Som Enclave is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000047791. Som Enclave is located at S No 127 H No 1B. This is a New being developed by Som Developers.

Som Enclave has 1 BHK & 2 BHK Apartments with carpet areas ranging from 304 to 369 Sq.ft. Carpet. The Project has total 44 of which 40 are currently available for sale.

Som Enclave is being developed on a total land area of 8309 Sq.ft. out of which 12206 Sq.ft. i.e 147% is reserved for recreational purposes. Som Enclave has 2 Wings / Towers Som Enclave Wing B,Som Enclave Wing C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Som Enclave
  • Location:
  • S No 127 H No 1B
  • Const. Stage:
    New
  • Possession:
    31 Dec 2028
Developer Details

  • Developer:
    Som Developers
  • Phone:
  • Address:
  • Sai Heritage Chs Ltd.
Project RERA Details
MAHA REARA No: P99000047791
Project Type Residential / Group Housing
RERA Project Status New
Architect Ashok K Rengde
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 28 Nov 2022
Last Retrived 28 Jul 2025
Som Enclave QR Code
Som Enclave
MahaRERA - P99000047791
Apartment Details & Configuration
TypeArea
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )
1 BHK25.74 Sq.mts. ( 277 Sq.ft. )
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )
1 BHK28.23 Sq.mts. ( 304 Sq.ft. )
2 BHK34.31 Sq.mts. ( 369 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Som Enclavelast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
As Per Dwg.
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
As Per Dwg.
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
As Per Dwg.
Open Parking
As Per Dwg.
Sewerage (Chamber, Lines, Septic Tank , STP)50% completed
50% Complete
As Per Dwg.
Solid Waste Management And Disposal
Na
Storm Water Drains
As Per Dwg.
Street Lighting
As Per Dwg.
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
As Per Dwg.
Water Supply
As Per Dwg.
Buildings / Wings in Som Enclave
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Som Enclave by Som Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

8309 Sq. ft.

Project Area

12206 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

44 apartments in total
Total
44
Booked
4
Available
40

Saleable Area Statistics (Sq. ft.)

13381 Total
Total
13381
Booked
1190
Available
12190
Total 44 apartments in project. 4 apartments booked. 9% apartments booked.
Total 13381 Sq.ft. saleable area. 1190 saleable area booked.
9% area booked.

Som Enclave Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Som Enclave Wing BDec 202851010281
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK25.57 Sq.mts. ( 275 Sq.ft. )3
None Booked0% Booked
0% Booked
1 BHK25.74 Sq.mts. ( 277 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK27.58 Sq.mts. ( 297 Sq.ft. )15
3 Booked20% Booked
20% Booked
1 BHK27.84 Sq.mts. ( 300 Sq.ft. )8
27 total apartments / 4 apartments booked. 14% apartments booked.
Work Description in Building Som Enclave Wing BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress50% done
50% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress30% done
30% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress80% done
80% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress69% done
69% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress50% done
50% Booked
Sanitary Fittings within the flats / premises
work-in-progress50% done
50% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress50% done
50% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Som Enclave Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Som Enclave Wing CDec 202851010171
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.23 Sq.mts. ( 304 Sq.ft. )13
None Booked0% Booked
0% Booked
2 BHK34.31 Sq.mts. ( 369 Sq.ft. )4
None Booked0% Booked
0% Booked
17 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Som Enclave Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress30% done
30% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress80% done
80% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress80% done
80% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress59% done
59% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress80% done
80% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress80% done
80% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress30% done
30% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Som Developers
for Project
Som Enclave
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation