Project overview
Uk Iridium is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800007275. Uk Iridium is located at 163 A Part. This is a Ongoing being developed by Damodar Suruchi Developers Pvt. Ltd..
Uk Iridium has 1 BHK Apartments with carpet areas ranging from 382 to 414 Sq.ft. Carpet. The Project has total 518 of which 47 are currently available for sale.
Uk Iridium is being developed on a total land area of 145405 Sq.ft. out of which 5825 Sq.ft. i.e 4% is reserved for recreational purposes. Uk Iridium has 2 Wings / Towers Tower 1,Tower 2
| Project | Developer | Location | Possession |
-
Project:
Uk Iridium
-
Location:
-
163 A Part
-
Const. Stage:
Ongoing
-
Possession:
30 Dec 2023
| MAHA REARA No: |
P51800007275 |
| Project Type |
Others |
| RERA Project Status |
Ongoing |
| Architect |
Shantanoo Rane And Associates |
| Funding Bank |
HDFC BANK |
| Proposed Possession |
30 Dec 2023 |
| Revised Possession |
30 Dec 2023 |
| Extended Possession |
12 Oct 2024 |
| Litigations |
No Litigations |
| Last Modified |
10 Nov 2023 |
| Last Retrived |
26 Jul 2025 |
Uk Iridium QR Code
Uk Iridium
MahaRERA - P51800007275
| Type | Area |
| 1 BHK | 26.15 Sq.mts. ( 281 Sq.ft. ) |
| 1 BHK | 26.72 Sq.mts. ( 288 Sq.ft. ) |
| 1 BHK | 36.73 Sq.mts. ( 395 Sq.ft. ) |
| 2 BHK | 48.45 Sq.mts. ( 522 Sq.ft. ) |
| 2 BHK | 49.25 Sq.mts. ( 530 Sq.ft. ) |
| 2 BHK | 50.59 Sq.mts. ( 545 Sq.ft. ) |
| Office space | 32.31 Sq.mts. ( 348 Sq.ft. ) |
| Office space | 18.02 Sq.mts. ( 194 Sq.ft. ) |
| Office space | 18.04 Sq.mts. ( 194 Sq.ft. ) |
| Office space | 18.16 Sq.mts. ( 195 Sq.ft. ) |
| Office space | 21.39 Sq.mts. ( 230 Sq.ft. ) |
| Office space | 21.4 Sq.mts. ( 230 Sq.ft. ) |
| Shop | 22.75 Sq.mts. ( 245 Sq.ft. ) |
| Shop | 25.92 Sq.mts. ( 279 Sq.ft. ) |
| Shop | 25.93 Sq.mts. ( 279 Sq.ft. ) |
| Shop | 39.86 Sq.mts. ( 429 Sq.ft. ) |
| 1 BHK | 35.46 Sq.mts. ( 382 Sq.ft. ) |
| 1 BHK | 38.1 Sq.mts. ( 410 Sq.ft. ) |
| 1 BHK | 38.5 Sq.mts. ( 414 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Uk Iridiumlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Work In Progress |
|
|
|
Work In Progress |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station50% completed
|
|
Work In Progress |
|
|
|
Na |
Entrance Lounge20% completed
|
|
Work In Progress |
Fire Protection And Fire Safety
Requirements
|
|
Work In Progress |
Fountain Waterfall at Main entrance
|
|
Work In Progress |
|
|
|
Work In Progress |
Landscaping & Tree Planting
|
|
Work In Progress |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)10% completed
|
|
Chamber Lines And Stp Only |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
Work In Progress |
|
|
|
Work In Progress |
Treatment And Disposal Of Sewage And Sullage Water30% completed
|
|
Na |
Water Conservation, Rain water Harvesting20% completed
|
|
Work In Progress |
Water Supply40% completed
|
|
Work In Progress |
Buildings / Wings in Uk Iridium
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Uk Iridium by Damodar Suruchi Developers Pvt. Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
518
apartments in total
Saleable Area Statistics (Sq. ft.)
220645
Total
Total 518 apartments in project. 471 apartments booked. 90% apartments booked.
Total 220645 Sq.ft. saleable area. 204573 saleable area booked.
93% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Tower 1 | Dec 2022 | 27 | 1 | 0 | 1 | 4 | 0 | 98 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 26.15 Sq.mts. ( 281 Sq.ft. ) | 54 | |
| 1 BHK | 26.72 Sq.mts. ( 288 Sq.ft. ) | 1 | |
| 1 BHK | 36.73 Sq.mts. ( 395 Sq.ft. ) | 54 | |
| 2 BHK | 48.45 Sq.mts. ( 522 Sq.ft. ) | 54 | |
| 2 BHK | 49.25 Sq.mts. ( 530 Sq.ft. ) | 12 | |
| 2 BHK | 50.59 Sq.mts. ( 545 Sq.ft. ) | 107 | |
| Office space | 32.31 Sq.mts. ( 348 Sq.ft. ) | 2 | |
| Office space | 18.02 Sq.mts. ( 194 Sq.ft. ) | 2 | |
| Office space | 18.04 Sq.mts. ( 194 Sq.ft. ) | 1 | |
| Office space | 18.16 Sq.mts. ( 195 Sq.ft. ) | 1 | |
| Office space | 21.39 Sq.mts. ( 230 Sq.ft. ) | 1 | |
| Office space | 21.4 Sq.mts. ( 230 Sq.ft. ) | 3 | |
| Shop | 21.4 Sq.mts. ( 230 Sq.ft. ) | 1 | |
| Shop | 22.75 Sq.mts. ( 245 Sq.ft. ) | 4 | |
| Shop | 25.92 Sq.mts. ( 279 Sq.ft. ) | 1 | |
| Shop | 25.93 Sq.mts. ( 279 Sq.ft. ) | 2 | |
| Shop | 39.86 Sq.mts. ( 429 Sq.ft. ) | 2 | |
302 total apartments / 279 apartments booked. 92% apartments booked. |
| Work Description in Building Tower 1 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Tower 2 | Dec 2022 | 27 | 1 | 0 | 1 | 4 | 0 | 55 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 35.46 Sq.mts. ( 382 Sq.ft. ) | 109 | |
| 1 BHK | 38.1 Sq.mts. ( 410 Sq.ft. ) | 53 | |
| 1 BHK | 38.5 Sq.mts. ( 414 Sq.ft. ) | 54 | |
216 total apartments / 192 apartments booked. 88% apartments booked. |
| Work Description in Building Tower 2 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Damodar Suruchi Developers Pvt. Ltd.
for Project
Uk Iridium
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |