Project overview
The Centre Park is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700011284. The Centre Park is located at New 114/1,2 - 113/1. This is a Ongoing being developed by Salasar Unique Realtors Llp.
The Centre Park has 0 & NA Apartments with carpet areas ranging from 0 to 0 Sq.ft. Carpet. The Project has total 288 of which 288 are currently available for sale.
The Centre Park is being developed on a total land area of 761984 Sq.ft. out of which 134459 Sq.ft. i.e 18% is reserved for recreational purposes. The Centre Park has 3 Wings / Towers Hazel - D3,Maple - F1,Na
| Project | Developer | Location | Possession |
-
Project:
The Centre Park
-
Location:
-
New 114/1,2 - 113/1
-
Const. Stage:
Ongoing
-
Possession:
30 Dec 2023
| MAHA REARA No: |
P51700011284 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
Ongoing |
| Architect |
Avinash Mhatre & Associates |
| Funding Bank |
BASSEIN CATHOLIC COOPERATIVE BANK LIMITED |
| Proposed Possession |
30 Dec 2023 |
| Revised Possession |
30 Dec 2023 |
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
31 Aug 2017 |
| Last Retrived |
26 Jul 2025 |
The Centre Park QR Code
The Centre Park
MahaRERA - P51700011284
| Type | Area |
| 2 BHK | 54.7 Sq.mts. ( 589 Sq.ft. ) |
| 2 BHK | 55.26 Sq.mts. ( 595 Sq.ft. ) |
| 3 BHK | 77.44 Sq.mts. ( 834 Sq.ft. ) |
| 0 | 0 Sq.mts. ( 0 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of The Centre Parklast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Not Started |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Not Started |
|
|
|
Not Started |
Fire Protection And Fire Safety
Requirements
|
|
Not Started |
Landscaping & Tree Planting
|
|
Not Started |
|
|
|
Not Started |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
Not Started |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
Not Started |
|
|
|
Na |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Not Started |
|
|
|
By Mbmc After Oc |
Buildings / Wings in The Centre Park
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of The Centre Park by Salasar Unique Realtors Llplast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
288
apartments in total
Saleable Area Statistics (Sq. ft.)
190422
Total
Total 288 apartments in project. 0 apartments booked. 0% apartments booked.
Total 190422 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Hazel - D3 | Dec 2023 | 22 | 1 | 1 | 1 | 2 | 15 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 54.7 Sq.mts. ( 589 Sq.ft. ) | 62 | |
| 2 BHK | 55.26 Sq.mts. ( 595 Sq.ft. ) | 19 | |
| 3 BHK | 77.44 Sq.mts. ( 834 Sq.ft. ) | 84 | |
165 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Hazel - D3 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Maple - F1 | Dec 2023 | 20 | 1 | 1 | 1 | 2 | 8 | 1 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 2 BHK | 54.7 Sq.mts. ( 589 Sq.ft. ) | 94 | |
| 2 BHK | 55.26 Sq.mts. ( 595 Sq.ft. ) | 29 | |
123 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Maple - F1 | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Na | Dec 2023 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 0 | 0 Sq.mts. ( 0 Sq.ft. ) | 0 | |
| NA | 0 Sq.mts. ( 0 Sq.ft. ) | 0 | |
|
| Work Description in Building Na | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Salasar Unique Realtors Llp
for Project
The Centre Park
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |