Project overview
Udyam Kunj Chs Redevelopment Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800009775. Udyam Kunj Chs Redevelopment Phase I is located at 400097. This is a On-Going Project being developed by Mahendra Mhatre.
Udyam Kunj Chs Redevelopment Phase I has 1 BHK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 420 to 915 Sq.ft. Carpet. The Project has total 10 of which 5 are currently available for sale.
Udyam Kunj Chs Redevelopment Phase I is being developed on a total land area of 30166 Sq.ft. out of which 4525 Sq.ft. i.e 15% is reserved for recreational purposes. Udyam Kunj Chs Redevelopment Phase I has 1 Wings / Towers Udyam Kunj
| Project | Developer | Location | Possession |
-
Developer:
Mahendra Mhatre
-
Phone:
-
Address:
-
Ground Floor, Jaiguru, Lane No 2, Opp. Little Genius School, Pandurangwadi, 400063
| MAHA REARA No: |
P51800009775 |
| Project Type |
Residential |
| RERA Project Status |
On-Going Project |
| Architect |
Kavaiya And Associates |
| Funding Bank |
Bank of Baroda |
| Proposed Possession |
31 Dec 2017 |
| Revised Possession |
31 Dec 2017 |
| Extended Possession |
31 Dec 2018 |
| Litigations |
Yes |
| Last Modified |
05 May 2019 |
| Last Retrived |
28 Jul 2025 |
Udyam Kunj Chs Redevelopment Phase I QR Code
Udyam Kunj Chs Redevelopment Phase I
MahaRERA - P51800009775
| Type | Area |
| 1 BHK | 39.02 Sq.mts. ( 420 Sq.ft. ) |
| 1 BHK | 44.13 Sq.mts. ( 475 Sq.ft. ) |
| 1 BHK | 45.47 Sq.mts. ( 489 Sq.ft. ) |
| 1 BHK | 47.38 Sq.mts. ( 510 Sq.ft. ) |
| 1 BHK | 47.84 Sq.mts. ( 515 Sq.ft. ) |
| 2 BHK | 56.19 Sq.mts. ( 605 Sq.ft. ) |
| 2 BHK | 66.89 Sq.mts. ( 720 Sq.ft. ) |
| 3 BHK | 84.96 Sq.mts. ( 915 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Udyam Kunj Chs Redevelopment Phase Ilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space90% completed
|
|
Work In Progress |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
Work Completed |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements95% completed
|
|
Work In Progress |
Landscaping & Tree Planting90% completed
|
|
Work In Progress |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)99% completed
|
|
Street Connection In Progress |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains90% completed
|
|
Work In Progress Outside Swd |
Street Lighting90% completed
|
|
Fittings Work In Progress |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting90% completed
|
|
Work In Progress |
Water Supply95% completed
|
|
After Occupation Certificate |
Buildings / Wings in Udyam Kunj Chs Redevelopment Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Udyam Kunj Chs Redevelopment Phase I by Mahendra Mhatrelast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
10
apartments in total
Saleable Area Statistics (Sq. ft.)
6053
Total
Total 10 apartments in project. 5 apartments booked. 50% apartments booked.
Total 6053 Sq.ft. saleable area. 2640 saleable area booked.
44% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Udyam Kunj | Jan 1900 | 9 | 1 | 0 | 1 | 0 | 0 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 39.02 Sq.mts. ( 420 Sq.ft. ) | 1 | |
| 1 BHK | 44.13 Sq.mts. ( 475 Sq.ft. ) | 1 | |
| 1 BHK | 45.47 Sq.mts. ( 489 Sq.ft. ) | 2 | |
| 1 BHK | 47.38 Sq.mts. ( 510 Sq.ft. ) | 1 | |
| 1 BHK | 47.84 Sq.mts. ( 515 Sq.ft. ) | 1 | |
| 2 BHK | 56.19 Sq.mts. ( 605 Sq.ft. ) | 1 | |
| 2 BHK | 66.89 Sq.mts. ( 720 Sq.ft. ) | 1 | |
| 3 BHK | 84.96 Sq.mts. ( 915 Sq.ft. ) | 2 | |
10 total apartments / 5 apartments booked. 50% apartments booked. |
| Work Description in Building Udyam Kunj | Completion |
| Excavation | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Mahendra Mhatre
for Project
Udyam Kunj Chs Redevelopment Phase I
last updated on
28 Jul 2025 as per information obtained from MARA RERA.