Project overview

Supreme Madhukar is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800032692. Supreme Madhukar is located at Tps Iii Borivali At Kastur Park, Cts No 620/17 Of Village Borivali. This is a New being developed by Supreme Enterprise.

Supreme Madhukar has 2 BHK, 3 BHK, Office space & Shop Apartments with carpet areas ranging from 137 to 102 Sq.ft. Carpet. The Project has total 31 of which 2 are currently available for sale.

Supreme Madhukar is being developed on a total land area of 11722 Sq.ft. Supreme Madhukar has 2 Wings / Towers Wing A,Wing B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Supreme Madhukar
  • Location:
  • Tps Iii Borivali At Kastur Park, Cts No 620/17 Of Village Borivali
  • Const. Stage:
    New
  • Possession:
    05 Jan 2025
Developer Details

  • Developer:
    Supreme Enterprise
  • Phone:
  • Address:
  • Mangal Aarambh
Project RERA Details
MAHA REARA No: P51800032692
Project Type Others
RERA Project Status New
Architect Mhatre Wagle Shirgaonkar
Funding Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
Proposed Possession 05 Jan 2025
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 24 Jan 2022
Last Retrived 26 Jul 2025
Supreme Madhukar QR Code
Supreme Madhukar
MahaRERA - P51800032692
Apartment Details & Configuration
TypeArea
2 BHK58.11 Sq.mts. ( 625 Sq.ft. )
2 BHK63.14 Sq.mts. ( 680 Sq.ft. )
3 BHK71.1 Sq.mts. ( 765 Sq.ft. )
3 BHK81.9 Sq.mts. ( 882 Sq.ft. )
Office space97.3 Sq.mts. ( 1047 Sq.ft. )
Shop10.22 Sq.mts. ( 110 Sq.ft. )
Shop12.73 Sq.mts. ( 137 Sq.ft. )
Shop13.38 Sq.mts. ( 144 Sq.ft. )
Shop13.85 Sq.mts. ( 149 Sq.ft. )
2 BHK54.55 Sq.mts. ( 587 Sq.ft. )
2 BHK61.15 Sq.mts. ( 658 Sq.ft. )
Office space64.59 Sq.mts. ( 695 Sq.ft. )
Shop9.48 Sq.mts. ( 102 Sq.ft. )
Shop17.84 Sq.mts. ( 192 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Supreme Madhukarlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station90% completed
90% Complete
Will Be Provided Before Possession
Energy management
Na
Fire Protection And Fire Safety Requirements80% completed
80% Complete
Will Be Provided Before Possession
Landscaping & Tree Planting90% completed
90% Complete
Will Be Provided Before Possession
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)90% completed
90% Complete
Will Be Provided Before Possession
Solid Waste Management And Disposal90% completed
90% Complete
Will Be Provided By Mcgm
Storm Water Drains90% completed
90% Complete
Will Be Provided Before Possession
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting90% completed
90% Complete
Will Be Provided Before Possession
Water Supply90% completed
90% Complete
Will Be Provided Before Possession
Buildings / Wings in Supreme Madhukar
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Supreme Madhukar by Supreme Enterpriselast updated on 26 Jul 2025 as per information obtained from MARA RERA.

11722 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

31 apartments in total
Total
31
Booked
29
Available
2

Saleable Area Statistics (Sq. ft.)

14591 Total
Total
14591
Booked
13831
Available
760
Total 31 apartments in project. 29 apartments booked. 93% apartments booked.
Total 14591 Sq.ft. saleable area. 13831 saleable area booked.
95% area booked.

Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing AMay 202510100001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK58.11 Sq.mts. ( 625 Sq.ft. )1
1 Booked100% Booked
100% Booked
2 BHK63.14 Sq.mts. ( 680 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK71.1 Sq.mts. ( 765 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK81.9 Sq.mts. ( 882 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space97.3 Sq.mts. ( 1047 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop10.22 Sq.mts. ( 110 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop12.73 Sq.mts. ( 137 Sq.ft. )3
3 Booked100% Booked
100% Booked
Shop13.38 Sq.mts. ( 144 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop13.85 Sq.mts. ( 149 Sq.ft. )1
1 Booked100% Booked
100% Booked
12 total apartments / 12 apartments booked. 100% apartments booked.
Work Description in Building Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress85% done
85% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BMay 202510100001
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK54.55 Sq.mts. ( 587 Sq.ft. )8
8 Booked100% Booked
100% Booked
2 BHK61.15 Sq.mts. ( 658 Sq.ft. )3
2 Booked66% Booked
66% Booked
3 BHK81.9 Sq.mts. ( 882 Sq.ft. )1
1 Booked100% Booked
100% Booked
Office space64.59 Sq.mts. ( 695 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop9.48 Sq.mts. ( 102 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop12.73 Sq.mts. ( 137 Sq.ft. )3
3 Booked100% Booked
100% Booked
Shop13.38 Sq.mts. ( 144 Sq.ft. )1
1 Booked100% Booked
100% Booked
Shop17.84 Sq.mts. ( 192 Sq.ft. )1
1 Booked100% Booked
100% Booked
19 total apartments / 17 apartments booked. 89% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress90% done
90% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress86% done
86% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress90% done
90% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress90% done
90% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Supreme Enterprise
for Project
Supreme Madhukar
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation