Project overview

Tiara Hills Phase I Bldg No 3, 5 And 2 is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700010406. Tiara Hills Phase I Bldg No 3, 5 And 2 is located at 1351,2 1366 1471,2,3 1483,4,7 1491,3. This is a Ongoing being developed by Pnk Space Development Pvt Ltd.

Tiara Hills Phase I Bldg No 3, 5 And 2 has 1 BHK & 2 BHK Apartments with carpet areas ranging from 295 to 468 Sq.ft. Carpet. The Project has total 406 of which 60 are currently available for sale.

Tiara Hills Phase I Bldg No 3, 5 And 2 is being developed on a total land area of 203938 Sq.ft. out of which 19105 Sq.ft. i.e 9% is reserved for recreational purposes. Tiara Hills Phase I Bldg No 3, 5 And 2 has 3 Wings / Towers Tiara Hills Bldg No 2,Tiara Hills Bldg No 3,Tiara Hills Bldg No 5

ProjectDeveloperLocationPossession
Jp North EstellaJp Infra Realty Private LimitedSurvey Hissa No 24-3 Pt At Vil Ghodbunder Dist And Taluka Thane -40110730-12-2021 00:00:00
Shubh AtikaRavi Developments87/1D, 224 Pt30-12-2023 00:00:00
Harsh Residency And The Corporate LoungeHarsh Real Estate Private LimitedCts No 5,18 And 3230-12-2021 00:00:00
Gaurav ExcellencyRavi DevelopmentsThane01-04-2017 00:00:00
Goldstar Decent HomesGoldstar Sankalp ConstructionS No 104 Village Ghodbunder Taluka And Dist Thane Near Miraroad East31-12-2018 00:00:00
N G CanaryRna Builders (Ng)Survey No 98 Hissa No 115-12-2019 00:00:00
Ana Avant Garde Phase 1Steelfab Engineering Corporation1335Pt, 1424Pt31-12-2018 00:00:00
Gaurav SamruddhiRavi DevelopmentsThane, 40110731-12-2018 00:00:00
Smital AvenueD. L. Builders Pvt. Ltd.10431-03-2018 00:00:00
Tiara Hills Phase I Bldg No 3, 5 And 2Pnk Space Development Pvt Ltd1351,2 1366 1471,2,3 1483,4,7 1491,330-12-2025 00:00:00
Jp North AlexaJp Infra Realty Private LimitedSurvey Hissa No 26/5 Pt And 25/1 Pt At Vill Ghodbunder Dist Taluka Thane 40110730-12-2025 00:00:00
Jp North Imperia - Tower 1Jp Infra Realty Private LimitedSurvey Hissa No 109-9 At Village Ghodbunder Dist And Taluka Thane - 40110730-12-2025 00:00:00
Kasturi BlossomSiddhivinayak EnterpriseOld Survey No. 2131-12-2027 00:00:00
Codename StarlifeJp Infra Realty Private Limited111 -1-2 111-2 111-5 111-8-3 111-8-4 119-1 119-2 119-3 119-4 124-1 124-2 124-3 118-4-1 118-5 118-7 125-1 125-231-12-2031 00:00:00
The Palace Tower BJp Infra Realty Private Limited118/4 Pt, 118/7 Pt, 118/8 Pt, 125/1 Pt, 125/2 Pt, 125/3, 125/4, 125/5A, 125/6/3, 125/7/2, 126/1 Pt, 126/2 Pt, 126/3, 126/4, 126/5 Pt, 126/6, 127/1 Pt, 127/3 Pt, 134/1 Pt, 134/2 Pt, 134/3 Pt31-12-2028 00:00:00
The Palace Tower CJp Infra Realty Private Limited118/4 Pt, 118/7 Pt, 118/8 Pt, 125/1 Pt, 125/2 Pt, 125/3, 125/4, 125/5A, 125/6/3, 125/7/2, 126/1 Pt, 126/2 Pt, 126/3, 126/4, 126/5 Pt, 126/6, 127/1 Pt, 127/3 Pt, 134/1 Pt, 134/2 Pt, 134/3 Pt, 134/4 Pt31-12-2028 00:00:00
Jp North Imperia - Tower 2Jp Infra Realty Private LimitedSurvey Hissa No 106 At Vil Ghodbunder Dist And Taluka Thane - 40110730-12-2025 00:00:00
IndradhanushSonam Homes Private Limited20/230-10-2024 00:00:00
Raj AkshayRaj AkshaySurvey No 127 Hissa No 130-12-2025 00:00:00
Raj EstateD.V.Builders & Developers Pvt. Ltd.11/2/1A,11/2/1B,11/3,4,530-06-2018 00:00:00
PlatinumSilver EnterprisesOld Survey No. 7, New Survey No 6131-12-2018 00:00:00
Seven Eleven Construction Apna GharNarendra Lalchand MehtaSurvey Number 19/130-09-2018 00:00:00
Jp North ElaraJp Infra Realty Private LimitedSurvey Hissa No 24-3Pt 22-2Pt 22-5 112-2Pt 113-2Pt 117-3,4,5 At Vil Ghodbunder Dist Tal Thane 40110730-06-2022 00:00:00
Apna Ghar Phase-Ii Plot-BSeven Eleven Construction Private LimitedProperty Bearing Survey No. 111/2,111/330-06-2022 00:00:00
Apna Ghar Phase IiiSeven Eleven Construction Private LimitedNear Vinay Nagar, Mira Road East, Behind Jhankar Company, Village Ghodbunder30-12-2022 00:00:00
Jp North EuphoriaJp Infra Realty Private LimitedSurvey Hissa No 117-1Pt 117-5Pt 117-6Pt 118-2Pt 118-3Pt Vil Ghodbunder Dist And Taluka Thane 40110730-12-2025 00:00:00
Arch Gardens I And IiSai Prem Developers Private Limited109/131-12-2018 00:00:00
Arkade Art Phase 2Arkade Realty109330-12-2021 00:00:00
Jp North AtriaJp Infra Realty Private LimitedSurvey Hissa No 24-3 Pt 21-2A 21-2B 22-2 Pt At Vil Ghodhbunder Dist And Tal Thane - 40110730-12-2021 00:00:00
Gaurav AsterRavi Developments27/8, 27/931-12-2018 00:00:00
Hiral Shree SamarthHiral Homes401107, Thane30-06-2018 00:00:00
Hill GalaxyR R BuildersSurvey No. 26/331-12-2018 00:00:00
Apna Ghar Phase-Ii Plot-ASeven Eleven Construction Private LimitedProperty Bearing S. No. 25/2 Hissa No. 1/1 And 1/2 Of S. No. 111 And S. No. 112/130-06-2022 00:00:00
Arkade Art Phase 1Arkade Realty1093,6, 1111031-12-2018 00:00:00
North BarcelonaJp Infra Residency Private LimitedSurvey Hissa No 30-7 And 30-8 At Village Ghodbunder, Dist And Taluka Thane - 40110730-12-2025 00:00:00
ForestaTejas Vyas40110731-12-2021 00:00:00
Project Details
  • Project:
    Tiara Hills Phase I Bldg No 3, 5 And 2
  • Location:
  • 1351,2 1366 1471,2,3 1483,4,7 1491,3
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2025
Developer Details

  • Developer:
    Pnk Space Development Pvt Ltd
  • Phone:
  • Address:
  • Asmita Super Market Building
Project RERA Details
MAHA REARA No: P51700010406
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Nirmeek Associates
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 30 Dec 2025
Revised Possession 30 Dec 2025
Extended Possession 30 Dec 2026
Litigations No Litigations
Last Modified 03 Jan 2024
Last Retrived 26 Jul 2025
Tiara Hills Phase I Bldg No 3, 5 And 2 QR Code
Tiara Hills Phase I Bldg No 3, 5 And 2
MahaRERA - P51700010406
Apartment Details & Configuration
TypeArea
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )
2 BHK43.51 Sq.mts. ( 468 Sq.ft. )
2 BHK43.01 Sq.mts. ( 463 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Tiara Hills Phase I Bldg No 3, 5 And 2last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Will Be Done Prior To Oc
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station60% completed
60% Complete
Will Be Done Prior To Oc
Energy management
Na
Fire Protection And Fire Safety Requirements50% completed
50% Complete
Will Be Done Prior To Oc
FITNESS CENTER
Will Be Done Prior To Oc
Landscaping & Tree Planting
Will Be Done Prior To Oc
Open Parking
Will Be Done Prior To Oc
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
Will Be Done Prior To Oc
Solid Waste Management And Disposal
Na
Storm Water Drains50% completed
50% Complete
Will Be Done Prior To Oc
Street Lighting65% completed
65% Complete
Will Be Done Prior To Oc
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
Will Be Done Prior To Oc
Water Supply
Will Be Done Prior To Oc
Buildings / Wings in Tiara Hills Phase I Bldg No 3, 5 And 2
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tiara Hills Phase I Bldg No 3, 5 And 2 by Pnk Space Development Pvt Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

203938 Sq. ft.

Project Area

19105 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

406 apartments in total
Total
406
Booked
346
Available
60

Saleable Area Statistics (Sq. ft.)

132198 Total
Total
132198
Booked
112400
Available
19797
Total 406 apartments in project. 346 apartments booked. 85% apartments booked.
Total 132198 Sq.ft. saleable area. 112400 saleable area booked.
85% area booked.

Tiara Hills Bldg No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tiara Hills Bldg No 2Dec 202424111017164
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )189
157 Booked83% Booked
83% Booked
2 BHK43.51 Sq.mts. ( 468 Sq.ft. )30
23 Booked76% Booked
76% Booked
219 total apartments / 180 apartments booked. 82% apartments booked.
Work Description in Building Tiara Hills Bldg No 2Completion
Basement (if any)
work-in-progress70% done
70% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
work-in-progress70% done
70% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress35% done
35% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
work-in-progress80% done
80% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress70% done
70% Booked
X number of Podiums
X number of Slabs of Super Structure

Tiara Hills Bldg No 3

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tiara Hills Bldg No 3Dec 202424111017146
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )99
88 Booked88% Booked
88% Booked
99 total apartments / 88 apartments booked. 88% apartments booked.
Work Description in Building Tiara Hills Bldg No 3Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress95% done
95% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress78% done
78% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
work-in-progress58% done
58% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Tiara Hills Bldg No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tiara Hills Bldg No 5Dec 202424111017132
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK27.45 Sq.mts. ( 295 Sq.ft. )47
42 Booked89% Booked
89% Booked
2 BHK43.01 Sq.mts. ( 463 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK43.51 Sq.mts. ( 468 Sq.ft. )34
30 Booked88% Booked
88% Booked
88 total apartments / 78 apartments booked. 88% apartments booked.
Work Description in Building Tiara Hills Bldg No 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress95% done
95% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress78% done
78% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress25% done
25% Booked
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
work-in-progress90% done
90% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Pnk Space Development Pvt Ltd
for Project
Tiara Hills Phase I Bldg No 3, 5 And 2
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation