Project overview

Swastik Epitome Building 2 Phase I Ground To 7 Floors is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000006718. Swastik Epitome Building 2 Phase I Ground To 7 Floors is located at 185/B/1, 185/B/2, 185/B/3. This is a Ongoing being developed by Hemant Ramesh Mhatre.

Swastik Epitome Building 2 Phase I Ground To 7 Floors has 1 BHK & 1.5 BHK Apartments with carpet areas ranging from 394 to 474 Sq.ft. Carpet. The Project has total 182 of which 73 are currently available for sale.

Swastik Epitome Building 2 Phase I Ground To 7 Floors is being developed on a total land area of 36824 Sq.ft. out of which 30426 Sq.ft. i.e 83% is reserved for recreational purposes. Swastik Epitome Building 2 Phase I Ground To 7 Floors has 5 Wings / Towers C Wing,D Wing,E Wing,F Wing,G Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Swastik Epitome Building 2 Phase I Ground To 7 Floors
  • Location:
  • 185/B/1, 185/B/2, 185/B/3
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2019
Developer Details

  • Developer:
    Hemant Ramesh Mhatre
  • Phone:
  • Address:
  • Radha Krishna
Project RERA Details
MAHA REARA No: P99000006718
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect En Con
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2019
Revised Possession 31 Dec 2019
Extended Possession 31 Aug 2024
Litigations No Litigations
Last Modified 22 Jan 2025
Last Retrived 28 Jul 2025
Swastik Epitome Building 2 Phase I Ground To 7 Floors QR Code
Swastik Epitome Building 2 Phase I Ground To 7 Floors
MahaRERA - P99000006718
Apartment Details & Configuration
TypeArea
1 BHK38.55 Sq.mts. ( 415 Sq.ft. )
1.5 BHK46.41 Sq.mts. ( 500 Sq.ft. )
2 BHK49.24 Sq.mts. ( 530 Sq.ft. )
2 BHK49.35 Sq.mts. ( 531 Sq.ft. )
1 BHK36.59 Sq.mts. ( 394 Sq.ft. )
1 BHK37.5 Sq.mts. ( 404 Sq.ft. )
1 BHK37.94 Sq.mts. ( 408 Sq.ft. )
1.5 BHK41.98 Sq.mts. ( 452 Sq.ft. )
1.5 BHK43.53 Sq.mts. ( 469 Sq.ft. )
2 BHK57.84 Sq.mts. ( 623 Sq.ft. )
1 BHK37.19 Sq.mts. ( 400 Sq.ft. )
2 BHK55.39 Sq.mts. ( 596 Sq.ft. )
1 BHK36.76 Sq.mts. ( 396 Sq.ft. )
1 BHK37.33 Sq.mts. ( 402 Sq.ft. )
1 BHK37.97 Sq.mts. ( 409 Sq.ft. )
1.5 BHK44.07 Sq.mts. ( 474 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Swastik Epitome Building 2 Phase I Ground To 7 Floorslast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
2826.61 (Includes Common Rg Podium)
Club House10% completed
10% Complete
On Common Rg Podium As Part Of Complete Layout
Community Buildings
Cfc Plot As Approved
Electrical Meter Room, Sub-Station, Receiving Station20% completed
20% Complete
Part Of Complete Layout
Landscaping & Tree Planting
Part Of Complete Layout
Open Parking
36 Nos.
Sewerage (Chamber, Lines, Septic Tank , STP)
Stp To Be Provided As Part Of Complete Layout
Solid Waste Management And Disposal
Part Of Complete Layout
Storm Water Drains20% completed
20% Complete
Part Of Complete Layout
Street Lighting
Part Of Complete Layout
Temple
On Common Rg Podium As Part Of Complete Layout
Treatment And Disposal Of Sewage And Sullage Water
Part Of Complete Layout
Water Supply
To Be Provided By Vvcmc
Water Conservation, Rain water Harvesting
Part Of Complete Layout
Fire Protection And Fire Safety Requirements20% completed
20% Complete
Part Of Complete Layout
Energy management
Part Of Complete Layout
Buildings / Wings in Swastik Epitome Building 2 Phase I Ground To 7 Floors
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Swastik Epitome Building 2 Phase I Ground To 7 Floors by Hemant Ramesh Mhatrelast updated on 28 Jul 2025 as per information obtained from MARA RERA.

