Project overview

Tribeca is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800009815. Tribeca is located at F/692. This is a Ongoing being developed by Nestor Builders & Developers Private Limited.

Tribeca has 1 BHK, 2 BHK, 2.5 BHK, 3 BHK & 7 BHK Apartments with carpet areas ranging from 1085 to 1006 Sq.ft. Carpet. The Project has total 21 of which 3 are currently available for sale.

Tribeca is being developed on a total land area of 6660 Sq.ft. Tribeca has 1 Wings / Towers Tribeca

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Tribeca
  • Location:
  • F/692
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Nestor Builders & Developers Private Limited
  • Phone:
  • Address:
  • Nestor Court
Project RERA Details
MAHA REARA No: P51800009815
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sp Associates
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession 31 Dec 2019
Litigations No Litigations
Last Modified 08 Feb 2019
Last Retrived 26 Jul 2025
Tribeca QR Code
Tribeca
MahaRERA - P51800009815
Apartment Details & Configuration
TypeArea
1 BHK48.07 Sq.mts. ( 517 Sq.ft. )
1 BHK53.65 Sq.mts. ( 577 Sq.ft. )
2 BHK60.68 Sq.mts. ( 653 Sq.ft. )
2 BHK61.24 Sq.mts. ( 659 Sq.ft. )
2 BHK61.51 Sq.mts. ( 662 Sq.ft. )
2 BHK70.37 Sq.mts. ( 757 Sq.ft. )
2.5 BHK76.5 Sq.mts. ( 823 Sq.ft. )
3 BHK93.5 Sq.mts. ( 1006 Sq.ft. )
3 BHK100.79 Sq.mts. ( 1085 Sq.ft. )
7 BHK210.6 Sq.mts. ( 2267 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Tribecalast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Tribeca
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tribeca by Nestor Builders & Developers Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

6660 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

21 apartments in total
Total
21
Booked
18
Available
3

Saleable Area Statistics (Sq. ft.)

18217 Total
Total
18217
Booked
14962
Available
3255
Total 21 apartments in project. 18 apartments booked. 85% apartments booked.
Total 18217 Sq.ft. saleable area. 14962 saleable area booked.
82% area booked.

Tribeca

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
TribecaDec 2018131110029
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK48.07 Sq.mts. ( 517 Sq.ft. )2
2 Booked100% Booked
100% Booked
1 BHK53.65 Sq.mts. ( 577 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK60.68 Sq.mts. ( 653 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK61.24 Sq.mts. ( 659 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK61.51 Sq.mts. ( 662 Sq.ft. )2
2 Booked100% Booked
100% Booked
2 BHK70.37 Sq.mts. ( 757 Sq.ft. )5
5 Booked100% Booked
100% Booked
2.5 BHK76.5 Sq.mts. ( 823 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK93.5 Sq.mts. ( 1006 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK100.79 Sq.mts. ( 1085 Sq.ft. )5
2 Booked40% Booked
40% Booked
7 BHK210.6 Sq.mts. ( 2267 Sq.ft. )1
1 Booked100% Booked
100% Booked
21 total apartments / 18 apartments booked. 85% apartments booked.
Work Description in Building TribecaCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Nestor Builders & Developers Private Limited
for Project
Tribeca
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation