Project overview

Sunrise C is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700000625. Sunrise C is located at S. No. 104/16-Part Of Village Balkum. This is a Ongoing being developed by Agile Real Estate Pvt. Ltd..

Sunrise C has 1 BHK & 2 BHK Premium Apartments with carpet areas ranging from 1933 to 86856 Sq.ft. Carpet. The Project has total 126 of which 13 are currently available for sale.

Sunrise C is being developed on a total land area of 5673 Sq.ft. Sunrise C has 1 Wings / Towers Wing C - Ebony

ProjectDeveloperLocationPossession
Sunrise CAgile Real Estate Pvt. Ltd.S. No. 104/16-Part Of Village Balkum30-12-2023 00:00:00
Sunrise AAgile Real Estate Pvt. Ltd.S. No. 97/5-Part,97/6C-Part Of Village Balkum30-12-2023 00:00:00
Sunrise DAgile Real Estate Pvt. Ltd.S. No. 104/16-Part,97/1-Part, 95/26C-Part Of Village Balkum30-12-2023 00:00:00
Immensa DAgile Real Estate Pvt. Ltd.S.No.90/3A-Part,95/2-Part,90/3C-Part Of Village Balkum30-12-2025 00:00:00
Marigold B WingShree Tirupati Greenfield Developers1/1C, 1/1D, 1/1E, 1/1F, 1/1G30-12-2022 00:00:00
Highland Springs B4- A WingSiddhi Real Estate Developers74/5Apart30-06-2023 00:00:00
Highland Park Building 2- K25 Wing A Phase 2Siddhi Gaurav EnterprisesS. N. 87/2 And 82/630-12-2024 00:00:00
Saptashree HeightsSaptashree Reality Private LimitedGut No 25 Hissa No 2 , 331-05-2018 00:00:00
Sunrise BAgile Real Estate Pvt. Ltd.S. No. 104/16-Part Of Village Balkum30-12-2023 00:00:00
Immensa EAgile Real Estate Pvt. Ltd.S.No.90/3C-Part,95/8-Part,95/9-Part Of Village Balkum30-12-2025 00:00:00
Sunrise EAgile Real Estate Pvt. Ltd.S. No.97/1-Part,97/2-Part30-12-2023 00:00:00
Immensa BAgile Real Estate Pvt. Ltd.S.No.95/1-Part,95/3-Part,95/7A-Part Of Village Balkum30-12-2025 00:00:00
Lodha Amara - Tower 20, 21Macrotech Developers Limited69/1 And 69/330-09-2023 00:00:00
The Icon Phase 1Leading Frontier Private LimitedSurvey No 60/18,60/19,Survey No 61/2A To 61/2F, 61/3,62/3,62/5E,62/6,62/7,62/9C30-12-2022 00:00:00
Lodha Amara - Tower 29,31Macrotech Developers LimitedNew S.Nos. 63/5,64/230-07-2022 00:00:00
Lodha Amara - Tower 32,33Macrotech Developers LimitedNew S.Nos. 64/2,64/3, 64/728-08-2022 00:00:00
Immensa AAgile Real Estate Pvt. Ltd.S No.95/7A-Part,95/13-Part,95/7B-Part Of Village Of Balkum30-12-2025 00:00:00
Immensa CAgile Real Estate Pvt. Ltd.S. No.91-Part30-12-2025 00:00:00
Lodha Amara - Tower 1 - 5, 7 - 19 Macrotech Developers LimitedNew Snos62/0,63/1,63/2,63/3,63/4,63/5,63/6,63/7,63/8,63/9,64/4,64/530-11-2019 00:00:00
Immensa GAgile Real Estate Pvt. Ltd.S.No.95/7C-Part,89/6-Part,95/16-Part Of Village Balkum30-12-2025 00:00:00
Immensa FAgile Real Estate Pvt. Ltd.S. No.95/9-Part,95/7C-Part Of Village Balkum30-12-2025 00:00:00
Immensa HAgile Real Estate Pvt. Ltd.S. No.95/7B-Part ,95/13-Part Of Village Balkum30-12-2025 00:00:00
Runwal PearlRunwal Construction Private LimitedGut No 21/B1 Gut No 21/B231-05-2019 00:00:00
Mayfair HeliosRaj Laxmi DevelopersNew Survey No 104/17 Of Village Balkum Thane31-12-2022 00:00:00
Pride Palms Majesty A1-B1 Phase 1Larkins RealtorsS.N.- 29/3 A,B31-12-2018 00:00:00
Highland Springs B4- C WingSiddhi Real Estate Developers74/5A 59/1A 59/1B 46/1830-12-2023 00:00:00
Dosti West County - Dosti OakDosti EnterprisesNew Survey No 17/1, 17/2, 17/3Pt, 19/23, 19/29, 19/30Pt30-06-2022 00:00:00
Elite Solitaire 15Vijay Associates (Wadhwa)Part Of Survey No 37-1330-12-2021 00:00:00
Terraform ArcadeMoney Magnum Constructions37/10, 38/1, 146/1, 146/2P31-07-2022 00:00:00
Pride Palms Queens A2 Phase 2Larkins RealtorsS.N.- 28 And S.N.- 29/3 A,B,C30-12-2021 00:00:00
Vardhman Garden Phase IiDiwali Construction CompanyThane31-12-2022 00:00:00
Highland Springs B4- E WingSiddhi Real Estate Developers46/18Pt, 47/13Pt31-10-2019 00:00:00
Sector 5 - Wing CAgile Real Estate Pvt. Ltd.New S No 89/1 Part 89/2/B Part 89/3 Part 89/4 Part 89/5 Part Of Village Balkum30-12-2027 00:00:00
Highland Park Building 6 And 7- K23 Phase 1Siddhi Gaurav EnterprisesS. N. 85 And 87/231-12-2019 00:00:00
Pride Palms Queens B2 Phase 3Larkins RealtorsS.N.- 28 And S.N. 29/3 A,B,C30-12-2021 00:00:00
Highland Springs B4- B WingSiddhi Real Estate Developers74/5A30-06-2023 00:00:00
Sector 5 - Wing AAgile Real Estate Pvt. Ltd.New S No.79/9 Part30-12-2027 00:00:00
Sector 5 - Wing BAgile Real Estate Pvt. Ltd.New S No 79/7 Part 83/1 Part 83/2A Part 89/3 Part Of Village Balkum30-12-2027 00:00:00
Terraform K - ResidencesMoney Magnum ConstructionsPart Of 37/10, 38/1, 146/1, 146/2P30-09-2023 00:00:00
Runwal Eirene - Part IRunwal Developers Private LimitedSurvey Nos As Documented30-06-2025 00:00:00
Project Details
  • Project:
    Sunrise C
  • Location:
  • S. No. 104/16-Part Of Village Balkum
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    Agile Real Estate Pvt. Ltd.
  • Phone:
  • Address:
  • Kalpataru Synergy
Project RERA Details
MAHA REARA No: P51700000625
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Dsp Design Associates Pvt. Ltd.
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession
Litigations No Litigations
Last Modified 16 Jul 2018
Last Retrived 26 Jul 2025
Sunrise C QR Code
Sunrise C
MahaRERA - P51700000625
Apartment Details & Configuration
TypeArea
1 BHK179.56 Sq.mts. ( 1933 Sq.ft. )
2 BHK Premium8069.12 Sq.mts. ( 86856 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sunrise Clast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
2 No. of Common Basement100% completed
95% Complete
Common Development As Per Afs
2 Nos. of Common Podiums100% completed
95% Complete
Common Development As Per Afs
Aggregate area of recreational Open Space100% completed
95% Complete
7328 Sq Mt Common Rg As Per Afs
Club house, fitness centers, swimming pool & other recreation areas83% completed
83% Complete
Common Amenities As Per Afs
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Energy management55% completed
55% Complete
To Be Done Before Completion Of Whole Project
Fire Protection And Fire Safety Requirements95% completed
95% Complete
To Be Done Before Completion Of Whole Project
Landscaping & Tree Planting99% completed
99% Complete
To Be Done Before Completion Of Whole Project
Open Parking
To Be Done Before Completion Of Whole Project
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Stp Only
Solid Waste Management And Disposal100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Storm Water Drains100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Street Lighting100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Water Conservation, Rain water Harvesting100% completed
95% Complete
To Be Done Before Completion Of Whole Project
Water Supply60% completed
60% Complete
Supply From Local Authority
Buildings / Wings in Sunrise C
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sunrise C by Agile Real Estate Pvt. Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.

5673 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

126 apartments in total
Total
126
Booked
113
Available
13

Saleable Area Statistics (Sq. ft.)

10604164 Total
Total
10604164
Booked
9814729
Available
789435
Total 126 apartments in project. 113 apartments booked. 89% apartments booked.
Total 10604164 Sq.ft. saleable area. 9814729 saleable area booked.
93% area booked.

Wing C - Ebony

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing C - EbonyDec 202227121254268
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK179.56 Sq.mts. ( 1933 Sq.ft. )4
None Booked0% Booked
0% Booked
2 BHK Premium8069.12 Sq.mts. ( 86856 Sq.ft. )122
113 Booked92% Booked
92% Booked
126 total apartments / 113 apartments booked. 89% apartments booked.
Work Description in Building Wing C - EbonyCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress96% done
96% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress96% done
96% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress95% done
95% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress95% done
95% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress36% done
36% Booked
Sanitary Fittings within the flats / premises
work-in-progress36% done
36% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress95% done
95% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Agile Real Estate Pvt. Ltd.
for Project
Sunrise C
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation