Project overview

Tulsi Kalash City is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000014259. Tulsi Kalash City is located at Gut No.142/7, 142/8/1, 142/9, 142/11/A, 142/12/1/A, 142/12/2, 142/12/3/A. This is a New being developed by Trilok Properties Private Limited.

Tulsi Kalash City has OFFICE & SHOP Apartments with carpet areas ranging from 247 to 718 Sq.ft. Carpet. The Project has total 430 of which 247 are currently available for sale.

Tulsi Kalash City is being developed on a total land area of 127230 Sq.ft. Tulsi Kalash City has 8 Wings / Towers Wing - A,Wing - B,Wing - C,Wing - D,Wing - E,Wing - F,Wing - G,Wing - X

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Tulsi Kalash City
  • Location:
  • Gut No.142/7, 142/8/1, 142/9, 142/11/A, 142/12/1/A, 142/12/2, 142/12/3/A
  • Const. Stage:
    New
  • Possession:
    30 Dec 2024
Developer Details

  • Developer:
    Trilok Properties Private Limited
  • Phone:
  • Address:
  • V Times Square
Project RERA Details
MAHA REARA No: P52000014259
Project Type Residential / Group Housing
RERA Project Status New
Architect Destination Architects Interior Designs
Funding Bank BANK OF BARODA
Proposed Possession 30 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 03 Nov 2018
Last Retrived 28 Jul 2025
Tulsi Kalash City QR Code
Tulsi Kalash City
MahaRERA - P52000014259
Apartment Details & Configuration
TypeArea
1 BHK22.61 Sq.mts. ( 243 Sq.ft. )
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )
1 BHK26.29 Sq.mts. ( 283 Sq.ft. )
1 BHK26.37 Sq.mts. ( 284 Sq.ft. )
2 BHK31.08 Sq.mts. ( 335 Sq.ft. )
2 BHK32.15 Sq.mts. ( 346 Sq.ft. )
2 BHK35.96 Sq.mts. ( 387 Sq.ft. )
2 BHK31.19 Sq.mts. ( 336 Sq.ft. )
2 BHK32.16 Sq.mts. ( 346 Sq.ft. )
1 BHK24.63 Sq.mts. ( 265 Sq.ft. )
1 BHK25.6 Sq.mts. ( 276 Sq.ft. )
1 BHK26.22 Sq.mts. ( 282 Sq.ft. )
2 BHK36.01 Sq.mts. ( 388 Sq.ft. )
1 BHK25.18 Sq.mts. ( 271 Sq.ft. )
1 BHK25.69 Sq.mts. ( 277 Sq.ft. )
1 BHK26.23 Sq.mts. ( 282 Sq.ft. )
2 BHK31.18 Sq.mts. ( 336 Sq.ft. )
2 BHK36.27 Sq.mts. ( 390 Sq.ft. )
1 BHK24.15 Sq.mts. ( 260 Sq.ft. )
2 BHK36.23 Sq.mts. ( 390 Sq.ft. )
1 BHK26.47 Sq.mts. ( 285 Sq.ft. )
1 RK17.42 Sq.mts. ( 188 Sq.ft. )
1 RK20.84 Sq.mts. ( 224 Sq.ft. )
OFFICE35.77 Sq.mts. ( 385 Sq.ft. )
OFFICE47.89 Sq.mts. ( 515 Sq.ft. )
OFFICE57.95 Sq.mts. ( 624 Sq.ft. )
OFFICE66.75 Sq.mts. ( 718 Sq.ft. )
SHOP22.99 Sq.mts. ( 247 Sq.ft. )
SHOP26.71 Sq.mts. ( 288 Sq.ft. )
SHOP27.32 Sq.mts. ( 294 Sq.ft. )
SHOP27.37 Sq.mts. ( 295 Sq.ft. )
SHOP28.11 Sq.mts. ( 303 Sq.ft. )
SHOP28.86 Sq.mts. ( 311 Sq.ft. )
SHOP30.95 Sq.mts. ( 333 Sq.ft. )
SHOP31.7 Sq.mts. ( 341 Sq.ft. )
SHOP34.05 Sq.mts. ( 367 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Tulsi Kalash Citylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Not Commenced. Meter Rrom Will Be Provided As Per
Energy management
Na
Fire Protection And Fire Safety Requirements
Not Commenced. Will Be Provided As Per Cfo Noc
Landscaping & Tree Planting
Not Commenced. Will Be Provided As Per Dcpr For Re
Open Parking
58 Nos.
Sewerage (Chamber, Lines, Septic Tank , STP)
Not Commenced. Will Be Provided As Per Dcpr For Re
Solid Waste Management And Disposal
Na
Storm Water Drains
Not Commenced. Will Be Provided As Per Dcpr For Re
Street Lighting
Not Commenced. Will Be Provided As Per Dcpr For Re
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Not Commenced. Will Be Provided As Per Dcpr For Re
Buildings / Wings in Tulsi Kalash City
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tulsi Kalash City by Trilok Properties Private Limitedlast updated on 28 Jul 2025 as per information obtained from MARA RERA.

127230 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

430 apartments in total
Total
430
Booked
183
Available
247

Saleable Area Statistics (Sq. ft.)

124528 Total
Total
124528
Booked
54445
Available
70083
Total 430 apartments in project. 183 apartments booked. 42% apartments booked.
Total 124528 Sq.ft. saleable area. 54445 saleable area booked.
44% area booked.

Wing - A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - ADec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.61 Sq.mts. ( 243 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )14
9 Booked64% Booked
64% Booked
1 BHK26.29 Sq.mts. ( 283 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK26.37 Sq.mts. ( 284 Sq.ft. )7
5 Booked71% Booked
71% Booked
2 BHK31.08 Sq.mts. ( 335 Sq.ft. )7
2 Booked28% Booked
28% Booked
2 BHK32.15 Sq.mts. ( 346 Sq.ft. )7
2 Booked28% Booked
28% Booked
2 BHK35.96 Sq.mts. ( 387 Sq.ft. )7
7 Booked100% Booked
100% Booked
63 total apartments / 42 apartments booked. 66% apartments booked.
Work Description in Building Wing - ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - BDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )14
12 Booked85% Booked
85% Booked
1 BHK26.37 Sq.mts. ( 284 Sq.ft. )7
5 Booked71% Booked
71% Booked
2 BHK31.19 Sq.mts. ( 336 Sq.ft. )7
2 BHK32.16 Sq.mts. ( 346 Sq.ft. )7
4 Booked57% Booked
57% Booked
2 BHK35.96 Sq.mts. ( 387 Sq.ft. )7
7 Booked100% Booked
100% Booked
49 total apartments / 34 apartments booked. 69% apartments booked.
Work Description in Building Wing - BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - CDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.63 Sq.mts. ( 265 Sq.ft. )14
11 Booked78% Booked
78% Booked
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )7
1 BHK25.6 Sq.mts. ( 276 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )14
10 Booked71% Booked
71% Booked
1 BHK26.22 Sq.mts. ( 282 Sq.ft. )7
2 BHK31.19 Sq.mts. ( 336 Sq.ft. )7
3 Booked42% Booked
42% Booked
2 BHK36.01 Sq.mts. ( 388 Sq.ft. )7
5 Booked71% Booked
71% Booked
63 total apartments / 37 apartments booked. 58% apartments booked.
Work Description in Building Wing - CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress40% done
40% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - DDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.63 Sq.mts. ( 265 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK25.18 Sq.mts. ( 271 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )7
1 BHK25.69 Sq.mts. ( 277 Sq.ft. )7
6 Booked85% Booked
85% Booked
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )14
4 Booked28% Booked
28% Booked
1 BHK26.23 Sq.mts. ( 282 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK31.18 Sq.mts. ( 336 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK36.27 Sq.mts. ( 390 Sq.ft. )7
4 Booked57% Booked
57% Booked
63 total apartments / 33 apartments booked. 52% apartments booked.
Work Description in Building Wing - DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - EDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.15 Sq.mts. ( 260 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK25.31 Sq.mts. ( 272 Sq.ft. )7
2 Booked28% Booked
28% Booked
1 BHK26.08 Sq.mts. ( 281 Sq.ft. )14
5 Booked35% Booked
35% Booked
2 BHK31.18 Sq.mts. ( 336 Sq.ft. )7
2 Booked28% Booked
28% Booked
2 BHK32.16 Sq.mts. ( 346 Sq.ft. )7
5 Booked71% Booked
71% Booked
2 BHK36.23 Sq.mts. ( 390 Sq.ft. )7
3 Booked42% Booked
42% Booked
49 total apartments / 20 apartments booked. 40% apartments booked.
Work Description in Building Wing - ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - FDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.47 Sq.mts. ( 285 Sq.ft. )14
1 RK17.42 Sq.mts. ( 188 Sq.ft. )28
None Booked0% Booked
0% Booked
1 RK20.84 Sq.mts. ( 224 Sq.ft. )14
56 total apartments / 3 apartments booked. 5% apartments booked.
Work Description in Building Wing - FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Wing - G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - GDec 20238101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.47 Sq.mts. ( 285 Sq.ft. )14
5 Booked35% Booked
35% Booked
1 RK17.42 Sq.mts. ( 188 Sq.ft. )28
1 RK20.84 Sq.mts. ( 224 Sq.ft. )14
4 Booked28% Booked
28% Booked
56 total apartments / 11 apartments booked. 19% apartments booked.
Work Description in Building Wing - GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress75% done
75% Booked
Stilt Floor
Completed 100% done
100% Booked

Wing - X

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - XDec 20234101001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
OFFICE35.77 Sq.mts. ( 385 Sq.ft. )12
None Booked0% Booked
0% Booked
OFFICE47.89 Sq.mts. ( 515 Sq.ft. )3
None Booked0% Booked
0% Booked
OFFICE57.95 Sq.mts. ( 624 Sq.ft. )3
None Booked0% Booked
0% Booked
OFFICE66.75 Sq.mts. ( 718 Sq.ft. )3
None Booked0% Booked
0% Booked
SHOP22.99 Sq.mts. ( 247 Sq.ft. )2
None Booked0% Booked
0% Booked
SHOP26.71 Sq.mts. ( 288 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP27.32 Sq.mts. ( 294 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP27.37 Sq.mts. ( 295 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP28.11 Sq.mts. ( 303 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP28.86 Sq.mts. ( 311 Sq.ft. )1
1 Booked100% Booked
100% Booked
SHOP30.95 Sq.mts. ( 333 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP31.7 Sq.mts. ( 341 Sq.ft. )1
None Booked0% Booked
0% Booked
SHOP34.05 Sq.mts. ( 367 Sq.ft. )1
None Booked0% Booked
0% Booked
31 total apartments / 3 apartments booked. 9% apartments booked.
Work Description in Building Wing - XCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Trilok Properties Private Limited
for Project
Tulsi Kalash City
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation