Project overview

Transcon Triumph Tower 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005361. Transcon Triumph Tower 1 is located at Cr5cpp+N78iy3lb3ve4nsw==. This is a Ongoing being developed by Transcon Developers Pvt. Ltd..

Transcon Triumph Tower 1 has 2 BHK, 3 BHK, 3 BHK Type 1, 3 BHK Type 2 & 4 BHK Apartments with carpet areas ranging from 1281 to 813 Sq.ft. Carpet. The Project has total 210 of which 1 are currently available for sale.

Transcon Triumph Tower 1 is being developed on a total land area of 13819 Sq.ft. Transcon Triumph Tower 1 has 1 Wings / Towers Tower 1

ProjectDeveloperLocationPossession
Ramrajya - Neptune Ekansh DNeptune Developers LimitedQekaat8jdxie5+3Sq0v8lsa0c8s/63I70cztszqzd7nnym5ff2jfqew3pep4wnrn3fju8af1a9oyf6vwkdwkoa==30-12-2023 00:00:00
Ramrajya - Neptune Ekansh CNeptune Developers LimitedHofvqp+Jiyr3bsw0sm1dfjlrz+Z9w6sruuhyhsnj7vn1fqim6i1awaq+2Qusvdbs30-09-2023 00:00:00
Ramrajya - Neptune Ekansh FNeptune Developers LimitedQekaat8jdxie5+3Sq0v8lsa0c8s/63I70cztszqzd7nnym5ff2jfqew3pep4wnrn3fju8af1a9oyf6vwkdwkoa==30-12-2023 00:00:00
Ramrajya - Neptune Ekansh BNeptune Developers LimitedQekaat8jdxie5+3Sq0v8lsa0c8s/63I70cztszqzd7nnym5ff2jfqew3pep4wnrn3fju8af1a9oyf6vwkdwkoa==30-09-2023 00:00:00
Ramrajya - Neptune Udaan ENeptune Developers LimitedVxdgi4hvn2zibefacczutljdhdom08gnyjv04gw87ssutgsp4scc3cjtg1iazhsp30-12-2023 00:00:00
Ramrajya - Neptune Jal Tarang ENeptune Developers Limited40Kbfcf2t/Zzxmdey13upwlrgi8n6zitfoxkzllmcib9dao7+I8n2dvn/4Pxmt+Ssw/4Kml9rlgkr+Yxki4udq==30-12-2023 00:00:00
Ramrajya - Neptune Udaan BNeptune Developers LimitedVxdgi4hvn2zibefacczutgh8iov730pszx495izdqn9exhq3rsugj/Grkrjfhqvf30-12-2023 00:00:00
Ramrajya - Neptune Udaan DNeptune Developers LimitedVxdgi4hvn2zibefacczutcserw3ckpf6o14v8l0cxuschbebeogsw69kuptkmc5zsbpzluziad2bzzjlohv1dq==30-12-2023 00:00:00
Ramrajya - Neptune Jal Tarang DNeptune Developers Limited40Kbfcf2t/Zzxmdey13upwlrgi8n6zitfoxkzllmcib9dao7+I8n2dvn/4Pxmt+Ssw/4Kml9rlgkr+Yxki4udq==30-12-2023 00:00:00
AtlantisCrystal Pride Developers8Yu0dv8zn/J20iltfy4l1w==30-12-2025 00:00:00
Transcon Triumph Tower 1Transcon Developers Pvt. Ltd.Cr5cpp+N78iy3lb3ve4nsw==30-12-2022 00:00:00
Yura Business ParkYura Business Park Private LimitedB68b2ydaektamijl0mjyjw==30-12-2021 00:00:00
Vengurlekars ChaitraVengurlekars Shreesai Builders And Developers Private Limited2Iutcixn+Hqsa5acofkekw==31-12-2019 00:00:00
Elite ResidenceOdin EnterpriseIph4p2m4hqwsaaolvo3cn4l8yno8pt5hkycnbxto4zrjmirghplbx8mbfkuuoxzz30-12-2024 00:00:00
Shikhar AOrbit Ventures Developers/6D5w0llv/S+Ww8ctq8laqnlxexpcojbu5mcx5klshc=31-12-2019 00:00:00
Swiz HeightsMohid Construction CoTihzif28rbhmjk1+7U86qw==31-12-2019 00:00:00
Azad Nagar Kedar Darshan ChslPrathamesh Krupa Buildcon Private LimitedKlwbm1sidmnpgtsd0tyghg==19-08-2018 00:00:00
Shraddha WoodsTouchwood DevelopersOff Cessar Road31-12-2021 00:00:00
Mircale HeritageCitimake Builders Private Limtied400102, Mumbai Suburban30-06-2020 00:00:00
Solaris Titanium TowersSolaris Developers Private LimitedShl6btn0kkacdjpukawhla==31-12-2019 00:00:00
Vision Heights Wing AFiona Realty Private LimitedYnyvr4ysur3p3jrl6lgxva==30-12-2025 00:00:00
Prime BuildersPrime Builders And DevelopersPebo/Vpaboyvoe7ceu4jwa==30-11-2020 00:00:00
Smgk Associate Residency Wing B Phase 1 -1St To 16Th FloorsVastu Shilpa Complex Designers Pvt LtdCyhfin5sqw3m6t4yfkwusvzv+Ezp/Fv/Ebe0sbcruae=31-12-2018 00:00:00
Ocean Heights By Midcity GroupM/S Midcity Heights400102, Mumbai Suburban31-10-2017 00:00:00
CosmicMonarch And Querish BuildersMumbai Suburban, 40005331-12-2017 00:00:00
Redevelopment Of Sultanabad Darshan Chs LtdAftab Constructions1I+Pxr3b5fz4r5pscxutdktsyz1i7tnjj+Znysuaokm=31-12-2017 00:00:00
Labh Samarth HeightM.V. Labh AssociatesKgpqcirrdbr+Q42kncotemlhunvwdevmriyvuseagrs=31-12-2018 00:00:00
PROPOSED REDEVELOPMENT OF CTS NO 52, SHAGUFA MUNICIPAL EMPLOYEES CHS LTD, JOGESHWARI WESTAFTAB CONSTRUCTIONSMumbai Suburban, 40010231-12-2019 00:00:00
SorrentoSahaj Ankur DevelopersAlrik/Sqdfubbwjcus+Z6tkibdpj791g4xt6fgjti6kugjh8b3n95dpu5m4jt5gvfq3b9gi2nqdktl7djfyy7a==31-12-2018 00:00:00
Al MarjaanTown DevelopersHgkfjvoeu4neoy8syxiogk/0Ibkto0wnl+Td7um84kwqwiyhfrkhcnavf5eazenv31-12-2018 00:00:00
Runwal Elegante - Tower ARunwal Developers Pvt Ltd3Aueva70q4o3v2ump4g1iothxaiyqoqpbpti8sgjfak=31-03-2019 00:00:00
A.R AvenueAibani EnterpriseN6swh4jhqpy27nivydnohw==31-12-2019 00:00:00
Maredian HeightsMaredian Realtors Pvt. Ltd.Qlotj8nahzw8303wyhsvja==30-12-2024 00:00:00
Vishvaprem Co-Operative Housing Society LimitedDipti Home Makers Pvt LtdYgxpicx2pfzu9hl71ex7mq==30-06-2018 00:00:00
Stadium ViewAcme Avenue Infrastructure Pvt. Ltd.76Zsfgsvwskym9k4q7ecka==31-12-2019 00:00:00
Key Tech ParkM/S KeytechJmtsplup+Cs3wvl1mspqdq==30-12-2026 00:00:00
Antariksh AlbaAntariksh Infraprojects LlpI0css1debp0vuuxo6f2xkq==31-12-2018 00:00:00
Jms Business CentreJms RealtyDpzkplji9isv8dofnde4wq==30-12-2021 00:00:00
Woods Platina Wing B- Ebony TowerSukoon Developers Pvt LtdX5mt67dygupzhm5dphgbafcgd/Kp/Mpjox5lbzvkguaytwecugec0qqk3aan90i/31-07-2022 00:00:00
Laxmi Business ParkLaxmi Industrial EstateOv4ajidjqojrvkm2qcwn3g==31-12-2018 00:00:00
La AltezaEmerald DevelopersOwsefrvipky+C9yhjwr4junkbpfawgk91azw8xeeqvw=30-12-2021 00:00:00
Uk SangfroidKeemaya Build Private LimitedFkwenrwutdz/Pjuihuo+/Tfh+L+Qpkq+Hqisa89qj2/Kvth8mh1an3vrtfpvxnuz31-12-2019 00:00:00
Kush SapphireKush Buildcon LlpDf4rh6f3cid7aaczxkooaq==31-12-2018 00:00:00
CRYSTAL HEIGHTSCRYSTAL CONSTRUCTIONSMumbai Suburban, 40010231-07-2022 00:00:00
Morya GrandNakta Investment Pvt. Ltd.A3zs+W5lwvb7gew4vhzgjw==31-01-2022 00:00:00
Heritage ParkVelentine DevelopersKtrsshxqoztxfagrxncxpa==31-07-2022 00:00:00
Arc OneChandra Gupta Estates Private LimitedTinxgtwaryauf3sbzkvl7g==31-12-2026 00:00:00
Linkbay Residences Phase IPortsmouth Buildcon Private LimitedVce+Sbnp4x4aouoevnxxzkgvwuss6at40xy34gugnbg=31-10-2028 00:00:00
Roswalt ZaidenA S Hightech LlpBiwlshd0y/5Agkqegbp2vuitt7hvnfnwqclogx3mhv0e5chui/G2skeibrmpqkfslyqn82a51/B+Gbyu+Ohqe5l1zxxii3sd2exb1ggvisc=31-12-2028 00:00:00
Golden Heights @ Smgk UrbanaSmgk Developers Pvt. Ltd.Znzhlo5+Dpkzqz+Txo/K3ygve52fcmjjoprss5wpudauktmnq3tr3j45/7Rvyucp31-01-2023 00:00:00
Fatemid AvenueOpal Builders Pvt LtdMumbai Suburban, 40010231-12-2017 00:00:00
Rahimabad ChsImtiyaz QureshiMumbai Suburban, 40010231-07-2020 00:00:00
A. H. HeightsA.H. ConstructionsPnauc+Tvdykqnjheb7v7ig==16-08-2022 00:00:00
Agaa ResidencyAgaa EnterprisesZbz2itosupbzrepvpzpstg==30-12-2022 00:00:00
Agarwal PalazzoBalaji DevelopersTua8yazy3yjzzyd9m+Qphg==30-12-2023 00:00:00
Proposed Residential Cum Commercial Redevelopment Of Apna Ghar Unit No. 9 ChslBharat Realty Venture Private LimitedUa5ahbpfqkydrgvzzppf+J/T3sifauho8yl9liveguvjkqdjy/8Hwurds4/45Rpx30-09-2030 00:00:00
Avant Heritage - VAbhishek Properties (I) Pvt LtdDqan2sdupx1vcvkr5hm1wlw5y66bdqa/0Oq0gv9pujmbamnlrquj52eu1hoimx8uyp+Afviar4atx43tuqhreixlscyb0/Z4gdqqrynv18o=31-12-2027 00:00:00
Mittal CoveVgm Projects LlpRihnbvwxewmj1bkthyrzxa==30-06-2023 00:00:00
Pakeeza HeightsThe Enterprise5Tj+Cn4lmwxlgewbljz30vr4d7eocrplzyixjmiuuolz2ajexgrey2emqz8pmtry30-06-2024 00:00:00
SignatureVeer Savarkar Projects Private LimitedZoaluekgpr30++4Fzjv+Aapww64ukux50vcwqwsqi4s=30-06-2025 00:00:00
Pearl PlatinumChandiwala EnterprisesQeolbdwdqdqfsqgv+2Xz9h3peugwihe1k3n4ikpwdgeiyrvoucp7c2smq+7U6neftnyrgyeggj58zkkaflezaq==30-12-2023 00:00:00
Smgk Associate Residency Wing B Phase 2 17Th To 20Th FloorsVastu Shilpa Complex Designers Pvt LtdI4egq55x2fgayf2narglm5iqckbyz1/9Kdnayfddk5w=31-12-2019 00:00:00
Lashkaria EmpressLashkaria Housing & Infrastructure Private LimitedEjrexvmyavqsfkyh7reppexeq/M1ucnj/Wgkwktphfxdraxm9xejba4cskydqn7xvqitu9btkbpipxgzpvzsvw==30-06-2019 00:00:00
Level - The ResidencesM/S Siroya KeystoneDonxk9pietbt+Dep3l3kehuyylbi7yzhvenorssuar9dpcbf5o/Ulqs7bzojn0czztkvxgsrtcip3elxffhhca==30-12-2023 00:00:00
Andheri EktaMumbai Shelter Combines LlpVkjc6lrzw2y5evgalm4sk1vmnxrdn21deatje67dqvggeexeno+Txyqpzvmsn2qp30-09-2018 00:00:00
Sultanbad SadanFortune Realty400102, Mumbai Suburban31-05-2022 00:00:00
El SignoraParas Builders (1985)Off New Link Road31-12-2022 00:00:00
Dilkap VictorGorkap Properties & Investments Pvt. LtdBr97lnzmh7ac7hxwmewdzg==31-12-2019 00:00:00
Ravikiran Co-Operative Hsg Soc Ltd.Westin Developers Pvt. Ltd400053, Mumbai City01-06-2018 00:00:00
A R B HeightsArb DevelopersG35cmjvgsyhyws7ixgrj3qcbfcwegkyikeiqgw/Dduvxdn28fhkeifxcphap23ru30-12-2022 00:00:00
Millennium Court Co-Op. Soc. LtdMillennium Court Co Operative Housing Society Ltd.1Yk4e0xorfso6ixaceuinq==31-12-2018 00:00:00
MehrabadKhandwani Export Pvt LtdQs80/Jpawqwuygzxrrr5wq==30-12-2022 00:00:00
Makskap CentreDilip Estate & Town Planners Pvt LtdXolywd526vbukd0wz8k6vqgwwcoxsn9odpsiymcngok=31-12-2019 00:00:00
MASS ZAINAB HEIGHTSMASS ZIA DEVELOPMENT CORPORATIONMumbai Suburban31-05-2025 00:00:00
Gsa GrandeurG S A Constructions2Cwyjnq/Uhlalw7g1irqha==30-06-2021 00:00:00
Parinee IParinee Realty Private LimitedKkb39qfl7gzhse6k/B9gofojay9ckq2txalgympkot8=30-06-2021 00:00:00
LamorSankalp Siddhi Developers Pvt LtdTqjap8bxnuzum1bdpzykgr07xf6v8r/Urb+Hjlbqpr4vn0y0n2+J/Igqnz1ux2r8mw4hyxoyussiwqs6o2azd5+Rimoqtil38b3bwi8p2xo=30-06-2022 00:00:00
SHIKHAR BOrbit Ventures Developers400102, Mumbai Suburban31-12-2022 00:00:00
Cosmopolis Wing BJiten Agroland & Farm Private LimitedCeiduteepe8sxd3dm9zulbhc1ilictutfjodfo0gdro=31-03-2026 00:00:00
Live Well Chs LtdIcon ConstructionsFg1920geui+Pnsdzn08ydw==31-12-2029 00:00:00
Mk GraciaA R Amboli Developers Private LimitedRp2mpsjnomtgfg1faf3sunk7dqnfn6ahza8f+S9nwcjtf5qxtao/71Mfq4408x3na6n+Mbutdcup40bznvjkixj6yvbd5ywqjfpa4jau0nghfixtnxxyd3rjtoq77adyvaro3ylhvpdu2tmj9nsaua==31-12-2025 00:00:00
Azad Nagar Ashta Vinayak Chs LtdRajvi Builders And DevelopersPubq21acw84q8oenprqwtq==31-07-2022 00:00:00
Roswalt Shatataraka (Unit A) ChslRoswalt Realty Private Limited28-09-2028 00:00:00
The Westpark Phase-1Westpark Developers Private Limited30-06-2032 00:00:00
Gurukrupa EkamGurukrupa Realcon Infrabuild Llp25-04-2029 00:00:00
Khandelwal TattvaShree Krishna Sai Development Corporation31-12-2030 00:00:00
Dream SignaturePrime Realtors30-06-2030 00:00:00
Linkbay Residences Phase Ii Wing BPortsmouth Buildcon Private Limited And Shiv Infra Vision Private Limited30-06-2030 00:00:00
Project Details
  • Project:
    Transcon Triumph Tower 1
  • Location:
  • Cr5cpp+N78iy3lb3ve4nsw==
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2022
Developer Details

  • Developer:
    Transcon Developers Pvt. Ltd.
  • Phone:
  • Address:
  • Transcon Triumph
Project RERA Details
MAHA REARA No: P51800005361
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Shri Suresh A. Gaikwad - Skytech Consultants
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2022
Revised Possession 30 Dec 2022
Extended Possession
Litigations No Litigations
Last Modified 11 Aug 2017
Last Retrived 13 Feb 2026
Transcon Triumph Tower 1 QR Code
Transcon Triumph Tower 1
MahaRERA - P51800005361
Apartment Details & Configuration
TypeArea
2 BHK75.53 Sq.mts. ( 813 Sq.ft. )
3 BHK124.95 Sq.mts. ( 1345 Sq.ft. )
3 BHK Type 1119.01 Sq.mts. ( 1281 Sq.ft. )
3 BHK Type 2124.12 Sq.mts. ( 1336 Sq.ft. )
4 BHK194.81 Sq.mts. ( 2097 Sq.ft. )
4 BHK203.18 Sq.mts. ( 2187 Sq.ft. )
4 BHK269.5 Sq.mts. ( 2901 Sq.ft. )
4 BHK276.94 Sq.mts. ( 2981 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Transcon Triumph Tower 1last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space20% completed
20% Complete
Will Be Handed Over To Apex Body
Air Conditioned Triple Height Grand Entrance Lobby100% completed
95% Complete
Completed
Barbeque Corner
To Be Handed Over To Apex Body
CCTV Monitoring of Common Areas
To Be Handed Over To Apex Body
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station22% completed
22% Complete
To Be Handed Over To Apex Body
Energy management2% completed
2% Complete
As Per Moef To Be Handed Over To Apex Body
Fire Protection And Fire Safety Requirements77% completed
77% Complete
As Per Cfo To Be Handed Over To Apex Body
Fitness Center
To Be Handed Over To Apex Body
Landscaping & Tree Planting20% completed
20% Complete
To Be Handed Over To Apex Body
Multipurpose Court
To Be Handed Over To Apex Body
Open Parking
In Progress
Servant Washroom at Mid Landing of 1 Staircase
To Be Handed Over After Oc
Sewerage (Chamber, Lines, Septic Tank , STP)77% completed
77% Complete
Sewage Lines Have Been Done In Access Road Portion
Solid Waste Management And Disposal77% completed
77% Complete
To Be Handed Over To Apex Body
Storm Water Drains77% completed
77% Complete
Swd To Be Handed Over To Apex Body
Street Lighting100% completed
95% Complete
To Be Handed Over To Apex Body
Swimming Pool
To Be Handed Over To Apex Body
Tot Lot Area
To Be Handed Over To Apex Body
Treatment And Disposal Of Sewage And Sullage Water77% completed
77% Complete
As Per Moef Requirements To Be Handed Over To Apex
Water Conservation, Rain water Harvesting77% completed
77% Complete
Rwh To Be Handed Over To Apex Body
Water Supply77% completed
77% Complete
Bmc Water Connection To Be Handed Over To Apexbody
Buildings / Wings in Transcon Triumph Tower 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Transcon Triumph Tower 1 by Transcon Developers Pvt. Ltd.last updated on 13 Feb 2026 as per information obtained from MARA RERA.

13819 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

210 apartments in total
Total
210
Booked
209
Available
1

Saleable Area Statistics (Sq. ft.)

244391 Total
Total
244391
Booked
243110
Available
1281
Total 210 apartments in project. 209 apartments booked. 99% apartments booked.
Total 244391 Sq.ft. saleable area. 243110 saleable area booked.
99% area booked.

Tower 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tower 1Dec 20213211040411
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK75.53 Sq.mts. ( 813 Sq.ft. )98
98 Booked100% Booked
100% Booked
3 BHK124.95 Sq.mts. ( 1345 Sq.ft. )6
6 Booked100% Booked
100% Booked
3 BHK Type 1119.01 Sq.mts. ( 1281 Sq.ft. )55
54 Booked98% Booked
98% Booked
3 BHK Type 2124.12 Sq.mts. ( 1336 Sq.ft. )33
33 Booked100% Booked
100% Booked
4 BHK194.81 Sq.mts. ( 2097 Sq.ft. )4
4 Booked100% Booked
100% Booked
4 BHK203.18 Sq.mts. ( 2187 Sq.ft. )10
10 Booked100% Booked
100% Booked
4 BHK269.5 Sq.mts. ( 2901 Sq.ft. )1
1 Booked100% Booked
100% Booked
4 BHK276.94 Sq.mts. ( 2981 Sq.ft. )3
3 Booked100% Booked
100% Booked
210 total apartments / 209 apartments booked. 99% apartments booked.
Work Description in Building Tower 1Completion
Basement (if any)
work-in-progress85% done
85% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress57% done
57% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress57% done
57% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress76% done
76% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress76% done
76% Booked
Plinth
work-in-progress85% done
85% Booked
Podiums (if any)
work-in-progress99% done
99% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress30% done
30% Booked
Sanitary Fittings within the flats / premises
work-in-progress30% done
30% Booked
Slabs of Super Structure
work-in-progress95% done
95% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress60% done
60% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress60% done
60% Booked
Stilt Floor
work-in-progress86% done
86% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress85% done
85% Booked
X number of Podiums
work-in-progress99% done
99% Booked
X number of Slabs of Super Structure
work-in-progress95% done
95% Booked
Channel Partners
Channel Partners Registered by Developer
Transcon Developers Pvt. Ltd.
for Project
Transcon Triumph Tower 1
last updated on 13 Feb 2026 as per information obtained from MARA RERA.
Name Company Location Mobile Designation