36824 Sq. ft.

Project Area

30426 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

182 apartments in total
Total
182
Booked
109
Available
73

Saleable Area Statistics (Sq. ft.)

83647 Total
Total
83647
Booked
50587
Available
33060
Total 182 apartments in project. 109 apartments booked. 59% apartments booked.
Total 83647 Sq.ft. saleable area. 50587 saleable area booked.
60% area booked.

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingDec 202081011713
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK38.55 Sq.mts. ( 415 Sq.ft. )7
7 Booked100% Booked
100% Booked
1.5 BHK46.41 Sq.mts. ( 500 Sq.ft. )7
7 Booked100% Booked
100% Booked
2 BHK49.24 Sq.mts. ( 530 Sq.ft. )8
6 Booked75% Booked
75% Booked
2 BHK49.35 Sq.mts. ( 531 Sq.ft. )6
3 Booked50% Booked
50% Booked
28 total apartments / 23 apartments booked. 82% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

D Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D WingJun 202181011713
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.59 Sq.mts. ( 394 Sq.ft. )7
4 Booked57% Booked
57% Booked
1 BHK37.5 Sq.mts. ( 404 Sq.ft. )7
2 Booked28% Booked
28% Booked
1 BHK37.94 Sq.mts. ( 408 Sq.ft. )7
6 Booked85% Booked
85% Booked
1.5 BHK41.98 Sq.mts. ( 452 Sq.ft. )7
3 Booked42% Booked
42% Booked
1.5 BHK43.53 Sq.mts. ( 469 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK57.84 Sq.mts. ( 623 Sq.ft. )7
3 Booked42% Booked
42% Booked
42 total apartments / 18 apartments booked. 42% apartments booked.
Work Description in Building D WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

E Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
E WingJun 202181011714
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK37.19 Sq.mts. ( 400 Sq.ft. )14
6 Booked42% Booked
42% Booked
2 BHK55.39 Sq.mts. ( 596 Sq.ft. )14
12 Booked85% Booked
85% Booked
28 total apartments / 18 apartments booked. 64% apartments booked.
Work Description in Building E WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

F Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
F WingJun 202181011714
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.59 Sq.mts. ( 394 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK37.5 Sq.mts. ( 404 Sq.ft. )7
3 Booked42% Booked
42% Booked
1 BHK37.94 Sq.mts. ( 408 Sq.ft. )7
6 Booked85% Booked
85% Booked
1.5 BHK41.98 Sq.mts. ( 452 Sq.ft. )7
2 Booked28% Booked
28% Booked
1.5 BHK43.53 Sq.mts. ( 469 Sq.ft. )7
6 Booked85% Booked
85% Booked
2 BHK57.84 Sq.mts. ( 623 Sq.ft. )7
5 Booked71% Booked
71% Booked
42 total apartments / 25 apartments booked. 59% apartments booked.
Work Description in Building F WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

G Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
G WingJun 202181011814
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK36.59 Sq.mts. ( 394 Sq.ft. )7
2 Booked28% Booked
28% Booked
1 BHK36.76 Sq.mts. ( 396 Sq.ft. )7
7 Booked100% Booked
100% Booked
1 BHK37.33 Sq.mts. ( 402 Sq.ft. )7
5 Booked71% Booked
71% Booked
1 BHK37.97 Sq.mts. ( 409 Sq.ft. )14
10 Booked71% Booked
71% Booked
1.5 BHK44.07 Sq.mts. ( 474 Sq.ft. )7
42 total apartments / 25 apartments booked. 59% apartments booked.
Work Description in Building G WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress80% done
80% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
work-in-progress60% done
60% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Hemant Ramesh Mhatre
for Project
Swastik Epitome Building 2 Phase I Ground To 7 Floors
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation