Project overview

Udaan Aria is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000008827. Udaan Aria is located at 13-Pt. This is a Ongoing being developed by Udaan Builders And Developers.

Udaan Aria has Temple Apartments with carpet areas ranging from 431 to 431 Sq.ft. Carpet. The Project has total 372 of which 133 are currently available for sale.

Udaan Aria is being developed on a total land area of 132505 Sq.ft. out of which 16933 Sq.ft. i.e 13% is reserved for recreational purposes. Udaan Aria has 7 Wings / Towers A Type 01,B Type 04,C Type 02 Wing A,C Type 02 Wing B,Club House,D Type 3,Temple

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Udaan Aria
  • Location:
  • 13-Pt
  • Const. Stage:
    Ongoing
  • Possession:
    31 Jul 2022
Developer Details

  • Developer:
    Udaan Builders And Developers
  • Phone:
  • Address:
  • Thacker Tower
Project RERA Details
MAHA REARA No: P52000008827
Project Type Others
RERA Project Status Ongoing
Architect Structils Consultants Pvt Ltd
Funding Bank INDUSIND BANK
Proposed Possession 31 Jul 2022
Revised Possession 31 Jul 2022
Extended Possession 31 Jul 2024
Litigations No Litigations
Last Modified 26 May 2025
Last Retrived 28 Jul 2025
Udaan Aria QR Code
Udaan Aria
MahaRERA - P52000008827
Apartment Details & Configuration
TypeArea
1 BHK23.86 Sq.mts. ( 257 Sq.ft. )
1 BHK24.53 Sq.mts. ( 264 Sq.ft. )
1 BHK25.05 Sq.mts. ( 270 Sq.ft. )
1 BHK25.21 Sq.mts. ( 271 Sq.ft. )
1RK18.78 Sq.mts. ( 202 Sq.ft. )
Shop20.01 Sq.mts. ( 215 Sq.ft. )
Shop8.1 Sq.mts. ( 87 Sq.ft. )
Shop16.97 Sq.mts. ( 183 Sq.ft. )
1 BHK20.57 Sq.mts. ( 221 Sq.ft. )
1 BHK21.41 Sq.mts. ( 230 Sq.ft. )
1RK16.56 Sq.mts. ( 178 Sq.ft. )
1RK17.16 Sq.mts. ( 185 Sq.ft. )
1RK17.33 Sq.mts. ( 187 Sq.ft. )
1RK17.57 Sq.mts. ( 189 Sq.ft. )
1 BHK21.1 Sq.mts. ( 227 Sq.ft. )
1 BHK24.16 Sq.mts. ( 260 Sq.ft. )
1 BHK24.42 Sq.mts. ( 263 Sq.ft. )
1 BHK25.1 Sq.mts. ( 270 Sq.ft. )
1 BHK25.54 Sq.mts. ( 275 Sq.ft. )
CLUB HOUSE84 Sq.mts. ( 904 Sq.ft. )
1RK16.29 Sq.mts. ( 175 Sq.ft. )
Temple40 Sq.mts. ( 431 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Udaan Arialast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Club House and Swimming Pool100% completed
95% Complete
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting80% completed
80% Complete
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Na
Solid Waste Management And Disposal
Na
Storm Water Drains90% completed
90% Complete
Na
Street Lighting90% completed
90% Complete
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply90% completed
90% Complete
Na
Buildings / Wings in Udaan Aria
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Udaan Aria by Udaan Builders And Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

132505 Sq. ft.

Project Area

16933 Sq. ft.

Recreational Open Space

Total 7

Wings / Towers in Project

Apartments Statistics

372 apartments in total
Total
372
Booked
239
Available
133

Saleable Area Statistics (Sq. ft.)

82491 Total
Total
82491
Booked
52795
Available
29696
Total 372 apartments in project. 239 apartments booked. 64% apartments booked.
Total 82491 Sq.ft. saleable area. 52795 saleable area booked.
64% area booked.

A Type 01

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A Type 01Jul 202381000140
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.86 Sq.mts. ( 257 Sq.ft. )12
9 Booked75% Booked
75% Booked
1 BHK24.53 Sq.mts. ( 264 Sq.ft. )60
53 Booked88% Booked
88% Booked
72 total apartments / 62 apartments booked. 86% apartments booked.
Work Description in Building A Type 01Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress60% done
60% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress85% done
85% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

B Type 04

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B Type 04Jul 202381000146
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.86 Sq.mts. ( 257 Sq.ft. )23
6 Booked26% Booked
26% Booked
1 BHK24.53 Sq.mts. ( 264 Sq.ft. )25
5 Booked20% Booked
20% Booked
1 BHK25.05 Sq.mts. ( 270 Sq.ft. )8
1 BHK25.21 Sq.mts. ( 271 Sq.ft. )6
6 Booked100% Booked
100% Booked
1RK18.78 Sq.mts. ( 202 Sq.ft. )4
None Booked0% Booked
0% Booked
Shop20.01 Sq.mts. ( 215 Sq.ft. )4
3 Booked75% Booked
75% Booked
Shop8.1 Sq.mts. ( 87 Sq.ft. )6
3 Booked50% Booked
50% Booked
Shop16.97 Sq.mts. ( 183 Sq.ft. )2
1 Booked50% Booked
50% Booked
78 total apartments / 25 apartments booked. 32% apartments booked.
Work Description in Building B Type 04Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress30% done
30% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

C Type 02 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C Type 02 Wing AJul 202381000140
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK20.57 Sq.mts. ( 221 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK21.41 Sq.mts. ( 230 Sq.ft. )1
1 Booked100% Booked
100% Booked
1RK16.56 Sq.mts. ( 178 Sq.ft. )25
19 Booked76% Booked
76% Booked
1RK17.16 Sq.mts. ( 185 Sq.ft. )5
4 Booked80% Booked
80% Booked
1RK17.33 Sq.mts. ( 187 Sq.ft. )6
2 Booked33% Booked
33% Booked
1RK17.57 Sq.mts. ( 189 Sq.ft. )15
8 Booked53% Booked
53% Booked
54 total apartments / 34 apartments booked. 62% apartments booked.
Work Description in Building C Type 02 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress65% done
65% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress55% done
55% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked

C Type 02 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C Type 02 Wing BJul 202381000140
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK21.1 Sq.mts. ( 227 Sq.ft. )4
2 Booked50% Booked
50% Booked
1 BHK24.16 Sq.mts. ( 260 Sq.ft. )24
17 Booked70% Booked
70% Booked
1 BHK24.42 Sq.mts. ( 263 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK25.1 Sq.mts. ( 270 Sq.ft. )20
14 Booked70% Booked
70% Booked
1 BHK25.54 Sq.mts. ( 275 Sq.ft. )5
4 Booked80% Booked
80% Booked
60 total apartments / 42 apartments booked. 70% apartments booked.
Work Description in Building C Type 02 Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress60% done
60% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked

Club House

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Club HouseJul 20231100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
CLUB HOUSE84 Sq.mts. ( 904 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Club HouseCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked

D Type 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D Type 3Jul 202381000140
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK16.29 Sq.mts. ( 175 Sq.ft. )108
76 Booked70% Booked
70% Booked
108 total apartments / 76 apartments booked. 70% apartments booked.
Work Description in Building D Type 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress60% done
60% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress75% done
75% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress45% done
45% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked

Temple

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
TempleJul 20231100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Temple40 Sq.mts. ( 431 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building TempleCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Udaan Builders And Developers
for Project
Udaan Aria
last updated on 28 Jul 2025 as per information obtained from MARA RERA.