Project overview

The Chalets Avenue is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700008568. The Chalets Avenue is located at 12/1. This is a Ongoing being developed by Assets Reality.

The Chalets Avenue has 1 BHK Apartments with carpet areas ranging from 29063 to 29063 Sq.ft. Carpet. The Project has total 131 of which 13 are currently available for sale.

The Chalets Avenue is being developed on a total land area of 43056 Sq.ft. out of which 4166 Sq.ft. i.e 10% is reserved for recreational purposes. The Chalets Avenue has 4 Wings / Towers Type A,Type B,Type C,Wing A

ProjectDeveloperLocationPossession
Greenworld Developers Pvt. LtdGreenworld Devlopers Pvt. Ltd.2990 Pt A30-06-2021 00:00:00
ShivamGagan Developers & EngineersSurvey No 46 Hissa No.16 P31-03-2019 00:00:00
GeetanjaliHonest Homes16/11 18/3 19/1531-12-2019 00:00:00
Keshar Aagan Cooperative Housing SocietyGagan HomesPlot No 14/6 Survey No 42/A30-09-2026 00:00:00
Balaji AquaBalaji WorldOld Survey No. 39, Hissa No- 3/2/A, 3/2/C, 3/2/D05-11-2029 00:00:00
V Ten ResidencyV Ten Realty Private LimitedSurvey No 105 Hissa No 1 Village Chikanghar Kalyan 30-12-2020 00:00:00
Mangeshi FloraOm Realty123 7 2 123 231-03-2019 00:00:00
Shivaay ResidencyRohan Krishnapalsingh ThakurS.No. 42/14/B/C30-06-2019 00:00:00
Patel Colossus - Phase IiiPatel Group & CoSurvey No. 42A, H.No. 2 Pt, 3 Pt, 4 Pt, 7 Pt, 8Pt, 9 Pt, 24Pt30-12-2023 00:00:00
Patel Colossus Phase 1Patel Group & CoS. No. 42 A, H.N 2 Pt, 3 Pt, 4 Pt, 7 Pt, 8 Pt, 9 Pt, 24 Pt30-12-2022 00:00:00
Shrushti AvenueKishore DesaiThane, 42130131-12-2017 00:00:00
Nirman HeightsNirman HabitatsS No 12,Hissa No 4,Plot No531-08-2018 00:00:00
Ashapura PrasadAshapura Nirman DevelopersCts No. 7380 To 7384 And 7389, Survey No. 4231-12-2018 00:00:00
Bharat Residency Shivsai Builders & DevelopersS No 84 H No 7 /11 B31-05-2018 00:00:00
Jalal MansionMaryam Enterprises1545,154931-12-2018 00:00:00
Shiv SiddhiKedar ConstructionSurvey No 1 Hissa No 3/A-130-06-2023 00:00:00
Gnp LandmarkGnp Landmark61/9/131-01-2027 00:00:00
Geetant AshrayVasudha Construction CompanySurvey No 42/A Hissa No 19B/1631-12-2024 00:00:00
Atharva HeightsJai Shreegurutatvam Engineers And DevelopersSurvey No 130/2A/1 & 20/4A Cts 361531-12-2025 00:00:00
Balaji Exotica-Phase 1Balaji WorldSurvey No-16,H.No-8/2,Plot No-230-12-2022 00:00:00
Disha Co Operative Housing Society LtdGagan Developers And EngineersSurvey No 19 Hissa No 13 Part31-01-2020 00:00:00
Vaishnavi HeightsVaishnavi ConstructionSurvey No 42A, Hissa No 19/A/3 Cts No. 7273 To 7276, Survey No. 42/A, Hissa No. 19/A/8 Cts No.7277 To 728030-07-2024 00:00:00
Proposed Residential,Commercial Bldgs On Plot Bearing Old 96 C 2-Pt - Mayur MahalMayur Group (Rd)Old Survey No 96/C/2 Pt30-06-2027 00:00:00
Gayatri NiwasGayatri Builders2991231-12-2025 00:00:00
Suviam Pearl Phase ILaxmi Construction CoSurvey No.36, Hissa No.3/131-12-2026 00:00:00
Bhakti WindsorBhakti Realtors121/3B31-10-2026 00:00:00
Sai Sharada Chs LtdM Square DevelopersSr No. 87 H.No 9 Plot No- 2731-05-2026 00:00:00
Shivneri Park Co Op Hsg Soc LtdShree Swastik ConstructionsS No. 14 H. No. 1/331-03-2027 00:00:00
Sai ParkSai Satyam Realty LlpSurvey No. 21 Hiss No. 1/1, 10/1, 10/231-12-2027 00:00:00
Namdev ViharNamdev ConstructionS.No. 121 H.No. 7A2 7A330-12-2021 00:00:00
Capsule Business HubMaa Vaishnavi Builders & Developers2848A/1/130-06-2021 00:00:00
Sai VyankateshAnjana Sahebrao ChavanS No 16 H No 7 And S No 19 H No 130-06-2021 00:00:00
Mauli PrideMauli Krupa DevelopersSurvey No- 21, Hissa No- A01-12-2027 00:00:00
Empire TowerEkadanta DevelopersS No. 110/1A/1B/8 Plot No 9,1031-12-2026 00:00:00
Om VardhastaZk RealtySurvey No 12, Hissa No 4/R31-12-2027 00:00:00
Patels OrionDesire RealtySurvey No 86/1/131-03-2030 00:00:00
Om Yashlaxmi ApartmentOm Developers1135B/ 1136 / 113731-12-2019 00:00:00
Jigar Construction VenusPraful Haribhai SenjaliaSurvey No 110 / 1A And 1B31-03-2019 00:00:00
Tycoons Square Avenue Iii Tower CTycoons Avanti Projects Llp421301, Thane31-07-2020 00:00:00
Manali Heights A WingMitali Construction1/4, 121/7B31-12-2018 00:00:00
Athena EnclaveJai Mata Di DevelopersSno 9 Hno 3/1/2/2/A30-12-2023 00:00:00
The Chalets AvenueAssets Reality12/130-11-2018 00:00:00
Patel Colossus Phase IiPatel Group & CoSurvey No. 42A, H.N. 2 Pt, 3, Pt, 4 Pt, 7 Pt, 8 Pt, 9Pt30-12-2023 00:00:00
AmikrupaAarohi Development Corporation99-A12,99B30-09-2020 00:00:00
Ami Darshan E WingAarohi Development Corporation99-A1/2,99B31-12-2017 00:00:00
Atmaram Kene ResidencyMega DevelopersSn 82/7 And Sn 87/831-12-2018 00:00:00
Pluto C WingBhakti RealtoraB/123/1A31-12-2017 00:00:00
Chavan AdvaitamSaideep ConstructionsS.No.9 H.No. 3/1/2/2/C/1, 3/1/2/2/C/2 & S. No.15 H.No.4/131-12-2026 00:00:00
Pancham Co. Operative Hsg SocietyYuvraj Constructions131(P)30-06-2025 00:00:00
Patel MountPatel Group & CoS.No.42A, Hissa No. 2(Pt),3(Pt),(4Pt),7(Pt),8(Pt),9(Pt),24(Pt)30-06-2024 00:00:00
Project Details
  • Project:
    The Chalets Avenue
  • Location:
  • 12/1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Nov 2018
Developer Details

  • Developer:
    Assets Reality
  • Phone:
  • Address:
  • Sanghvi Estate
Project RERA Details
MAHA REARA No: P51700008568
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect M Square Architects Prop Mukesh B More
Funding Bank
Proposed Possession 30 Nov 2018
Revised Possession 30 Nov 2018
Extended Possession 31 Mar 2025
Litigations No Litigations
Last Modified 16 Jun 2025
Last Retrived 26 Jul 2025
The Chalets Avenue QR Code
The Chalets Avenue
MahaRERA - P51700008568
Apartment Details & Configuration
TypeArea
TYPE A ROW HOUSE373 Sq.mts. ( 4015 Sq.ft. )
2 BHK483 Sq.mts. ( 5199 Sq.ft. )
3 BHK491.54 Sq.mts. ( 5291 Sq.ft. )
1 BHK2700 Sq.mts. ( 29063 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of The Chalets Avenuelast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Temple And Garden
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Only Electric Room
Energy management
Na
Fire Protection And Fire Safety Requirements
As Per Fire Safety Norms
Landscaping & Tree Planting40% completed
40% Complete
Garden Ready
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)20% completed
20% Complete
Lines And Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting100% completed
95% Complete
15 Mt Dp Road Lights Poles
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting50% completed
50% Complete
On Rain Water Harvesting
Water Supply
Na
Buildings / Wings in The Chalets Avenue
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of The Chalets Avenue by Assets Realitylast updated on 26 Jul 2025 as per information obtained from MARA RERA.

43056 Sq. ft.

Project Area

4166 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

131 apartments in total
Total
131
Booked
118
Available
13

Saleable Area Statistics (Sq. ft.)

3225759 Total
Total
3225759
Booked
2895578
Available
330181
Total 131 apartments in project. 118 apartments booked. 90% apartments booked.
Total 3225759 Sq.ft. saleable area. 2895578 saleable area booked.
90% area booked.

Type A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Type AJan 19002100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
TYPE A ROW HOUSE373 Sq.mts. ( 4015 Sq.ft. )8
8 Booked100% Booked
100% Booked
8 total apartments / 8 apartments booked. 100% apartments booked.
Work Description in Building Type ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Type B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Type BJun 20213108008
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK483 Sq.mts. ( 5199 Sq.ft. )8
7 Booked87% Booked
87% Booked
8 total apartments / 7 apartments booked. 87% apartments booked.
Work Description in Building Type BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Type C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Type CSep 20233108008
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK491.54 Sq.mts. ( 5291 Sq.ft. )8
7 Booked87% Booked
87% Booked
8 total apartments / 7 apartments booked. 87% apartments booked.
Work Description in Building Type CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing ASep 20239100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK2700 Sq.mts. ( 29063 Sq.ft. )107
96 Booked89% Booked
89% Booked
107 total apartments / 96 apartments booked. 89% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress92% done
92% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress99% done
99% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
work-in-progress85% done
85% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Assets Reality
for Project
The Chalets Avenue
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation