Project overview

Tathastu is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700017002. Tathastu is located at Survey No 166 Hissa No 3. This is a New being developed by Maharashtra Developers.

Tathastu has 1 BHK Apartments with carpet areas ranging from 244 to 328 Sq.ft. Carpet. The Project has total 144 of which 144 are currently available for sale.

Tathastu is being developed on a total land area of 29170 Sq.ft. Tathastu has 8 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E,Wing F,Wing G,Wing H

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Tathastu
  • Location:
  • Survey No 166 Hissa No 3
  • Const. Stage:
    New
  • Possession:
    30 Mar 2023
Developer Details

  • Developer:
    Maharashtra Developers
  • Phone:
  • Address:
  • Addl Ambernath Midc Area
Project RERA Details
MAHA REARA No: P51700017002
Project Type Residential / Group Housing
RERA Project Status New
Architect Arc Designers
Funding Bank INDIAN OVERSEAS BANK
Proposed Possession 30 Mar 2023
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 28 Jun 2018
Last Retrived 26 Jul 2025
Tathastu QR Code
Tathastu
MahaRERA - P51700017002
Apartment Details & Configuration
TypeArea
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )
1 BHK23.71 Sq.mts. ( 255 Sq.ft. )
1 BHK25.26 Sq.mts. ( 272 Sq.ft. )
1 BHK28.72 Sq.mts. ( 309 Sq.ft. )
1 BHK29.1 Sq.mts. ( 313 Sq.ft. )
2 BHK37.71 Sq.mts. ( 406 Sq.ft. )
1 BHK24.89 Sq.mts. ( 268 Sq.ft. )
1 BHK25.38 Sq.mts. ( 273 Sq.ft. )
1 BHK25.46 Sq.mts. ( 274 Sq.ft. )
1 BHK29.13 Sq.mts. ( 314 Sq.ft. )
1RK15.34 Sq.mts. ( 165 Sq.ft. )
1 BHK25.25 Sq.mts. ( 272 Sq.ft. )
1 BHK28.75 Sq.mts. ( 309 Sq.ft. )
1 BHK30.71 Sq.mts. ( 331 Sq.ft. )
1 BHK22.48 Sq.mts. ( 242 Sq.ft. )
1 BHK22.72 Sq.mts. ( 245 Sq.ft. )
1 BHK23.55 Sq.mts. ( 253 Sq.ft. )
1 BHK23.81 Sq.mts. ( 256 Sq.ft. )
1 BHK24.74 Sq.mts. ( 266 Sq.ft. )
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )
1 BHK23.49 Sq.mts. ( 253 Sq.ft. )
1 BHK24.03 Sq.mts. ( 259 Sq.ft. )
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )
1 BHK30.39 Sq.mts. ( 327 Sq.ft. )
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )
1 BHK23.59 Sq.mts. ( 254 Sq.ft. )
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )
1 BHK23.33 Sq.mts. ( 251 Sq.ft. )
1 BHK24.93 Sq.mts. ( 268 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Tathastulast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking
As Per Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
-
Solid Waste Management And Disposal
Na
Storm Water Drains
-
Street Lighting
Existing
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply100% completed
95% Complete
Borewell
Buildings / Wings in Tathastu
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tathastu by Maharashtra Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

29170 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 8

Wings / Towers in Project

Apartments Statistics

144 apartments in total
Total
144
Booked
0
Available
144

Saleable Area Statistics (Sq. ft.)

39808 Total
Total
39808
Booked
0
Available
39808
Total 144 apartments in project. 0 apartments booked. 0% apartments booked.
Total 39808 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK23.53 Sq.mts. ( 253 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.71 Sq.mts. ( 255 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.26 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK28.72 Sq.mts. ( 309 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK29.1 Sq.mts. ( 313 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK37.71 Sq.mts. ( 406 Sq.ft. )4
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Excavation
work-in-progress50% done
50% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.89 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.38 Sq.mts. ( 273 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.46 Sq.mts. ( 274 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK29.13 Sq.mts. ( 314 Sq.ft. )4
None Booked0% Booked
0% Booked
1RK15.34 Sq.mts. ( 165 Sq.ft. )4
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Excavation
work-in-progress50% done
50% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK24.89 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK25.25 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK28.75 Sq.mts. ( 309 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.71 Sq.mts. ( 331 Sq.ft. )4
None Booked0% Booked
0% Booked
1 RK15.34 Sq.mts. ( 165 Sq.ft. )4
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.48 Sq.mts. ( 242 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK22.72 Sq.mts. ( 245 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.55 Sq.mts. ( 253 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK23.81 Sq.mts. ( 256 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.74 Sq.mts. ( 266 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK25.25 Sq.mts. ( 272 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK30.71 Sq.mts. ( 331 Sq.ft. )4
None Booked0% Booked
0% Booked
19 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.49 Sq.mts. ( 253 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.03 Sq.mts. ( 259 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK30.39 Sq.mts. ( 327 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
19 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing FMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.59 Sq.mts. ( 254 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing FCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing GMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.59 Sq.mts. ( 254 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.76 Sq.mts. ( 267 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.4 Sq.mts. ( 327 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )2
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing GCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing HMar 20225101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK22.65 Sq.mts. ( 244 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK23.33 Sq.mts. ( 251 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.65 Sq.mts. ( 265 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK24.93 Sq.mts. ( 268 Sq.ft. )4
None Booked0% Booked
0% Booked
1 BHK27.53 Sq.mts. ( 296 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.45 Sq.mts. ( 328 Sq.ft. )4
None Booked0% Booked
0% Booked
18 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing HCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Maharashtra Developers
for Project
Tathastu
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation