Project overview

Sumer Trinity Vertical Phase-I is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900017371. Sumer Trinity Vertical Phase-I is located at 1055 And 1056. This is a Ongoing being developed by Sumer Builders.

Sumer Trinity Vertical Phase-I has 4 BHK & 5 BHK Apartments with carpet areas ranging from 2952 to 4500 Sq.ft. Carpet. The Project has total 55 of which 47 are currently available for sale.

Sumer Trinity Vertical Phase-I is being developed on a total land area of 25177 Sq.ft. Sumer Trinity Vertical Phase-I has 1 Wings / Towers Vertical

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sumer Trinity Vertical Phase-I
  • Location:
  • 1055 And 1056
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2023
Developer Details

  • Developer:
    Sumer Builders
  • Phone:
  • Address:
  • Peninsula Corporate Park
Project RERA Details
MAHA REARA No: P51900017371
Project Type Others
RERA Project Status Ongoing
Architect Ar Purvi Somaya
Funding Bank YES BANK
Proposed Possession 30 Jun 2023
Revised Possession 30 Jun 2023
Extended Possession 30 Jun 2024
Litigations No Litigations
Last Modified 09 Sep 2021
Last Retrived 26 Jul 2025
Sumer Trinity Vertical Phase-I QR Code
Sumer Trinity Vertical Phase-I
MahaRERA - P51900017371
Apartment Details & Configuration
TypeArea
4 BHK274.24 Sq.mts. ( 2952 Sq.ft. )
4 BHK275.42 Sq.mts. ( 2965 Sq.ft. )
4 BHK290.54 Sq.mts. ( 3127 Sq.ft. )
4 BHK290.63 Sq.mts. ( 3128 Sq.ft. )
4 BHK294.62 Sq.mts. ( 3171 Sq.ft. )
4 BHK294.79 Sq.mts. ( 3173 Sq.ft. )
5 BHK388.68 Sq.mts. ( 4184 Sq.ft. )
5 BHK392.51 Sq.mts. ( 4225 Sq.ft. )
5 BHK418.04 Sq.mts. ( 4500 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sumer Trinity Vertical Phase-Ilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
36 Seater Lounge theater in Club House100% completed
95% Complete
As Per Approved Plan
6 Guest Rooms in Club House100% completed
95% Complete
As Per Approved Plan
Aggregate area of recreational Open Space
Na
Amber Terrace in Club House100% completed
95% Complete
As Per Approved Plan
Amphitheater
As Per Approved Plan
CCTV Cameras in Public Area
As Per Mcgm Norms
Club House100% completed
95% Complete
As Per Approved Plan
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station75% completed
75% Complete
As Per Approved Plan
Energy management
As Per Mcgm Norms
Fire Protection And Fire Safety Requirements
As Per Mcgm Norms
Gymnasium in Club House100% completed
95% Complete
As Per Approved Plan
Kids Bubble and Slide pool in Layout100% completed
95% Complete
As Per Approved Plan
Kids play area in Layout100% completed
95% Complete
As Per Approved Plan
Landscaping & Tree Planting60% completed
60% Complete
As Per Approved Plan
Luggage Screening in Lobby
Before Possession
Multi Cuisine Commercial Kitchen in Club House100% completed
95% Complete
As Per Approved Plan
Multipurpose Intelligent games court in Club House100% completed
95% Complete
As Per Approved Plan
Multipurpose Studio for Yoga Aerobics and Zumba in Club House100% completed
95% Complete
As Per Approved Plan
Open Parking
Na
Pavilions with shaded seating with Alfresco Dining in Layout100% completed
95% Complete
As Per Approved Plan
Pedestrian Walking Jogging track in Layout60% completed
60% Complete
As Per Approved Plan
Restaurant Cafe and banquet hall
As Per Approved Plan
Salon and Spa in Club House100% completed
95% Complete
As Per Approved Plan
Senior Citizens corner in Layout
As Per Approved Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
As Per Mcgm Norms
Solid Waste Management And Disposal
As Per Mcgm Norms
Squash Court in Club House100% completed
95% Complete
As Per Approved Plan
Storm Water Drains
As Per Mcgm Norms
Street Lighting
To Be Provided By Promoter
Study Reading area in Building
As Per Approved Plan
Swimming Pool and Deck in Layout100% completed
95% Complete
As Per Approved Plan
Tennis Court in Layout
As Per Approved Plan
Treatment And Disposal Of Sewage And Sullage Water
As Per Mcgm Norms
Water Conservation, Rain water Harvesting
As Per Mcgm Norms
Water Supply
As Per Mcgm Norms
Buildings / Wings in Sumer Trinity Vertical Phase-I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sumer Trinity Vertical Phase-I by Sumer Builderslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

25177 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

55 apartments in total
Total
55
Booked
8
Available
47

Saleable Area Statistics (Sq. ft.)

173696 Total
Total
173696
Booked
24524
Available
149172
Total 55 apartments in project. 8 apartments booked. 14% apartments booked.
Total 173696 Sq.ft. saleable area. 24524 saleable area booked.
14% area booked.

Vertical

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
VerticalDec 20223113120138
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
4 BHK274.24 Sq.mts. ( 2952 Sq.ft. )15
4 BHK275.42 Sq.mts. ( 2965 Sq.ft. )15
4 BHK290.54 Sq.mts. ( 3127 Sq.ft. )1
None Booked0% Booked
0% Booked
4 BHK290.63 Sq.mts. ( 3128 Sq.ft. )1
None Booked0% Booked
0% Booked
4 BHK294.62 Sq.mts. ( 3171 Sq.ft. )9
4 BHK294.79 Sq.mts. ( 3173 Sq.ft. )9
3 Booked33% Booked
33% Booked
5 BHK388.68 Sq.mts. ( 4184 Sq.ft. )2
None Booked0% Booked
0% Booked
5 BHK392.51 Sq.mts. ( 4225 Sq.ft. )1
None Booked0% Booked
0% Booked
5 BHK418.04 Sq.mts. ( 4500 Sq.ft. )2
None Booked0% Booked
0% Booked
55 total apartments / 8 apartments booked. 14% apartments booked.
Work Description in Building VerticalCompletion
Basement (if any)
work-in-progress70% done
70% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
work-in-progress70% done
70% Booked
Podiums (if any)
work-in-progress50% done
50% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress45% done
45% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
work-in-progress70% done
70% Booked
X number of Podiums
work-in-progress50% done
50% Booked
X number of Slabs of Super Structure
work-in-progress45% done
45% Booked
Channel Partners
Channel Partners Registered by Developer
Sumer Builders
for Project
Sumer Trinity Vertical Phase-I
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation