Project overview

Surya Cooperative Housing Society Ltd is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800018358. Surya Cooperative Housing Society Ltd is located at 61/1 To 3 Of Village Ismaliya, 61. This is a New being developed by Dipti Home Makers Pvt Ltd.

Surya Cooperative Housing Society Ltd has 1 BHK & 2 BHK Apartments with carpet areas ranging from 340 to 661 Sq.ft. Carpet. The Project has total 12 of which 5 are currently available for sale.

Surya Cooperative Housing Society Ltd is being developed on a total land area of 9428 Sq.ft. Surya Cooperative Housing Society Ltd has 1 Wings / Towers Surya Cooperative Housing Society Limited

ProjectDeveloperLocationPossession
Vijaylaxmi BlissVijaylaxmi Infracon LlpCts No 25 Plot No 530-06-2018 00:00:00
Nirant ApartmentAditi Constructions6351 To 531-12-2018 00:00:00
Shri Krishna Kunj Chs LtdEllora DevelopersCts No 202 202/1 To 3331-12-2018 00:00:00
Rishabh TowerVipul Pravinchandra Shah806/1, Cts, 80630-06-2018 00:00:00
Rathod NiwasAim Construction Co.7130-06-2019 00:00:00
Dlh Dream TowerDev Land & Housing Pvt Ltd407And 408, 39430-09-2019 00:00:00
Rajal ClassicNisar RealtorService Road31-12-2018 00:00:00
Bhawani HeightsM/S Bhawani DevelopersCts No 61 Part30-08-2020 00:00:00
Ashok SmrutiNew India Construction Company400069, Mumbai Suburban02-06-2012 00:00:00
Prem BuildersPrem Builders81A 81A 3 To 51 81C Pt25-10-2024 00:00:00
Lawns And Beyond - Phase 3, Omkar International DistrictOmkar Ventures Pvt. Ltd.400060, Mumbai Suburban30-03-2023 00:00:00
Lawns And Beyond - Phase 2, Omkar International DistrictOmkar Ventures Pvt. Ltd.Mumbai Suburban, 40006030-03-2023 00:00:00
Platinum Tower - 31Manas Gruhpravesh LlpCts No 195 Pt, Survey No 106-A30-06-2022 00:00:00
RajalNisar Properties Pvt. Ltd.Cts No 11530-06-2023 00:00:00
Shantiniketan 2 Chs LtdS D Bhalerao Constructions Pvt Ltd40005830-09-2015 00:00:00
State Bank Of India Employees Sakar Swapna ChslSelf Redevelopment Of State Bank Of India Employees Sakar Swapna Chsl17930-04-2025 00:00:00
Ratan HeritageNexus Builders & Developers254, 254/1 To 12431-12-2025 00:00:00
Rishabraj GardeniaH Rishabraj Realty67/2, 67/1, 6731-12-2024 00:00:00
The Residency Lak & Hanware Realty Llp520/1 To 520/8, Cts No 52030-06-2021 00:00:00
Royal Fantasy Phase IiRoyal Fantasy Constructions Private LimitedCts No 424, 424/1 To 3330-06-2019 00:00:00
Sheel EnclavesPoddar Infracon Private Limited160 160/1 To 630-12-2021 00:00:00
KalaniketanSiroyafm Constructions Pvt LtdCts F/734 Plot No. 28431-03-2018 00:00:00
Royal Fantasy Phase IiiRoyal Fantasy Constructions Private Limited424, 424/131-12-2019 00:00:00
Suparshwa UrbanaSuparshwa Estate133/1, 133/1/1 To 6731-12-2019 00:00:00
Lawns And Beyond - Phase 1, Omkar International DistrictOmkar Ventures Pvt. Ltd.400060, Mumbai Suburban30-03-2023 00:00:00
Aim Residency Phase IA M Enterprises285 1 To 4 And 288 1 To 2830-03-2024 00:00:00
Innovative InfoparkKhushi Developers8801-08-2019 00:00:00
Sale Building No 1 Vaastu Shanti Wing A B CM/S Anshuman DevelopersCts No 364 A230-06-2019 00:00:00
Sanskruti Building No 2 C WingNirman Realtors And Developers Ltd273 275 And 276 S No 20 H No 71430-12-2025 00:00:00
Suparshwa EterniaSuparshwa Estate133/1, 133/1/1 To 6731-12-2019 00:00:00
Platinum Tower - 1Akshay Gruhpravesh Llp1/6A, Survey No 106/1A, 195 Pt31-03-2020 00:00:00
Platinum Tower-4Shivkrupa Gruhpravesh Llp1/6A, Survey No 106/1A, 195 Pt30-09-2019 00:00:00
Krishna Milan HeightsMilan Interbuilt Private LimitedCts No.141 A, 141 A 1 To 2831-12-2024 00:00:00
Devine Mercy Sra Chs Prop.Mahesh MestryKevanipada, 26-10-2021 00:00:00
Surya Cooperative Housing Society LtdDipti Home Makers Pvt Ltd61/1 To 3 Of Village Ismaliya, 6130-12-2024 00:00:00
SilvereneShreeji CombineF/48931-12-2018 00:00:00
Maruti BhuvanSuresh Prabhushankar Sharma135, 135 1 To 1227-03-2019 00:00:00
Avenue Park - I Cb Enterprises593, 590, 592/1 T O 12, 594/1 To 37, 590/1 To 6, 59430-06-2022 00:00:00
Om Shivalaya Chs LtdDipti Home Makers Pvt LtdCts No. 72, 72 1 To 4 Of Village Ismaliya31-12-2025 00:00:00
Aim ParadiseS.K. Enterprises84, 84/1 To 5031-12-2026 00:00:00
Regent GrandeurRegent AssociatesPlot No 231-12-2025 00:00:00
Bhagwati AshishPritesh Damji Savla1215-11-2020 00:00:00
Kenorita Garment HubKeshvi Developers Pvt Ltd20631-03-2018 00:00:00
Sethia DarshanSethia Infrastructure Pvt Ltd524, 524 /1 To 14 Of Village Kurar And 358, 358 /1 To 11 Of Village Malad East30-12-2024 00:00:00
Rameshwar DarshanArcadia Developers Private LimitedCts No 1331-12-2017 00:00:00
Suvidha SquareSuvidha Milind Business VenturesCts 13A31-12-2019 00:00:00
Jangid AnnexeJangid Home Pvt Ltd83A Part, Village Majas31-12-2018 00:00:00
Sai GabhastiSai Corporation8331-12-2017 00:00:00
Rosalia ApartmentsKusum Associates48130-07-2020 00:00:00
Vardhman GrandeurVardhman Developers Ltd64/1-26, 6430-12-2019 00:00:00
A And O PalazzioAshapura Options Private LimitedCts 270Apt - 270A -1 To 22 And 29 To 32A31-07-2018 00:00:00
HansaAmn Enterprises118/ 1 To 9, 11830-12-2023 00:00:00
Palmrose BHillview VenturesCts 42 Pt30-12-2025 00:00:00
Regent Orchid - Hema Niwas ChslRdb Mumbai Infrastructures Private Limited123 / 1 To 3, 12330-09-2018 00:00:00
Regent Heights-New Ganga Niwas ChslRdb Mumbai Infrastructures Private Limited126, 126 / 1 And 230-06-2019 00:00:00
Rolex Sra ChsSquare Constructions253/1 To 26, 25331-03-2019 00:00:00
Aim PlatinumAim Realtors Private Limited287/1 To 6, 274/1 To 15 And 287, 27430-12-2025 00:00:00
Romell MyraRomell Properties Private Limited38230-12-2024 00:00:00
Romell OrbisRomell Properties Private Limited36530-12-2024 00:00:00
Aim HeritageM/S Aim Realtors Private Limited87 Of Village Ismalia31-12-2026 00:00:00
Horizon TowerI.R.Developers Llp368/301 ,368/30231-03-2026 00:00:00
Girnar Residency Wing B Phase 1Nidhaan Realty Llp175A ,183C31-12-2026 00:00:00
Ranes Trimurti ChslNew Laxmi EnterprisesMogra, 400060, Natwar Nagar Road Number 101-05-2028 00:00:00
Raj VegaRajesh Arvind Surti344 344/1 To 831-12-2029 00:00:00
Elite HomesMassif Infrastructure Developers8931-12-2029 00:00:00
Millionaire HeritageMillionaire Reality66/1 To 51, 6630-12-2023 00:00:00
ShivsolitaireSo Lucky BuildersMumbai City, 40006031-12-2018 00:00:00
Project Details
  • Project:
    Surya Cooperative Housing Society Ltd
  • Location:
  • 61/1 To 3 Of Village Ismaliya, 61
  • Const. Stage:
    New
  • Possession:
    30 Dec 2024
Developer Details

  • Developer:
    Dipti Home Makers Pvt Ltd
  • Phone:
  • Address:
  • Hendre Castle
Project RERA Details
MAHA REARA No: P51800018358
Project Type Residential / Group Housing
RERA Project Status New
Architect Mr Rajendra Pagnis
Funding Bank STATE BANK OF INDIA
Proposed Possession 30 Dec 2024
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 26 Oct 2018
Last Retrived 26 Jul 2025
Surya Cooperative Housing Society Ltd QR Code
Surya Cooperative Housing Society Ltd
MahaRERA - P51800018358
Apartment Details & Configuration
TypeArea
1 BHK31.59 Sq.mts. ( 340 Sq.ft. )
1 BHK37.9 Sq.mts. ( 408 Sq.ft. )
1 BHK40.88 Sq.mts. ( 440 Sq.ft. )
1 BHK41.81 Sq.mts. ( 450 Sq.ft. )
1 BHK43.01 Sq.mts. ( 463 Sq.ft. )
1 BHK43.29 Sq.mts. ( 466 Sq.ft. )
1 BHK43.39 Sq.mts. ( 467 Sq.ft. )
1 BHK44.96 Sq.mts. ( 484 Sq.ft. )
2 BHK54.72 Sq.mts. ( 589 Sq.ft. )
2 BHK56.86 Sq.mts. ( 612 Sq.ft. )
2 BHK59.27 Sq.mts. ( 638 Sq.ft. )
2 BHK61.41 Sq.mts. ( 661 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Surya Cooperative Housing Society Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station70% completed
70% Complete
Will Be Done As Per Approval
Energy management
Na
Fire Protection And Fire Safety Requirements70% completed
70% Complete
Will Be Done As Per Approval
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)70% completed
70% Complete
Will Be Done As Per Approval
Solid Waste Management And Disposal
Na
Storm Water Drains70% completed
70% Complete
Will Be Done As Per Approval
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting70% completed
70% Complete
Will Be Done As Per Approval
Water Supply70% completed
70% Complete
Will Be Done As Per Approval
Buildings / Wings in Surya Cooperative Housing Society Ltd
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Surya Cooperative Housing Society Ltd by Dipti Home Makers Pvt Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

9428 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

12 apartments in total
Total
12
Booked
7
Available
5

Saleable Area Statistics (Sq. ft.)

6018 Total
Total
6018
Booked
3580
Available
2438
Total 12 apartments in project. 7 apartments booked. 58% apartments booked.
Total 6018 Sq.ft. saleable area. 3580 saleable area booked.
59% area booked.

Surya Cooperative Housing Society Limited

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Surya Cooperative Housing Society LimitedDec 2023101010214
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.59 Sq.mts. ( 340 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK37.9 Sq.mts. ( 408 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK40.88 Sq.mts. ( 440 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK41.81 Sq.mts. ( 450 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK43.01 Sq.mts. ( 463 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK43.29 Sq.mts. ( 466 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK43.39 Sq.mts. ( 467 Sq.ft. )1
1 Booked100% Booked
100% Booked
1 BHK44.96 Sq.mts. ( 484 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK54.72 Sq.mts. ( 589 Sq.ft. )1
None Booked0% Booked
0% Booked
2 BHK56.86 Sq.mts. ( 612 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK59.27 Sq.mts. ( 638 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK61.41 Sq.mts. ( 661 Sq.ft. )1
None Booked0% Booked
0% Booked
12 total apartments / 7 apartments booked. 58% apartments booked.
Work Description in Building Surya Cooperative Housing Society LimitedCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress80% done
80% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress75% done
75% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress90% done
90% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Dipti Home Makers Pvt Ltd
for Project
Surya Cooperative Housing Society Ltd
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation