Project overview

Uma Residency, Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700011302. Uma Residency, Phase I is located at Survey No. 22 , Hissa No 2 And 6. This is a New being developed by Adarsh Infra Developers.

Uma Residency, Phase I has 1 BHK FLAT & 1 RK FLAT Apartments with carpet areas ranging from 222 to 315 Sq.ft. Carpet. The Project has total 120 of which 105 are currently available for sale.

Uma Residency, Phase I is being developed on a total land area of 48115 Sq.ft. out of which 7233 Sq.ft. i.e 15% is reserved for recreational purposes. Uma Residency, Phase I has 5 Wings / Towers Building E4,Building F3,Building F4,Building G1,Building G2

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Uma Residency, Phase I
  • Location:
  • Survey No. 22 , Hissa No 2 And 6
  • Const. Stage:
    New
  • Possession:
    30 Jun 2021
Developer Details

  • Developer:
    Adarsh Infra Developers
  • Phone:
  • Address:
  • Mirage Arcade
Project RERA Details
MAHA REARA No: P51700011302
Project Type Residential / Group Housing
RERA Project Status New
Architect Suyog Sanjay Pande Prop Of Parth Consultant & Town Planners
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Jun 2021
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 02 Apr 2024
Last Retrived 26 Jul 2025
Uma Residency, Phase I QR Code
Uma Residency, Phase I
MahaRERA - P51700011302
Apartment Details & Configuration
TypeArea
1 BHK FLAT29.45 Sq.mts. ( 317 Sq.ft. )
1 BHK FLAT30.6 Sq.mts. ( 329 Sq.ft. )
1 BHK FLAT31.15 Sq.mts. ( 335 Sq.ft. )
1 BHK FLAT32 Sq.mts. ( 344 Sq.ft. )
1 RK FLAT20.7 Sq.mts. ( 223 Sq.ft. )
1 RK FLAT21.8 Sq.mts. ( 235 Sq.ft. )
1 BHK FLAT29.3 Sq.mts. ( 315 Sq.ft. )
1 BHK FLAT30.51 Sq.mts. ( 328 Sq.ft. )
1 RK FLAT20.65 Sq.mts. ( 222 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Uma Residency, Phase Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
672 Sq Mtr
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
1 Electric Meter Room/Space For Each Wing
Energy management
Solar Water Heater System
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Minimum 40 Trees
Open Parking
Approx 50 Parkings
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Provision For Storm Water Drains
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Provision Rain Water Harvesting
Water Supply
Borewell Water With Ro Water Purifier By Promoter
Buildings / Wings in Uma Residency, Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Uma Residency, Phase I by Adarsh Infra Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

48115 Sq. ft.

Project Area

7233 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

120 apartments in total
Total
120
Booked
15
Available
105

Saleable Area Statistics (Sq. ft.)

35757 Total
Total
35757
Booked
4914
Available
30843
Total 120 apartments in project. 15 apartments booked. 12% apartments booked.
Total 35757 Sq.ft. saleable area. 4914 saleable area booked.
14% area booked.

Building E4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building E4Jun 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK FLAT29.45 Sq.mts. ( 317 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK FLAT30.6 Sq.mts. ( 329 Sq.ft. )4
1 Booked25% Booked
25% Booked
1 BHK FLAT31.15 Sq.mts. ( 335 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK FLAT32 Sq.mts. ( 344 Sq.ft. )16
5 Booked31% Booked
31% Booked
1 RK FLAT20.7 Sq.mts. ( 223 Sq.ft. )3
None Booked0% Booked
0% Booked
1 RK FLAT21.8 Sq.mts. ( 235 Sq.ft. )12
40 total apartments / 7 apartments booked. 17% apartments booked.
Work Description in Building Building E4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress77% done
77% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building F3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building F3Jun 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK FLAT29.3 Sq.mts. ( 315 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK FLAT30.51 Sq.mts. ( 328 Sq.ft. )16
None Booked0% Booked
0% Booked
20 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building F3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress77% done
77% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building F4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building F4Jun 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.3 Sq.mts. ( 315 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK30.51 Sq.mts. ( 328 Sq.ft. )16
8 Booked50% Booked
50% Booked
20 total apartments / 8 apartments booked. 40% apartments booked.
Work Description in Building Building F4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress75% done
75% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building G1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building G1Jun 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK FLAT29.3 Sq.mts. ( 315 Sq.ft. )10
None Booked0% Booked
0% Booked
1 RK FLAT20.65 Sq.mts. ( 222 Sq.ft. )10
None Booked0% Booked
0% Booked
20 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building G1Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building G2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building G2Jun 202151000100
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK FLAT29.3 Sq.mts. ( 315 Sq.ft. )10
None Booked0% Booked
0% Booked
1 RK FLAT20.65 Sq.mts. ( 222 Sq.ft. )10
None Booked0% Booked
0% Booked
20 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building G2Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Adarsh Infra Developers
for Project
Uma Residency, Phase I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation