Project overview

Tisai Srushti Phase 1 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700046320. Tisai Srushti Phase 1 is located at S No 4, H No 3A. This is a New being developed by Vvks Developers Private Limited.

Tisai Srushti Phase 1 has 1 BHK Apartments with carpet areas ranging from 409 to 431 Sq.ft. Carpet. The Project has total 84 of which 77 are currently available for sale.

Tisai Srushti Phase 1 is being developed on a total land area of 25295 Sq.ft. Tisai Srushti Phase 1 has 2 Wings / Towers Tisai Srushti Phase 1 Wing A,Tisai Srushti Phase 1 Wing B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Tisai Srushti Phase 1
  • Location:
  • S No 4, H No 3A
  • Const. Stage:
    New
  • Possession:
    31 Dec 2027
Developer Details

  • Developer:
    Vvks Developers Private Limited
  • Phone:
  • Address:
  • Nandivali
Project RERA Details
MAHA REARA No: P51700046320
Project Type Residential / Group Housing
RERA Project Status New
Architect Madan And Associates
Funding Bank CENTRAL BANK OF INDIA
Proposed Possession 31 Dec 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 22 Jun 2022
Last Retrived 26 Jul 2025
Tisai Srushti Phase 1 QR Code
Tisai Srushti Phase 1
MahaRERA - P51700046320
Apartment Details & Configuration
TypeArea
1 BHK36 Sq.mts. ( 388 Sq.ft. )
1 BHK38 Sq.mts. ( 409 Sq.ft. )
1 BHK40 Sq.mts. ( 431 Sq.ft. )
1 BHK38.09 Sq.mts. ( 410 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Tisai Srushti Phase 1last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station25% completed
25% Complete
To Be Done
Energy management
To Be Done
Fire Protection And Fire Safety Requirements
To Be Done
Landscaping & Tree Planting
Landscapping Is To Be Done And Trees To Be Plant
Open Parking
To Be Done
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank Work To Be Done
Solid Waste Management And Disposal
Na
Storm Water Drains25% completed
25% Complete
To Be Done
Street Lighting25% completed
25% Complete
To Be Done
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting25% completed
25% Complete
To Be Done
Water Supply25% completed
25% Complete
To Be Done
Buildings / Wings in Tisai Srushti Phase 1
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tisai Srushti Phase 1 by Vvks Developers Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

25295 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

84 apartments in total
Total
84
Booked
7
Available
77

Saleable Area Statistics (Sq. ft.)

34674 Total
Total
34674
Booked
2799
Available
31875
Total 84 apartments in project. 7 apartments booked. 8% apartments booked.
Total 34674 Sq.ft. saleable area. 2799 saleable area booked.
8% area booked.

Tisai Srushti Phase 1 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tisai Srushti Phase 1 Wing ADec 2027710150200
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36 Sq.mts. ( 388 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK38 Sq.mts. ( 409 Sq.ft. )14
4 Booked28% Booked
28% Booked
1 BHK40 Sq.mts. ( 431 Sq.ft. )14
None Booked0% Booked
0% Booked
35 total apartments / 7 apartments booked. 20% apartments booked.
Work Description in Building Tisai Srushti Phase 1 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress20% done
20% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress62% done
62% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress20% done
20% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tisai Srushti Phase 1 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tisai Srushti Phase 1 Wing BDec 2026710150200
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38 Sq.mts. ( 409 Sq.ft. )28
None Booked0% Booked
0% Booked
1 BHK38.09 Sq.mts. ( 410 Sq.ft. )14
None Booked0% Booked
0% Booked
1 BHK40 Sq.mts. ( 431 Sq.ft. )7
None Booked0% Booked
0% Booked
49 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Tisai Srushti Phase 1 Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress20% done
20% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress90% done
90% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress42% done
42% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress40% done
40% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress40% done
40% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress20% done
20% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Vvks Developers Private Limited
for Project
Tisai Srushti Phase 1
last updated on 26 Jul 2025 as per information obtained from MARA RERA.