Project overview

The Meadows is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800011383. The Meadows is located at Plot No.R-10, Cts No-260/9A. This is a Ongoing being developed by Guruashish Construction Private Limited.

The Meadows has RESIDENTIAL Apartments with carpet areas ranging from 686 to 893 Sq.ft. Carpet. The Project has total 610 of which 146 are currently available for sale.

The Meadows is being developed on a total land area of 176521 Sq.ft. out of which 51452 Sq.ft. i.e 29% is reserved for recreational purposes. The Meadows has 14 Wings / Towers Wing - B,Wing - D,Wing - E,Wing - F,Wing -A,Wing -A Phase-2 18Th To 27Th Floor,Wing -B Phase -2 18Th To 27Th Floor,Wing C Phase-2 18Th To 27Th Floor,Wing- C,Wing- G,Wing-D Phase-2 19Th To 33Rd Floor,Wing-E Phase-2 19Th To 27Th Floor,Wing-F Phase-2 19Th To 27Th Floor,Wing-G Phase-2 19Th To 27Th Floor

ProjectDeveloperLocationPossession
Redevelopment Of Ganpati Niwas ChslBharat Realty Venture Private LimitedCts No 99931-07-2025 00:00:00
Kalpataru Radiance DKeyana Estate LlpCts No.260/5A -Part Of Village Pahadi Goregaon West30-06-2022 00:00:00
Kalpataru Radiance AKeyana Estate LlpCts No.260/5A -Part Of Village Pahadi Goregaon West30-06-2022 00:00:00
Sharad Apartments Chs LtdAakar Constructions20331-12-2017 00:00:00
AthenaM/S. Sahajanand Developers26 Pt31-03-2020 00:00:00
Constrution Of 24 Lig Ts On Cts No 356 P At Siddharth Nagar Goregaon West Mumbai 400062Mumbai Housing And Area Development BoardCts No 356 Part30-06-2019 00:00:00
Raj - BaijuRaj Arcade Pvt. Ltd.Cts 456/ Plot No 32431-12-2019 00:00:00
AristaM/S. Sahajanand Developers26 Pt30-12-2022 00:00:00
HimbinduM/S. Sahajanand Developers292/21 To 30, 292 Pt31-12-2018 00:00:00
Kalpataru Radiance BKeyana Estate LlpCts No.260/5A Part Of Village Pahadi Goregaon West30-06-2022 00:00:00
Ekta Tripolis Phase IEkta Everglade Homes Private LimitedCts 22A/10 22A/11A, 22A/14 Pt, 2601/130-06-2021 00:00:00
Plot No 88Jitesh Bhawarlal Jain716, 7161 To 1131-05-2018 00:00:00
Mayadevi/ VikuthdhamHome Today Renovation India Pvt.Ltd584, 584/1 To 831-12-2018 00:00:00
Om Shubh LabhBali Realty Llp695, 695/1 To 695/630-06-2018 00:00:00
Aum HeightsAbhismit EnterprisesPlot No 30 Cts No 221 Pt31-12-2018 00:00:00
Goregaon Makarand Chs, ParagGolden Land16731-05-2019 00:00:00
Siddharth Nagar Sukhvilla Chs LtdDilip Hiralal DoshiPlot No 6 - Cts No 350 Part 350/ 13 To 1630-06-2018 00:00:00
Saanvi HeightsAdinath Enterprise83C, 8231-12-2018 00:00:00
Construction Of 83 Lig Ts On Guest Plot Cts No 43 Pt Of Unnatagar, Village Pahadi Goregaon Mumbai Housing And Area Development Board4331-12-2018 00:00:00
Redevelopment Of Transit Building No 32 And 33 Sidharth Nagar Goregaon WestMumbai Housing And Area Development BoardCts No 26731-03-2018 00:00:00
Construcion Of 28 Lig Tenement On Plot Ob 8,Siddharth Nagar ,Goregaon West,MumbaiMumbai Housing And Area Development BoardCts 26 Part31-12-2017 00:00:00
Redevelopment Of Office Building No1 Sidharth Nagrar Goregaon WestMumbai Housing And Area Development BoardCts No 348 Sidharth Nagargoregaon West31-12-2017 00:00:00
Navkar AshrayNavkar Builder &Amp; DevvelopersTilak Nagar30-04-2016 00:00:00
Anmol Fortune - IiWadhwa Realty Pvt Ltd. Cts No-58 Part 1 To 7631-12-2019 00:00:00
Ashtha Goregaon WestTown Developers41631-12-2019 00:00:00
34 Park EstateM/S Reddy Builders & Developers50 A Part, 55 Part, 49 Part31-07-2028 00:00:00
Laxmi HeightsLaxmidevi DevelopersPlot No 30731-12-2018 00:00:00
Swati C.H.S. LtdDilip Hiralal DoshiCts No 348 P 348 70 To 7230-06-2018 00:00:00
Kalpataru Radiance EKeyana Estate LlpCts No.260/5A Part Of Village Pahadi Goregaon West30-06-2022 00:00:00
Samarth ResidencyAjay Sitaram Surve560, 1 To 630-12-2022 00:00:00
Jairajratna Chs LtdMumbai Shelter Project Jairajratan LlpMumbai Suburban30-06-2019 00:00:00
Siddharth Nagar SatyadeepSai Developers400104, Mumbai Suburban31-12-2019 00:00:00
Ariisto Sommet-ResidentialAshvi Developers Private LimitedNotionally Divided Part Of Cts No 236/A/1, 236/A/5 Of Village Pahadi Goregaon Tal. Borivali Msd30-12-2023 00:00:00
Redevlopment Of Sundresh Chs LtdRaj Corporation27431-12-2017 00:00:00
Construction Of 94 Ews Ts And 182 Lig Ts On Cts No 43 Unnatnagar Goragaon WestMumbai Housing And Area Development Board43 Pt31-03-2018 00:00:00
M SpaceMahindra Lifespace Developers Limited899 C30-09-2019 00:00:00
Kalpataru Radiance CKeyana Estate LlpCts No.260/5A -Part Of Village Pahadi Goregaon West30-06-2022 00:00:00
Siddarth Nagar Arunodaya Chs LtdChiraginfraprojectspvt LtdMumbai Suburban, 40006231-03-2018 00:00:00
Ariisto Sommet-RetailAtithi Builders And Constructors Private Limited236/A/5 Of Village Pahadi Goregaon Tal. Borivali Msd, Notionally Divided Part Of Cts No 236/A/130-12-2023 00:00:00
Goregaon Rasik Co Op Hsg Society LtdAakar Real Estate DevelopersCts No. 208 Plot No 11431-03-2019 00:00:00
Meeras Empire And Meeras CrownRushabh Real Estate Developers Private Limited50Pt28-11-2023 00:00:00
Pahhal AvenueUmmang Realtors Llp799/1 To 8, 79931-12-2019 00:00:00
Redevelopment Of Navchandrakunj ChslPranav Constructions LimitedPlot No.42, Cts No.734/A, 734/1 To 630-03-2022 00:00:00
Siddharth Nagar Shivam Chs LtdVirendra Hiralal DoshiCts No 348 Part31-03-2025 00:00:00
Vijayi JwalaChirag Infraprojects Private Limited217(Pt)31-03-2027 00:00:00
Shree Hari EnclaveParesh PatelGoregaon West, Mumbai Suburban31-12-2025 00:00:00
Dridhena Developers And RealtorsDridhena Developers And Realtors662, 662/1 To 528-02-2019 00:00:00
Dharmanath KrupaBali Landmarks Llp679/1 To 679/7, 67931-12-2018 00:00:00
Building On Sub Plot - D, Cts No 101/B Of Village GoregaonSkyline Construction Co.Part Of Sub Plot D Cts No 101 B Of Village Goregaon At Oshiwara District Centre Goregaon W Mumbai31-10-2019 00:00:00
Siddharth Nagar Abhiman Chs Ltd Building No-25Mumbai Shelter Housing Development Pvt Ltd347 Part31-12-2019 00:00:00
Laxmi NagarReliable ConstructionsPlot No B-1 Cts 1A170-B Pahadi Goregaon W Tal Borivali Dist Mumbai 40009030-12-2023 00:00:00
Project Details
  • Project:
    The Meadows
  • Location:
  • Plot No.R-10, Cts No-260/9A
  • Const. Stage:
    Ongoing
  • Possession:
    19 Nov 2019
Developer Details

  • Developer:
    Guruashish Construction Private Limited
  • Phone:
  • Address:
  • Siddharth Nagar No.1
Project RERA Details
MAHA REARA No: P51800011383
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Space Moulders
Funding Bank
Proposed Possession 19 Nov 2019
Revised Possession 19 Nov 2019
Extended Possession
Litigations No Litigations
Last Modified 31 Aug 2017
Last Retrived 26 Jul 2025
The Meadows QR Code
The Meadows
MahaRERA - P51800011383
Apartment Details & Configuration
TypeArea
RESDIENTIAL61.47 Sq.mts. ( 662 Sq.ft. )
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )
RESIDENTIAL70.05 Sq.mts. ( 754 Sq.ft. )
RESIDENTIAL61.4 Sq.mts. ( 661 Sq.ft. )
RESIDENTIAL103.46 Sq.mts. ( 1114 Sq.ft. )
RESIDENTIAL103.54 Sq.mts. ( 1115 Sq.ft. )
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )
RESIDENTIAL82.88 Sq.mts. ( 892 Sq.ft. )
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )
RESIDENTIAL96.19 Sq.mts. ( 1035 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of The Meadowslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Yet To Commence
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Yet To Commence
Energy management
Yet To Commence
Fire Protection And Fire Safety Requirements
Yet To Commence
Landscaping & Tree Planting
Yet To Commence
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Yet To Commence
Solid Waste Management And Disposal
Yet To Commence
Storm Water Drains
Yet To Commence
Street Lighting
Yet To Commence
Treatment And Disposal Of Sewage And Sullage Water
Yet To Commence
Water Conservation, Rain water Harvesting
Yet To Commence
Water Supply
Yet To Commence
Buildings / Wings in The Meadows
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of The Meadows by Guruashish Construction Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

176521 Sq. ft.

Project Area

51452 Sq. ft.

Recreational Open Space

Total 14

Wings / Towers in Project

Apartments Statistics

610 apartments in total
Total
610
Booked
464
Available
146

Saleable Area Statistics (Sq. ft.)

509957 Total
Total
509957
Booked
383510
Available
126447
Total 610 apartments in project. 464 apartments booked. 76% apartments booked.
Total 509957 Sq.ft. saleable area. 383510 saleable area booked.
75% area booked.

Wing - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - BJan 190013111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESDIENTIAL61.47 Sq.mts. ( 662 Sq.ft. )10
10 Booked100% Booked
100% Booked
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )12
12 Booked100% Booked
100% Booked
RESIDENTIAL70.05 Sq.mts. ( 754 Sq.ft. )12
12 Booked100% Booked
100% Booked
RESIDENTIAL61.4 Sq.mts. ( 661 Sq.ft. )10
10 Booked100% Booked
100% Booked
44 total apartments / 44 apartments booked. 100% apartments booked.
Work Description in Building Wing - BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress28% done
28% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress80% done
80% Booked
X number of Slabs of Super Structure

Wing - D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - DJan 190014111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL103.46 Sq.mts. ( 1114 Sq.ft. )26
25 Booked96% Booked
96% Booked
RESIDENTIAL103.54 Sq.mts. ( 1115 Sq.ft. )24
13 Booked54% Booked
54% Booked
50 total apartments / 38 apartments booked. 76% apartments booked.
Work Description in Building Wing - DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing - E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - EJan 190014111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )13
12 Booked92% Booked
92% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )11
10 Booked90% Booked
90% Booked
RESIDENTIAL82.88 Sq.mts. ( 892 Sq.ft. )13
13 Booked100% Booked
100% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )13
50 total apartments / 37 apartments booked. 74% apartments booked.
Work Description in Building Wing - ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress23% done
23% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress30% done
30% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress30% done
30% Booked
X number of Slabs of Super Structure

Wing - F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing - FJan 190014111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL61.4 Sq.mts. ( 661 Sq.ft. )11
9 Booked81% Booked
81% Booked
RESIDENTIAL61.47 Sq.mts. ( 662 Sq.ft. )11
11 Booked100% Booked
100% Booked
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )13
12 Booked92% Booked
92% Booked
RESIDENTIAL70.05 Sq.mts. ( 754 Sq.ft. )13
12 Booked92% Booked
92% Booked
48 total apartments / 44 apartments booked. 91% apartments booked.
Work Description in Building Wing - FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress34% done
34% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress40% done
40% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress40% done
40% Booked
X number of Slabs of Super Structure

Wing -A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing -AJan 190013111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )12
10 Booked83% Booked
83% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )10
7 Booked70% Booked
70% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )22
18 Booked81% Booked
81% Booked
RESIDENTIAL96.19 Sq.mts. ( 1035 Sq.ft. )2
2 Booked100% Booked
100% Booked
46 total apartments / 37 apartments booked. 80% apartments booked.
Work Description in Building Wing -ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress28% done
28% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress80% done
80% Booked
X number of Slabs of Super Structure

Wing -A Phase-2 18Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing -A Phase-2 18Th To 27Th FloorJan 190010000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )10
10 Booked100% Booked
100% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )9
7 Booked77% Booked
77% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )20
12 Booked60% Booked
60% Booked
39 total apartments / 29 apartments booked. 74% apartments booked.
Work Description in Building Wing -A Phase-2 18Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing -B Phase -2 18Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing -B Phase -2 18Th To 27Th FloorJan 190010000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL61.4 Sq.mts. ( 661 Sq.ft. )9
7 Booked77% Booked
77% Booked
RESIDENTIAL61.47 Sq.mts. ( 662 Sq.ft. )9
7 Booked77% Booked
77% Booked
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )10
10 Booked100% Booked
100% Booked
RESIDENTIAL70.05 Sq.mts. ( 754 Sq.ft. )10
7 Booked70% Booked
70% Booked
38 total apartments / 31 apartments booked. 81% apartments booked.
Work Description in Building Wing -B Phase -2 18Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing C Phase-2 18Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing C Phase-2 18Th To 27Th FloorJan 190010000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )10
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )9
8 Booked88% Booked
88% Booked
RESIDENTIAL82.88 Sq.mts. ( 892 Sq.ft. )10
9 Booked90% Booked
90% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )10
8 Booked80% Booked
80% Booked
39 total apartments / 26 apartments booked. 66% apartments booked.
Work Description in Building Wing C Phase-2 18Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing- C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing- CJan 190013111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )12
10 Booked83% Booked
83% Booked
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )10
10 Booked100% Booked
100% Booked
RESIDENTIAL82.88 Sq.mts. ( 892 Sq.ft. )12
11 Booked91% Booked
91% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )12
6 Booked50% Booked
50% Booked
46 total apartments / 37 apartments booked. 80% apartments booked.
Work Description in Building Wing- CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Wing- G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing- GJan 190014111401
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )13
12 Booked92% Booked
92% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )11
10 Booked90% Booked
90% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )24
12 Booked50% Booked
50% Booked
RESIDENTIAL96.19 Sq.mts. ( 1035 Sq.ft. )2
1 Booked50% Booked
50% Booked
50 total apartments / 35 apartments booked. 70% apartments booked.
Work Description in Building Wing- GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress38% done
38% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress80% done
80% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
work-in-progress80% done
80% Booked
X number of Slabs of Super Structure

Wing-D Phase-2 19Th To 33Rd Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing-D Phase-2 19Th To 33Rd FloorJan 190015000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL103.46 Sq.mts. ( 1114 Sq.ft. )30
29 Booked96% Booked
96% Booked
RESIDENTIAL103.54 Sq.mts. ( 1115 Sq.ft. )26
10 Booked38% Booked
38% Booked
56 total apartments / 39 apartments booked. 69% apartments booked.
Work Description in Building Wing-D Phase-2 19Th To 33Rd FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing-E Phase-2 19Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing-E Phase-2 19Th To 27Th FloorJan 19009000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )9
7 Booked77% Booked
77% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )8
6 Booked75% Booked
75% Booked
RESIDENTIAL82.88 Sq.mts. ( 892 Sq.ft. )9
6 Booked66% Booked
66% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )9
35 total apartments / 20 apartments booked. 57% apartments booked.
Work Description in Building Wing-E Phase-2 19Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing-F Phase-2 19Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing-F Phase-2 19Th To 27Th FloorJan 19009000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL61.4 Sq.mts. ( 661 Sq.ft. )8
4 Booked50% Booked
50% Booked
RESIDENTIAL61.47 Sq.mts. ( 662 Sq.ft. )8
3 Booked37% Booked
37% Booked
RESIDENTIAL70 Sq.mts. ( 753 Sq.ft. )9
5 Booked55% Booked
55% Booked
RESIDENTIAL70.05 Sq.mts. ( 754 Sq.ft. )9
7 Booked77% Booked
77% Booked
34 total apartments / 19 apartments booked. 55% apartments booked.
Work Description in Building Wing-F Phase-2 19Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing-G Phase-2 19Th To 27Th Floor

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing-G Phase-2 19Th To 27Th FloorJan 19009000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
RESIDENTIAL63.76 Sq.mts. ( 686 Sq.ft. )9
7 Booked77% Booked
77% Booked
RESIDENTIAL69.92 Sq.mts. ( 753 Sq.ft. )8
7 Booked87% Booked
87% Booked
RESIDENTIAL82.94 Sq.mts. ( 893 Sq.ft. )18
14 Booked77% Booked
77% Booked
35 total apartments / 28 apartments booked. 80% apartments booked.
Work Description in Building Wing-G Phase-2 19Th To 27Th FloorCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Guruashish Construction Private Limited
for Project
The Meadows
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation