Project overview

Sparsh Phase-Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000016230. Sparsh Phase-Ii is located at 42, 118, 124/1 And 124/2. This is a New being developed by Shree Enterprises.

Sparsh Phase-Ii has 1 BHK Type 1, 1 BHK Type 2, 1 BHK Type 3, 1 BHK Type 4 & 1 RK Apartments with carpet areas ranging from 194 to 329 Sq.ft. Carpet. The Project has total 158 of which 18 are currently available for sale.

Sparsh Phase-Ii is being developed on a total land area of 14227 Sq.ft. Sparsh Phase-Ii has 5 Wings / Towers Building No 4,Building No 5 Wing A,Building No 5 Wing B,Building No 6 Wing A,Building No 6 Wing B

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sparsh Phase-Ii
  • Location:
  • 42, 118, 124/1 And 124/2
  • Const. Stage:
    New
  • Possession:
    30 Mar 2022
Developer Details

  • Developer:
    Shree Enterprises
  • Phone:
  • Address:
  • Balaji Bhavan
Project RERA Details
MAHA REARA No: P52000016230
Project Type Residential / Group Housing
RERA Project Status New
Architect An Arch Architect & Planner
Funding Bank ICICI BANK LIMITED
Proposed Possession 30 Mar 2022
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 04 Mar 2025
Last Retrived 28 Jul 2025
Sparsh Phase-Ii QR Code
Sparsh Phase-Ii
MahaRERA - P52000016230
Apartment Details & Configuration
TypeArea
2 BHK Type 145.14 Sq.mts. ( 486 Sq.ft. )
2 BHK Type 245.2 Sq.mts. ( 487 Sq.ft. )
2 BHK Type 345.27 Sq.mts. ( 487 Sq.ft. )
2 BHK Type 445.93 Sq.mts. ( 494 Sq.ft. )
1 BHK Type 130.5 Sq.mts. ( 328 Sq.ft. )
1 BHK Type 230.6 Sq.mts. ( 329 Sq.ft. )
1 BHK Type 128.75 Sq.mts. ( 309 Sq.ft. )
1 BHK Type 229.41 Sq.mts. ( 317 Sq.ft. )
1RK Type 120.55 Sq.mts. ( 221 Sq.ft. )
1RK Type 220.96 Sq.mts. ( 226 Sq.ft. )
1 BHK Type 230.52 Sq.mts. ( 329 Sq.ft. )
1 BHK Type 330.57 Sq.mts. ( 329 Sq.ft. )
1 RK18.02 Sq.mts. ( 194 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sparsh Phase-Iilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Children Play Area
Before Possession
Club House with Gymnasium
Before Possession
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Before Possession
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Before Possession
Open Parking
Na
Party Lawn with performing stage
Before Possession
Sewerage (Chamber, Lines, Septic Tank , STP)23% completed
23% Complete
Before Possession
Solid Waste Management And Disposal
Na
Storm Water Drains
Before Possession
Street Lighting
Before Possession
Treatment And Disposal Of Sewage And Sullage Water
Na
Walking Trail
Before Possession
Water Conservation, Rain water Harvesting
Before Possession
Water Supply
Before Possession
Buildings / Wings in Sparsh Phase-Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sparsh Phase-Ii by Shree Enterpriseslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

14227 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

158 apartments in total
Total
158
Booked
140
Available
18

Saleable Area Statistics (Sq. ft.)

57457 Total
Total
57457
Booked
50447
Available
7010
Total 158 apartments in project. 140 apartments booked. 88% apartments booked.
Total 57457 Sq.ft. saleable area. 50447 saleable area booked.
88% area booked.

Building No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4Mar 20217101007
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK Type 145.14 Sq.mts. ( 486 Sq.ft. )24
18 Booked75% Booked
75% Booked
2 BHK Type 245.2 Sq.mts. ( 487 Sq.ft. )3
2 Booked66% Booked
66% Booked
2 BHK Type 345.27 Sq.mts. ( 487 Sq.ft. )15
14 Booked93% Booked
93% Booked
2 BHK Type 445.93 Sq.mts. ( 494 Sq.ft. )4
4 Booked100% Booked
100% Booked
46 total apartments / 38 apartments booked. 82% apartments booked.
Work Description in Building Building No 4Completion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Building No 5 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 5 Wing AMar 202171010020
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK Type 130.5 Sq.mts. ( 328 Sq.ft. )12
12 Booked100% Booked
100% Booked
1 BHK Type 230.6 Sq.mts. ( 329 Sq.ft. )16
15 Booked93% Booked
93% Booked
28 total apartments / 27 apartments booked. 96% apartments booked.
Work Description in Building Building No 5 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress75% done
75% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor

Building No 5 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 5 Wing BMar 202171010021
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK Type 128.75 Sq.mts. ( 309 Sq.ft. )3
2 Booked66% Booked
66% Booked
1 BHK Type 229.41 Sq.mts. ( 317 Sq.ft. )4
3 Booked75% Booked
75% Booked
1 BHK Type 330.5 Sq.mts. ( 328 Sq.ft. )6
6 Booked100% Booked
100% Booked
1 BHK Type 430.6 Sq.mts. ( 329 Sq.ft. )8
7 Booked87% Booked
87% Booked
1RK Type 120.55 Sq.mts. ( 221 Sq.ft. )3
3 Booked100% Booked
100% Booked
1RK Type 220.96 Sq.mts. ( 226 Sq.ft. )4
4 Booked100% Booked
100% Booked
28 total apartments / 25 apartments booked. 89% apartments booked.
Work Description in Building Building No 5 Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress75% done
75% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor

Building No 6 Wing A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 6 Wing AMar 202171010024
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK Type 130.5 Sq.mts. ( 328 Sq.ft. )12
9 Booked75% Booked
75% Booked
1 BHK Type 230.6 Sq.mts. ( 329 Sq.ft. )16
15 Booked93% Booked
93% Booked
28 total apartments / 24 apartments booked. 85% apartments booked.
Work Description in Building Building No 6 Wing ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor

Building No 6 Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 6 Wing BMar 202171010024
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK Type 130.5 Sq.mts. ( 328 Sq.ft. )6
5 Booked83% Booked
83% Booked
1 BHK Type 230.52 Sq.mts. ( 329 Sq.ft. )3
3 Booked100% Booked
100% Booked
1 BHK Type 330.57 Sq.mts. ( 329 Sq.ft. )4
4 Booked100% Booked
100% Booked
1 BHK Type 430.6 Sq.mts. ( 329 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 RK18.02 Sq.mts. ( 194 Sq.ft. )7
6 Booked85% Booked
85% Booked
28 total apartments / 26 apartments booked. 92% apartments booked.
Work Description in Building Building No 6 Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress95% done
95% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress20% done
20% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress95% done
95% Booked
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Shree Enterprises
for Project
Sparsh Phase-Ii
last updated on 28 Jul 2025 as per information obtained from MARA RERA.