaikunth Cluster 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700003793. Vaikunth Cluster 2 is located at No 7/1 To 14, 8/1To37, 39To42, 9/1To17, 10/2To9, 10/10A,10/10B,10/11To18, 99/13B, 15B. This is a New being developed by PEPL Developers Pvt Ltd.

Vaikunth Cluster 2 has 2 BHK Apartments with carpet areas ranging from 635 to 743 Sq.ft. Carpet. The Project has total 551 of which 17 are currently available for sale.

Vaikunth Cluster 2 is being developed on a total land area of 52335 Sq.ft. out of which 13634 Sq.ft. i.e 26% is reserved for recreational purposes. Vaikunth Cluster 2 has 2 Wings / Towers Vairat,Vijit

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Vaikunth Cluster 2
  • Location:
  • No 7/1 To 14, 8/1To37, 39To42, 9/1To17, 10/2To9, 10/10A,10/10B,10/11To18, 99/13B, 15B
  • Const. Stage:
    New
  • Possession:
    30 Dec 2024
Developer Details

  • Developer:
    PEPL Developers Pvt Ltd
  • Phone:
  • Address:
  • Piramal Tower
Project RERA Details
MAHA REARA No: P51700003793
Project Type Residential / Group Housing
RERA Project Status New
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 28 Nov 2018
Last Retrived 13 Feb 2026
Vaikunth Cluster 2 QR Code
Vaikunth Cluster 2
MahaRERA - P51700003793
Apartment Details & Configuration
TypeArea
2 BHK59 Sq.mts. ( 635 Sq.ft. )
2 BHK68 Sq.mts. ( 732 Sq.ft. )
3 BHK81 Sq.mts. ( 872 Sq.ft. )
2 BHK60 Sq.mts. ( 646 Sq.ft. )
2 BHK65 Sq.mts. ( 700 Sq.ft. )
2 BHK69 Sq.mts. ( 743 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Vaikunth Cluster 2last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space95% completed
95% Complete
Work Yet To Be Started
Cafe
Work Yet To Be Started
Community Buildings95% completed
95% Complete
Part Of Larger Layout
Convenience Store
Work Yet To Be Started
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Work Yet To Be Started
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
As Per Statutory Requirements
Guest Suite
Na
Gymnasium
Work Yet To Be Started
Kids Pool
Work Yet To Be Started
Landscaping & Tree Planting75% completed
75% Complete
Work Yet To Be Started
Mini cricket ground
Work Yet To Be Started
Multi purpose court
Work Yet To Be Started
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Work Yet To Be Started
Solid Waste Management And Disposal100% completed
95% Complete
Work Yet To Be Started
Squash Court
Work Yet To Be Started
Storm Water Drains100% completed
95% Complete
As Per Statutory Requirements
Street Lighting95% completed
95% Complete
Work Yet To Be Started
Swimming Pool
Work Yet To Be Started
Treatment And Disposal Of Sewage And Sullage Water90% completed
90% Complete
Stp Is Common Facility As A Part Of Larger Layout
Water Conservation, Rain water Harvesting100% completed
95% Complete
Work Yet To Be Started
Water Supply100% completed
95% Complete
Work Yet To Be Started
Buildings / Wings in Vaikunth Cluster 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Vaikunth Cluster 2 by PEPL Developers Pvt Ltdlast updated on 13 Feb 2026 as per information obtained from MARA RERA.

52335 Sq. ft.

Project Area

13634 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

551 apartments in total
Total
551
Booked
534
Available
17

Saleable Area Statistics (Sq. ft.)

369743 Total
Total
369743
Booked
357150
Available
12594
Total 551 apartments in project. 534 apartments booked. 96% apartments booked.
Total 369743 Sq.ft. saleable area. 357150 saleable area booked.
97% area booked.

Vairat

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VairatDec 20244010050386
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59 Sq.mts. ( 635 Sq.ft. )204
202 Booked99% Booked
99% Booked
2 BHK68 Sq.mts. ( 732 Sq.ft. )5
4 Booked80% Booked
80% Booked
3 BHK81 Sq.mts. ( 872 Sq.ft. )69
63 Booked91% Booked
91% Booked
278 total apartments / 269 apartments booked. 96% apartments booked.
Work Description in Building VairatCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Vijit

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VijitDec 20244010050300
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59 Sq.mts. ( 635 Sq.ft. )65
64 Booked98% Booked
98% Booked
2 BHK60 Sq.mts. ( 646 Sq.ft. )198
194 Booked97% Booked
97% Booked
2 BHK65 Sq.mts. ( 700 Sq.ft. )5
3 Booked60% Booked
60% Booked
2 BHK69 Sq.mts. ( 743 Sq.ft. )5
4 Booked80% Booked
80% Booked
273 total apartments / 265 apartments booked. 97% apartments booked.
Work Description in Building VijitCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
PEPL Developers Pvt Ltd
for Project
Vaikunth Cluster 2
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation