Project overview
The Pinnacle is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800005304. The Pinnacle is located at 904 A And 905. This is a Ongoing being developed by Gerarie Enterprises And Developers Pvt. Ltd.
The Pinnacle has 2 BHK & 3 BHK Apartments with carpet areas ranging from 662 to 917 Sq.ft. Carpet. The Project has total 41 of which 0 are currently available for sale.
The Pinnacle is being developed on a total land area of 13104 Sq.ft. out of which 1966 Sq.ft. i.e 15% is reserved for recreational purposes. The Pinnacle has 1 Wings / Towers Jamnaram Chs Ltd
| Project | Developer | Location | Possession |
-
Project:
The Pinnacle
-
Location:
-
904 A And 905
-
Const. Stage:
Ongoing
-
Possession:
31 Dec 2018
| MAHA REARA No: |
P51800005304 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Mr. Jitendra Dewoolkar |
| Funding Bank |
ICICI BANK LIMITED |
| Proposed Possession |
31 Dec 2018 |
| Revised Possession |
31 Dec 2018 |
| Extended Possession |
31 Dec 2019 |
| Litigations |
No Litigations |
| Last Modified |
28 Dec 2018 |
| Last Retrived |
26 Jul 2025 |
The Pinnacle QR Code
The Pinnacle
MahaRERA - P51800005304
| Type | Area |
| 2 BHK | 61.49 Sq.mts. ( 662 Sq.ft. ) |
| 2 BHK | 62.37 Sq.mts. ( 671 Sq.ft. ) |
| 2 BHK | 63 Sq.mts. ( 678 Sq.ft. ) |
| 2 BHK | 67.25 Sq.mts. ( 724 Sq.ft. ) |
| 2 BHK | 69.1 Sq.mts. ( 744 Sq.ft. ) |
| 3 BHK | 78.15 Sq.mts. ( 841 Sq.ft. ) |
| 3 BHK | 85.19 Sq.mts. ( 917 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of The Pinnaclelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Pending Building Under Construction |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Will Be Done Prior To Oc |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
As Per Cfo Noc |
Landscaping & Tree Planting100% completed
|
|
Tree Noc Received |
|
|
|
Na |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
Sewarage Noc Received |
Solid Waste Management And Disposal
|
|
Na |
Storm Water Drains100% completed
|
|
Swd Completion Certificate Received |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting100% completed
|
|
Rain Water Harvesting As Per Consultant |
Water Supply100% completed
|
|
Plug Connection Received |
Buildings / Wings in The Pinnacle
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of The Pinnacle by Gerarie Enterprises And Developers Pvt. Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
41
apartments in total
Saleable Area Statistics (Sq. ft.)
32089
Total
Total 41 apartments in project. 41 apartments booked. 100% apartments booked.
Total 32089 Sq.ft. saleable area. 32089 saleable area booked.
100% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Jamnaram Chs Ltd | Dec 2018 | 22 | 1 | 0 | 1 | 0 | 0 | 75 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 61.49 Sq.mts. ( 662 Sq.ft. ) | 5 | |
| 2 BHK | 62.37 Sq.mts. ( 671 Sq.ft. ) | 1 | |
| 2 BHK | 63 Sq.mts. ( 678 Sq.ft. ) | 3 | |
| 2 BHK | 67.25 Sq.mts. ( 724 Sq.ft. ) | 12 | |
| 2 BHK | 69.1 Sq.mts. ( 744 Sq.ft. ) | 2 | |
| 3 BHK | 78.15 Sq.mts. ( 841 Sq.ft. ) | 8 | |
| 3 BHK | 85.19 Sq.mts. ( 917 Sq.ft. ) | 10 | |
41 total apartments / 41 apartments booked. 100% apartments booked. |
| Work Description in Building Jamnaram Chs Ltd | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Gerarie Enterprises And Developers Pvt. Ltd
for Project
The Pinnacle
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |