Project overview
Upakram Chs Ltd. is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800012344. Upakram Chs Ltd. is located at 400064, Mumbai Suburban. This is a On-Going Project being developed by Rajvi Builders And Developers.
Upakram Chs Ltd. has 1 BHK, 1RK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 255 to 1009 Sq.ft. Carpet. The Project has total 71 of which 14 are currently available for sale.
Upakram Chs Ltd. is being developed on a total land area of 17478 Sq.ft. Upakram Chs Ltd. has 1 Wings / Towers Upakram Chs Ltd
| Project | Developer | Location | Possession |
| Sankalp Heritage | Shyam Biharilal Gehani | 986/1 T O4, 986 | 31-12-2019 00:00:00 |
| Sky Residency Loksadan Chs Phase 1 Up To G Plus 7Pt. | Sky Property Developers Private Limited | 766, 766/1 To 5 | 31-12-2017 00:00:00 |
| Aqsa Palace Chs Ltd | K T Group | 400064, Mumbai Suburban | 30-09-2017 00:00:00 |
| Sun-Vision Avenue | Woodland Constructions Pvt Ltd | 400064, Mumbai Suburban | 31-03-2018 00:00:00 |
| Auris Serenity Tower 1 | Transcon-Sheth Creators Private Limited | Cts No 332 Part 333 Part 325/A/1 Part | 30-12-2022 00:00:00 |
| Auris Serenity Tower 3 | Transcon-Sheth Creators Private Limited | Cts No 326 Part 375 Part 376/A Part 376/A Part 376/A/3 376/A/4 382 Part | 30-12-2024 00:00:00 |
-
Project:
Upakram Chs Ltd.
-
Location:
-
400064, Mumbai Suburban
-
Const. Stage:
On-Going Project
-
Possession:
01 Jan 2017
-
Developer:
Rajvi Builders And Developers
-
Phone:
-
Address:
-
Shop No.10 &Amp; 11, Majithia Apartments, Vile Parle West, Above Irla Nursing Home, Irla, 400092
| MAHA REARA No: |
P51800012344 |
| Project Type |
Residential |
| RERA Project Status |
On-Going Project |
| Funding Bank |
Central Bank of India |
| Proposed Possession |
01 Jan 2017 |
| Revised Possession |
01 Jul 2022 |
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
31 Jul 2017 |
| Last Retrived |
28 Jul 2025 |
Upakram Chs Ltd. QR Code
Upakram Chs Ltd.
MahaRERA - P51800012344
| Type | Area |
| 1 BHK | 28.15 Sq.mts. ( 303 Sq.ft. ) |
| 1 BHK | 34.84 Sq.mts. ( 375 Sq.ft. ) |
| 1 BHK | 40.96 Sq.mts. ( 441 Sq.ft. ) |
| 1RK | 23.69 Sq.mts. ( 255 Sq.ft. ) |
| 2 BHK | 45.05 Sq.mts. ( 485 Sq.ft. ) |
| 2 BHK | 46.82 Sq.mts. ( 504 Sq.ft. ) |
| 2 BHK | 47.1 Sq.mts. ( 507 Sq.ft. ) |
| 2 BHK | 51.28 Sq.mts. ( 552 Sq.ft. ) |
| 2 BHK | 52.86 Sq.mts. ( 569 Sq.ft. ) |
| 2 BHK | 64.38 Sq.mts. ( 693 Sq.ft. ) |
| 3 BHK | 66.89 Sq.mts. ( 720 Sq.ft. ) |
| 3 BHK | 75.44 Sq.mts. ( 812 Sq.ft. ) |
| 3 BHK | 77.85 Sq.mts. ( 838 Sq.ft. ) |
| 3 BHK | 93.74 Sq.mts. ( 1009 Sq.ft. ) |
| 3 BHK | 59.92 Sq.mts. ( 645 Sq.ft. ) |
| 3 BHK | 63.73 Sq.mts. ( 686 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Upakram Chs Ltd.last updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Incomplete |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Incomplete |
Landscaping & Tree Planting
|
|
Incomplete |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Incomplete |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
Incomplete |
|
|
|
Incomplete |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Incomplete |
|
|
|
Incomplete |
Buildings / Wings in Upakram Chs Ltd.
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Upakram Chs Ltd. by Rajvi Builders And Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
71
apartments in total
Saleable Area Statistics (Sq. ft.)
39350
Total
Total 71 apartments in project. 57 apartments booked. 80% apartments booked.
Total 39350 Sq.ft. saleable area. 30513 saleable area booked.
78% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Upakram Chs Ltd | Jan 1900 | 16 | 1 | 0 | 1 | 0 | 0 | 71 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 28.15 Sq.mts. ( 303 Sq.ft. ) | 4 | |
| 1 BHK | 34.84 Sq.mts. ( 375 Sq.ft. ) | 4 | |
| 1 BHK | 40.96 Sq.mts. ( 441 Sq.ft. ) | 14 | |
| 1RK | 23.69 Sq.mts. ( 255 Sq.ft. ) | 1 | |
| 2 BHK | 45.05 Sq.mts. ( 485 Sq.ft. ) | 7 | |
| 2 BHK | 46.82 Sq.mts. ( 504 Sq.ft. ) | 4 | |
| 2 BHK | 47.1 Sq.mts. ( 507 Sq.ft. ) | 2 | |
| 2 BHK | 51.28 Sq.mts. ( 552 Sq.ft. ) | 8 | |
| 2 BHK | 52.86 Sq.mts. ( 569 Sq.ft. ) | 1 | |
| 2 BHK | 64.38 Sq.mts. ( 693 Sq.ft. ) | 4 | |
| 3 BHK | 66.89 Sq.mts. ( 720 Sq.ft. ) | 1 | |
| 3 BHK | 75.44 Sq.mts. ( 812 Sq.ft. ) | 6 | |
| 3 BHK | 77.85 Sq.mts. ( 838 Sq.ft. ) | 1 | |
| 3 BHK | 93.74 Sq.mts. ( 1009 Sq.ft. ) | 1 | |
| 3 BHK | 59.92 Sq.mts. ( 645 Sq.ft. ) | 8 | |
| 3 BHK | 63.73 Sq.mts. ( 686 Sq.ft. ) | 5 | |
71 total apartments / 57 apartments booked. 80% apartments booked. |
| Work Description in Building Upakram Chs Ltd | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Rajvi Builders And Developers
for Project
Upakram Chs Ltd.
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |