Project overview
Tulsi Sagar is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000027987. Tulsi Sagar is located at Plot No 149. This is a New being developed by Tulsi Lifespace Llp.
Tulsi Sagar has 1 BHK & 2 BHK Apartments with carpet areas ranging from 368 to 579 Sq.ft. Carpet. The Project has total 28 of which 28 are currently available for sale.
Tulsi Sagar is being developed on a total land area of 5920 Sq.ft. Tulsi Sagar has 1 Wings / Towers Tulsi Sagar
| Project | Developer | Location | Possession |
-
Project:
Tulsi Sagar
-
Location:
-
Plot No 149
-
Const. Stage:
New
-
Possession:
30 Jun 2024
-
Developer:
Tulsi Lifespace Llp
-
Phone:
-
Address:
-
Satra Plaza Premises Chs
| MAHA REARA No: |
P52000027987 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Amit N Patil Architects |
| Funding Bank |
TAMILNAD MERCANTILE BANK LIMITED |
| Proposed Possession |
30 Jun 2024 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
05 Feb 2025 |
| Last Retrived |
28 Jul 2025 |
Tulsi Sagar QR Code
Tulsi Sagar
MahaRERA - P52000027987
| Type | Area |
| 1 BHK | 34.18 Sq.mts. ( 368 Sq.ft. ) |
| 2 BHK | 53.79 Sq.mts. ( 579 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Tulsi Sagarlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station50% completed
|
|
In Later Scope Of Work |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements10% completed
|
|
In Later Scope Of Work |
Landscaping & Tree Planting
|
|
In Later Scope Of Work |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)45% completed
|
|
In Later Scope Of Work |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains45% completed
|
|
In Later Scope Of Work |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting45% completed
|
|
In Later Scope Of Work |
Water Supply45% completed
|
|
In Later Scope Of Work |
Buildings / Wings in Tulsi Sagar
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tulsi Sagar by Tulsi Lifespace Llplast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
28
apartments in total
Saleable Area Statistics (Sq. ft.)
13257
Total
Total 28 apartments in project. 0 apartments booked. 0% apartments booked.
Total 13257 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Tulsi Sagar | Jun 2024 | 8 | 1 | 0 | 7 | 0 | 0 | 7 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 34.18 Sq.mts. ( 368 Sq.ft. ) | 14 | |
| 2 BHK | 53.79 Sq.mts. ( 579 Sq.ft. ) | 14 | |
28 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Tulsi Sagar | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Tulsi Lifespace Llp
for Project
Tulsi Sagar
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |