Project overview

ProjectDeveloperLocationPossession
Project Details
  • Project:
  • Location:
  • Const. Stage:
  • Possession:
Developer Details

  • Developer:
  • Phone:
  • Address:
Project RERA Details
MAHA REARA No:
Project Type
RERA Project Status
Architect
Funding Bank
Proposed Possession
Revised Possession
Extended Possession
Litigations
Last Modified
Last Retrived
Apartment Details & Configuration
TypeArea
1 BHK28.45 Sq.mts. ( 306 Sq.ft. )
1 BHK28.66 Sq.mts. ( 308 Sq.ft. )
1 BHK31.52 Sq.mts. ( 339 Sq.ft. )
1 RK21.73 Sq.mts. ( 234 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of last updated on as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Meter Room Under Staircase Work Yet Not Started
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Tree Planting Work Yet Not Started
Open Parking
As Per Plan Work Yet Not Started
Sewerage (Chamber, Lines, Septic Tank , STP)
Work Yet Not Started
Solid Waste Management And Disposal
Na
Storm Water Drains
Work Yet Not Started
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting Work Yet Not Started
Water Supply
Mjp Will Provided Water Connection After Oc
Buildings / Wings in
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of by last updated on as per information obtained from MARA RERA.

Project Area

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

20 apartments in total
Total
20
Booked
11
Available
9

Saleable Area Statistics (Sq. ft.)

5940 Total
Total
5940
Booked
3258
Available
2682
Total 20 apartments in project. 11 apartments booked. 55% apartments booked.
Total 5940 Sq.ft. saleable area. 3258 saleable area booked.
55% area booked.

Tarabai Apartment

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Tarabai ApartmentDec 20195100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.45 Sq.mts. ( 306 Sq.ft. )5
2 Booked40% Booked
40% Booked
1 BHK28.66 Sq.mts. ( 308 Sq.ft. )5
3 Booked60% Booked
60% Booked
1 BHK31.52 Sq.mts. ( 339 Sq.ft. )5
3 Booked60% Booked
60% Booked
1 RK21.73 Sq.mts. ( 234 Sq.ft. )5
3 Booked60% Booked
60% Booked
20 total apartments / 11 apartments booked. 55% apartments booked.
Work Description in Building Tarabai ApartmentCompletion
Excavation
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress20% done
20% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress85% done
85% Booked
Channel Partners
Channel Partners Registered by Developer
for Project
last updated on as per information obtained from MARA RERA.
Name Company Location Mobile Designation