Project overview

Spring Field is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000004250. Spring Field is located at Gut No 70, Plot No 1 To 11. This is a Ongoing being developed by M/S. Shyam Sagar Developers.

Spring Field has 1 BHK & 2 BHK Apartments with carpet areas ranging from 336 to 458 Sq.ft. Carpet. The Project has total 144 of which 96 are currently available for sale.

Spring Field is being developed on a total land area of 74035 Sq.ft. out of which 9010 Sq.ft. i.e 12% is reserved for recreational purposes. Spring Field has 4 Wings / Towers Bldg No 1,Bldg No 2,Bldg No 5,Bldg No 6

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Spring Field
  • Location:
  • Gut No 70, Plot No 1 To 11
  • Const. Stage:
    Ongoing
  • Possession:
    30 Dec 2023
Developer Details

  • Developer:
    M/S. Shyam Sagar Developers
  • Phone:
  • Address:
  • Gold Crest Business Centre
Project RERA Details
MAHA REARA No: P99000004250
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Sudhir R Magdum
Funding Bank HDFC BANK
Proposed Possession 30 Dec 2023
Revised Possession 30 Dec 2023
Extended Possession 30 Jun 2027
Litigations No Litigations
Last Modified 04 Mar 2024
Last Retrived 28 Jul 2025
Spring Field QR Code
Spring Field
MahaRERA - P99000004250
Apartment Details & Configuration
TypeArea
1 BHK31.17 Sq.mts. ( 336 Sq.ft. )
2 BHK42.46 Sq.mts. ( 457 Sq.ft. )
SHOP14.63 Sq.mts. ( 157 Sq.ft. )
SHOP17.56 Sq.mts. ( 189 Sq.ft. )
SHOP24.22 Sq.mts. ( 261 Sq.ft. )
1 BHK32.91 Sq.mts. ( 354 Sq.ft. )
2 BHK42.59 Sq.mts. ( 458 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Spring Fieldlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Completed
Community Buildings
Completed
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Na
Energy management
Yet To Be Done
Fire Protection And Fire Safety Requirements
Yet To Be Done
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting
Internal P.C.C. Work
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Spring Field
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Spring Field by M/S. Shyam Sagar Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

74035 Sq. ft.

Project Area

9010 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

144 apartments in total
Total
144
Booked
48
Available
96

Saleable Area Statistics (Sq. ft.)

55480 Total
Total
55480
Booked
17353
Available
38127
Total 144 apartments in project. 48 apartments booked. 33% apartments booked.
Total 55480 Sq.ft. saleable area. 17353 saleable area booked.
31% area booked.

Bldg No 1

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 1Dec 20234000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.17 Sq.mts. ( 336 Sq.ft. )2
1 Booked50% Booked
50% Booked
2 BHK42.46 Sq.mts. ( 457 Sq.ft. )26
SHOP14.63 Sq.mts. ( 157 Sq.ft. )4
2 Booked50% Booked
50% Booked
SHOP17.56 Sq.mts. ( 189 Sq.ft. )4
2 Booked50% Booked
50% Booked
SHOP24.22 Sq.mts. ( 261 Sq.ft. )4
2 Booked50% Booked
50% Booked
40 total apartments / 8 apartments booked. 20% apartments booked.
Work Description in Building Bldg No 1Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Bldg No 2

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 2Dec 20234000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.17 Sq.mts. ( 336 Sq.ft. )2
None Booked0% Booked
0% Booked
2 BHK42.46 Sq.mts. ( 457 Sq.ft. )26
SHOP14.63 Sq.mts. ( 157 Sq.ft. )4
1 Booked25% Booked
25% Booked
SHOP17.56 Sq.mts. ( 189 Sq.ft. )4
1 Booked25% Booked
25% Booked
SHOP24.22 Sq.mts. ( 261 Sq.ft. )4
None Booked0% Booked
0% Booked
40 total apartments / 6 apartments booked. 15% apartments booked.
Work Description in Building Bldg No 2Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Bldg No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 5Dec 20234000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.17 Sq.mts. ( 336 Sq.ft. )2
1 Booked50% Booked
50% Booked
1 BHK32.91 Sq.mts. ( 354 Sq.ft. )16
7 Booked43% Booked
43% Booked
2 BHK42.59 Sq.mts. ( 458 Sq.ft. )14
4 Booked28% Booked
28% Booked
32 total apartments / 12 apartments booked. 37% apartments booked.
Work Description in Building Bldg No 5Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Bldg No 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 6Dec 20234000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK31.17 Sq.mts. ( 336 Sq.ft. )2
None Booked0% Booked
0% Booked
1 BHK32.91 Sq.mts. ( 354 Sq.ft. )16
15 Booked93% Booked
93% Booked
2 BHK42.59 Sq.mts. ( 458 Sq.ft. )14
7 Booked50% Booked
50% Booked
32 total apartments / 22 apartments booked. 68% apartments booked.
Work Description in Building Bldg No 6Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
M/S. Shyam Sagar Developers
for Project
Spring Field
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation