Project overview
Tathastu is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700017002. Tathastu is located at Survey No 166 Hissa No 3. This is a New being developed by Maharashtra Developers.
Tathastu has 1 BHK Apartments with carpet areas ranging from 244 to 328 Sq.ft. Carpet. The Project has total 144 of which 144 are currently available for sale.
Tathastu is being developed on a total land area of 29170 Sq.ft. Tathastu has 8 Wings / Towers Wing A,Wing B,Wing C,Wing D,Wing E,Wing F,Wing G,Wing H
| Project | Developer | Location | Possession |
-
Project:
Tathastu
-
Location:
-
Survey No 166 Hissa No 3
-
Const. Stage:
New
-
Possession:
30 Mar 2023
-
Developer:
Maharashtra Developers
-
Phone:
-
Address:
-
Addl Ambernath Midc Area
| MAHA REARA No: |
P51700017002 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Arc Designers |
| Funding Bank |
INDIAN OVERSEAS BANK |
| Proposed Possession |
30 Mar 2023 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
28 Jun 2018 |
| Last Retrived |
26 Jul 2025 |
Tathastu QR Code
Tathastu
MahaRERA - P51700017002
| Type | Area |
| 1 BHK | 23.53 Sq.mts. ( 253 Sq.ft. ) |
| 1 BHK | 23.71 Sq.mts. ( 255 Sq.ft. ) |
| 1 BHK | 25.26 Sq.mts. ( 272 Sq.ft. ) |
| 1 BHK | 28.72 Sq.mts. ( 309 Sq.ft. ) |
| 1 BHK | 29.1 Sq.mts. ( 313 Sq.ft. ) |
| 2 BHK | 37.71 Sq.mts. ( 406 Sq.ft. ) |
| 1 BHK | 24.89 Sq.mts. ( 268 Sq.ft. ) |
| 1 BHK | 25.38 Sq.mts. ( 273 Sq.ft. ) |
| 1 BHK | 25.46 Sq.mts. ( 274 Sq.ft. ) |
| 1 BHK | 29.13 Sq.mts. ( 314 Sq.ft. ) |
| 1RK | 15.34 Sq.mts. ( 165 Sq.ft. ) |
| 1 BHK | 25.25 Sq.mts. ( 272 Sq.ft. ) |
| 1 BHK | 28.75 Sq.mts. ( 309 Sq.ft. ) |
| 1 BHK | 30.71 Sq.mts. ( 331 Sq.ft. ) |
| 1 BHK | 22.48 Sq.mts. ( 242 Sq.ft. ) |
| 1 BHK | 22.72 Sq.mts. ( 245 Sq.ft. ) |
| 1 BHK | 23.55 Sq.mts. ( 253 Sq.ft. ) |
| 1 BHK | 23.81 Sq.mts. ( 256 Sq.ft. ) |
| 1 BHK | 24.74 Sq.mts. ( 266 Sq.ft. ) |
| 1 BHK | 22.65 Sq.mts. ( 244 Sq.ft. ) |
| 1 BHK | 23.49 Sq.mts. ( 253 Sq.ft. ) |
| 1 BHK | 24.03 Sq.mts. ( 259 Sq.ft. ) |
| 1 BHK | 24.65 Sq.mts. ( 265 Sq.ft. ) |
| 1 BHK | 24.76 Sq.mts. ( 267 Sq.ft. ) |
| 1 BHK | 30.39 Sq.mts. ( 327 Sq.ft. ) |
| 1 BHK | 30.4 Sq.mts. ( 327 Sq.ft. ) |
| 1 BHK | 30.45 Sq.mts. ( 328 Sq.ft. ) |
| 1 BHK | 23.59 Sq.mts. ( 254 Sq.ft. ) |
| 1 BHK | 27.53 Sq.mts. ( 296 Sq.ft. ) |
| 1 BHK | 23.33 Sq.mts. ( 251 Sq.ft. ) |
| 1 BHK | 24.93 Sq.mts. ( 268 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Tathastulast updated on 26 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station
|
|
Na |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting
|
|
Na |
|
|
|
As Per Plan |
Sewerage (Chamber, Lines, Septic Tank , STP)
|
|
- |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
- |
|
|
|
Existing |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Na |
Water Supply100% completed
|
|
Borewell |
Buildings / Wings in Tathastu
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Tathastu by Maharashtra Developerslast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
144
apartments in total
Saleable Area Statistics (Sq. ft.)
39808
Total
Total 144 apartments in project. 0 apartments booked. 0% apartments booked.
Total 39808 Sq.ft. saleable area. 0 saleable area booked.
0% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing A | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 23.53 Sq.mts. ( 253 Sq.ft. ) | 1 | |
| 1 BHK | 23.71 Sq.mts. ( 255 Sq.ft. ) | 4 | |
| 1 BHK | 25.26 Sq.mts. ( 272 Sq.ft. ) | 4 | |
| 1 BHK | 28.72 Sq.mts. ( 309 Sq.ft. ) | 1 | |
| 1 BHK | 29.1 Sq.mts. ( 313 Sq.ft. ) | 4 | |
| 2 BHK | 37.71 Sq.mts. ( 406 Sq.ft. ) | 4 | |
18 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing A | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing B | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 24.89 Sq.mts. ( 268 Sq.ft. ) | 4 | |
| 1 BHK | 25.38 Sq.mts. ( 273 Sq.ft. ) | 4 | |
| 1 BHK | 25.46 Sq.mts. ( 274 Sq.ft. ) | 1 | |
| 1 BHK | 29.13 Sq.mts. ( 314 Sq.ft. ) | 4 | |
| 1RK | 15.34 Sq.mts. ( 165 Sq.ft. ) | 4 | |
17 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing B | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing C | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 24.89 Sq.mts. ( 268 Sq.ft. ) | 4 | |
| 1 BHK | 25.25 Sq.mts. ( 272 Sq.ft. ) | 4 | |
| 1 BHK | 28.75 Sq.mts. ( 309 Sq.ft. ) | 1 | |
| 1 BHK | 30.71 Sq.mts. ( 331 Sq.ft. ) | 4 | |
| 1 RK | 15.34 Sq.mts. ( 165 Sq.ft. ) | 4 | |
17 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing C | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing D | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 22.48 Sq.mts. ( 242 Sq.ft. ) | 1 | |
| 1 BHK | 22.72 Sq.mts. ( 245 Sq.ft. ) | 1 | |
| 1 BHK | 23.55 Sq.mts. ( 253 Sq.ft. ) | 4 | |
| 1 BHK | 23.81 Sq.mts. ( 256 Sq.ft. ) | 4 | |
| 1 BHK | 24.74 Sq.mts. ( 266 Sq.ft. ) | 1 | |
| 1 BHK | 25.25 Sq.mts. ( 272 Sq.ft. ) | 4 | |
| 1 BHK | 30.71 Sq.mts. ( 331 Sq.ft. ) | 4 | |
19 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing D | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing E | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 22.65 Sq.mts. ( 244 Sq.ft. ) | 1 | |
| 1 BHK | 23.49 Sq.mts. ( 253 Sq.ft. ) | 4 | |
| 1 BHK | 24.03 Sq.mts. ( 259 Sq.ft. ) | 1 | |
| 1 BHK | 24.65 Sq.mts. ( 265 Sq.ft. ) | 4 | |
| 1 BHK | 24.76 Sq.mts. ( 267 Sq.ft. ) | 4 | |
| 1 BHK | 30.39 Sq.mts. ( 327 Sq.ft. ) | 1 | |
| 1 BHK | 30.4 Sq.mts. ( 327 Sq.ft. ) | 2 | |
| 1 BHK | 30.45 Sq.mts. ( 328 Sq.ft. ) | 2 | |
19 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing E | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing F | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 22.65 Sq.mts. ( 244 Sq.ft. ) | 1 | |
| 1 BHK | 23.59 Sq.mts. ( 254 Sq.ft. ) | 4 | |
| 1 BHK | 24.65 Sq.mts. ( 265 Sq.ft. ) | 4 | |
| 1 BHK | 24.76 Sq.mts. ( 267 Sq.ft. ) | 4 | |
| 1 BHK | 27.53 Sq.mts. ( 296 Sq.ft. ) | 1 | |
| 1 BHK | 30.4 Sq.mts. ( 327 Sq.ft. ) | 2 | |
| 1 BHK | 30.45 Sq.mts. ( 328 Sq.ft. ) | 2 | |
18 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing F | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing G | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 22.65 Sq.mts. ( 244 Sq.ft. ) | 1 | |
| 1 BHK | 23.59 Sq.mts. ( 254 Sq.ft. ) | 4 | |
| 1 BHK | 24.65 Sq.mts. ( 265 Sq.ft. ) | 4 | |
| 1 BHK | 24.76 Sq.mts. ( 267 Sq.ft. ) | 4 | |
| 1 BHK | 27.53 Sq.mts. ( 296 Sq.ft. ) | 1 | |
| 1 BHK | 30.4 Sq.mts. ( 327 Sq.ft. ) | 2 | |
| 1 BHK | 30.45 Sq.mts. ( 328 Sq.ft. ) | 2 | |
18 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing G | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Wing H | Mar 2022 | 5 | 1 | 0 | 1 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 22.65 Sq.mts. ( 244 Sq.ft. ) | 1 | |
| 1 BHK | 23.33 Sq.mts. ( 251 Sq.ft. ) | 4 | |
| 1 BHK | 24.65 Sq.mts. ( 265 Sq.ft. ) | 4 | |
| 1 BHK | 24.93 Sq.mts. ( 268 Sq.ft. ) | 4 | |
| 1 BHK | 27.53 Sq.mts. ( 296 Sq.ft. ) | 1 | |
| 1 BHK | 30.45 Sq.mts. ( 328 Sq.ft. ) | 4 | |
18 total apartments / 0 apartments booked. 0% apartments booked. |
| Work Description in Building Wing H | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | |
| Overall Percentage of Completion of the work done For the entire Building /Wing | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
| The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | |
| X number of Basement(s) and Plinth | |
| X number of Podiums | |
| X number of Slabs of Super Structure | |
Channel Partners Registered by Developer
Maharashtra Developers
for Project
Tathastu
last updated on
26 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |