Sound Delight is a MahaRERA Registered Project bearing MahaRERA Registration Number P51900002485. Sound Delight is located at Gut No 32. This is a Ongoing being developed by Soundlines Ecohomes.

Sound Delight has 1.5 Apartments with carpet areas ranging from 561 to 561 Sq.ft. Carpet. The Project has total 184 of which 87 are currently available for sale.

Sound Delight is being developed on a total land area of 171471 Sq.ft. out of which 39934 Sq.ft. i.e 23% is reserved for recreational purposes. Sound Delight has 13 Wings / Towers A Wing,B Wing,Bunglows,C Wing,D Wing,E Wing,F Wing,G Wing,H Wing,I Wing,J Wing,K Wing,L Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sound Delight
  • Location:
  • Gut No 32
  • Const. Stage:
    Ongoing
  • Possession:
    30 Sep 2020
Developer Details

  • Developer:
    Soundlines Ecohomes
  • Phone:
  • Address:
  • Kamal Mansion
Project RERA Details
MAHA REARA No: P51900002485
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Apices Studio Pvt Ltd
Funding Bank HDFC BANK
Proposed Possession 30 Sep 2020
Revised Possession 30 Sep 2020
Extended Possession 30 Sep 2026
Litigations No Litigations
Last Modified 30 Nov 2021
Last Retrived 28 Jul 2025
Sound Delight QR Code
Sound Delight
MahaRERA - P51900002485
Apartment Details & Configuration
TypeArea
2.5 BHK68.15 Sq.mts. ( 734 Sq.ft. )
2.5 BHK68.47 Sq.mts. ( 737 Sq.ft. )
2.5 BHK73.6 Sq.mts. ( 792 Sq.ft. )
2.5 BHK73.92 Sq.mts. ( 796 Sq.ft. )
1.551.57 Sq.mts. ( 555 Sq.ft. )
Bungalow152.68 Sq.mts. ( 1643 Sq.ft. )
2.571.19 Sq.mts. ( 766 Sq.ft. )
2.568.39 Sq.mts. ( 736 Sq.ft. )
2.573.83 Sq.mts. ( 795 Sq.ft. )
1 BHK42.79 Sq.mts. ( 461 Sq.ft. )
1 BHK43.88 Sq.mts. ( 472 Sq.ft. )
2.573.95 Sq.mts. ( 796 Sq.ft. )
duplex124.51 Sq.mts. ( 1340 Sq.ft. )
1 BHK44.58 Sq.mts. ( 480 Sq.ft. )
1 BHK44.74 Sq.mts. ( 482 Sq.ft. )
2.563.15 Sq.mts. ( 680 Sq.ft. )
2.568.48 Sq.mts. ( 737 Sq.ft. )
2.571.85 Sq.mts. ( 773 Sq.ft. )
2.5 BHK68.57 Sq.mts. ( 738 Sq.ft. )
2.5 BHK72.5 Sq.mts. ( 780 Sq.ft. )
1.552.09 Sq.mts. ( 561 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sound Delightlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station70% completed
70% Complete
In Progress Offer Taken From Msedcl For Load Sanct
Energy management70% completed
70% Complete
Solar Water Heating &Amp; Power Is Consider
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
In Progress
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Internal Completed External Drainage Started
Solid Waste Management And Disposal
Na
Storm Water Drains
Internal Rwp Completed External In Wip
Street Lighting
Will Be Done After Road Work
Treatment And Disposal Of Sewage And Sullage Water
Water Will Used For Flashing
Water Conservation, Rain water Harvesting
Na
Water Supply
Internal Completed External Started
Buildings / Wings in Sound Delight
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sound Delight by Soundlines Ecohomeslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

171471 Sq. ft.

Project Area

39934 Sq. ft.

Recreational Open Space

Total 13

Wings / Towers in Project

Apartments Statistics

184 apartments in total
Total
184
Booked
97
Available
87

Saleable Area Statistics (Sq. ft.)

127520 Total
Total
127520
Booked
57482
Available
70039
Total 184 apartments in project. 97 apartments booked. 52% apartments booked.
Total 127520 Sq.ft. saleable area. 57482 saleable area booked.
45% area booked.

A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
A WingSep 20264104004
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.5 BHK68.15 Sq.mts. ( 734 Sq.ft. )2
2 Booked100% Booked
100% Booked
2.5 BHK68.47 Sq.mts. ( 737 Sq.ft. )6
4 Booked66% Booked
66% Booked
2.5 BHK73.6 Sq.mts. ( 792 Sq.ft. )2
1 Booked50% Booked
50% Booked
2.5 BHK73.92 Sq.mts. ( 796 Sq.ft. )6
4 Booked66% Booked
66% Booked
16 total apartments / 11 apartments booked. 68% apartments booked.
Work Description in Building A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
B WingSep 20264003003
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.551.57 Sq.mts. ( 555 Sq.ft. )4
3 Booked75% Booked
75% Booked
2.568.47 Sq.mts. ( 737 Sq.ft. )6
4 Booked66% Booked
66% Booked
2.573.92 Sq.mts. ( 796 Sq.ft. )6
3 Booked50% Booked
50% Booked
16 total apartments / 10 apartments booked. 62% apartments booked.
Work Description in Building B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

Bunglows

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
BunglowsSep 20260000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow152.68 Sq.mts. ( 1643 Sq.ft. )4
None Booked0% Booked
0% Booked
4 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building BunglowsCompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

C Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
C WingSep 20264103003
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.551.57 Sq.mts. ( 555 Sq.ft. )4
2 Booked50% Booked
50% Booked
2.568.15 Sq.mts. ( 734 Sq.ft. )2
1 Booked50% Booked
50% Booked
2.568.47 Sq.mts. ( 737 Sq.ft. )8
2 Booked25% Booked
25% Booked
2.571.19 Sq.mts. ( 766 Sq.ft. )4
None Booked0% Booked
0% Booked
2.573.6 Sq.mts. ( 792 Sq.ft. )2
None Booked0% Booked
0% Booked
2.573.92 Sq.mts. ( 796 Sq.ft. )4
None Booked0% Booked
0% Booked
24 total apartments / 5 apartments booked. 20% apartments booked.
Work Description in Building C WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

D Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
D WingSep 20264100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.568.39 Sq.mts. ( 736 Sq.ft. )2
1 Booked50% Booked
50% Booked
2.568.47 Sq.mts. ( 737 Sq.ft. )10
3 Booked30% Booked
30% Booked
2.573.83 Sq.mts. ( 795 Sq.ft. )2
None Booked0% Booked
0% Booked
2.573.92 Sq.mts. ( 796 Sq.ft. )10
24 total apartments / 5 apartments booked. 20% apartments booked.
Work Description in Building D WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

E Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
E WingSep 20264108008
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK42.79 Sq.mts. ( 461 Sq.ft. )8
8 Booked100% Booked
100% Booked
1 BHK43.88 Sq.mts. ( 472 Sq.ft. )8
8 Booked100% Booked
100% Booked
16 total apartments / 16 apartments booked. 100% apartments booked.
Work Description in Building E WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

F Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
F WingSep 20260000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.568.47 Sq.mts. ( 737 Sq.ft. )2
None Booked0% Booked
0% Booked
2.573.95 Sq.mts. ( 796 Sq.ft. )2
1 Booked50% Booked
50% Booked
duplex124.51 Sq.mts. ( 1340 Sq.ft. )6
None Booked0% Booked
0% Booked
10 total apartments / 1 apartments booked. 10% apartments booked.
Work Description in Building F WingCompletion
Basement (if any)
work-in-progress30% done
30% Booked
Excavation
work-in-progress30% done
30% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
work-in-progress30% done
30% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

G Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
G WingSep 2026410100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK44.58 Sq.mts. ( 480 Sq.ft. )12
11 Booked91% Booked
91% Booked
1 BHK44.74 Sq.mts. ( 482 Sq.ft. )6
6 Booked100% Booked
100% Booked
18 total apartments / 17 apartments booked. 94% apartments booked.
Work Description in Building G WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

H Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
H WingSep 20264109009
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK44.58 Sq.mts. ( 480 Sq.ft. )12
7 Booked58% Booked
58% Booked
1 BHK44.74 Sq.mts. ( 482 Sq.ft. )6
5 Booked83% Booked
83% Booked
18 total apartments / 12 apartments booked. 66% apartments booked.
Work Description in Building H WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

I Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
I WingSep 20264108008
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.551.57 Sq.mts. ( 555 Sq.ft. )12
12 Booked100% Booked
100% Booked
2.563.15 Sq.mts. ( 680 Sq.ft. )2
None Booked0% Booked
0% Booked
14 total apartments / 12 apartments booked. 85% apartments booked.
Work Description in Building I WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress90% done
90% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked

J Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
J WingSep 20260106006
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.568.15 Sq.mts. ( 734 Sq.ft. )2
None Booked0% Booked
0% Booked
2.568.48 Sq.mts. ( 737 Sq.ft. )2
None Booked0% Booked
0% Booked
2.571.85 Sq.mts. ( 773 Sq.ft. )8
2 Booked25% Booked
25% Booked
2.573.92 Sq.mts. ( 796 Sq.ft. )4
2 Booked50% Booked
50% Booked
16 total apartments / 4 apartments booked. 25% apartments booked.
Work Description in Building J WingCompletion
Basement (if any)
work-in-progress30% done
30% Booked
Excavation
work-in-progress30% done
30% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
work-in-progress30% done
30% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

K Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
K WingSep 20264106006
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.5 BHK68.57 Sq.mts. ( 738 Sq.ft. )2
2 Booked100% Booked
100% Booked
2.5 BHK72.5 Sq.mts. ( 780 Sq.ft. )2
2 Booked100% Booked
100% Booked
4 total apartments / 4 apartments booked. 100% apartments booked.
Work Description in Building K WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress70% done
70% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress70% done
70% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
work-in-progress70% done
70% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
Completed 100% done
100% Booked

L Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
L WingSep 20260000000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1.552.09 Sq.mts. ( 561 Sq.ft. )4
None Booked0% Booked
0% Booked
4 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building L WingCompletion
Basement (if any)
work-in-progress30% done
30% Booked
Excavation
work-in-progress30% done
30% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
work-in-progress30% done
30% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Soundlines Ecohomes
for Project
Sound Delight
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation