Project overview

Solitaire Highway is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000012069. Solitaire Highway is located at 37 B 1. This is a Ongoing being developed by Aakar Realtors.

Solitaire Highway has GALA Apartments with carpet areas ranging from 1079 to 1037 Sq.ft. Carpet. The Project has total 29 of which 0 are currently available for sale.

Solitaire Highway is being developed on a total land area of 59630 Sq.ft. Solitaire Highway has 2 Wings / Towers Opal,Sapphire

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Solitaire Highway
  • Location:
  • 37 B 1
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2018
Developer Details

  • Developer:
    Aakar Realtors
  • Phone:
  • Address:
  • Shubham
Project RERA Details
MAHA REARA No: P99000012069
Project Type Industrial
RERA Project Status Ongoing
Architect Encon
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 31 Dec 2018
Revised Possession 31 Dec 2018
Extended Possession
Litigations No Litigations
Last Modified 01 Sep 2017
Last Retrived 28 Jul 2025
Solitaire Highway QR Code
Solitaire Highway
MahaRERA - P99000012069
Apartment Details & Configuration
TypeArea
GALA53.43 Sq.mts. ( 575 Sq.ft. )
GALA75.94 Sq.mts. ( 817 Sq.ft. )
GALA121.02 Sq.mts. ( 1303 Sq.ft. )
GALA132.69 Sq.mts. ( 1428 Sq.ft. )
GALA176.23 Sq.mts. ( 1897 Sq.ft. )
GALA207.54 Sq.mts. ( 2234 Sq.ft. )
GALA234.46 Sq.mts. ( 2524 Sq.ft. )
GALA239.13 Sq.mts. ( 2574 Sq.ft. )
GALA279.68 Sq.mts. ( 3010 Sq.ft. )
GALA66.32 Sq.mts. ( 714 Sq.ft. )
GALA84.85 Sq.mts. ( 913 Sq.ft. )
GALA96.38 Sq.mts. ( 1037 Sq.ft. )
GALA100.2 Sq.mts. ( 1079 Sq.ft. )
GALA112.22 Sq.mts. ( 1208 Sq.ft. )
GALA124.62 Sq.mts. ( 1341 Sq.ft. )
GALA165.71 Sq.mts. ( 1784 Sq.ft. )
GALA181.52 Sq.mts. ( 1954 Sq.ft. )
GALA190.93 Sq.mts. ( 2055 Sq.ft. )
GALA196.31 Sq.mts. ( 2113 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Solitaire Highwaylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Done
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Done
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Completed
Solid Waste Management And Disposal100% completed
95% Complete
Completed
Storm Water Drains100% completed
95% Complete
Completed
Street Lighting100% completed
95% Complete
Completed
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Completed
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Completed
Buildings / Wings in Solitaire Highway
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Solitaire Highway by Aakar Realtorslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

59630 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 2

Wings / Towers in Project

Apartments Statistics

29 apartments in total
Total
29
Booked
29
Available
0

Saleable Area Statistics (Sq. ft.)

41557 Total
Total
41557
Booked
41557
Available
0
Total 29 apartments in project. 29 apartments booked. 100% apartments booked.
Total 41557 Sq.ft. saleable area. 41557 saleable area booked.
100% area booked.

Opal

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
OpalDec 20183100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
GALA53.43 Sq.mts. ( 575 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA75.94 Sq.mts. ( 817 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA121.02 Sq.mts. ( 1303 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA132.69 Sq.mts. ( 1428 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA176.23 Sq.mts. ( 1897 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA207.54 Sq.mts. ( 2234 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA234.46 Sq.mts. ( 2524 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA239.13 Sq.mts. ( 2574 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA279.68 Sq.mts. ( 3010 Sq.ft. )1
1 Booked100% Booked
100% Booked
9 total apartments / 9 apartments booked. 100% apartments booked.
Work Description in Building OpalCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Sapphire

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
SapphireDec 20183100000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
GALA66.32 Sq.mts. ( 714 Sq.ft. )2
2 Booked100% Booked
100% Booked
GALA84.85 Sq.mts. ( 913 Sq.ft. )3
3 Booked100% Booked
100% Booked
GALA96.38 Sq.mts. ( 1037 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA100.2 Sq.mts. ( 1079 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA112.22 Sq.mts. ( 1208 Sq.ft. )8
8 Booked100% Booked
100% Booked
GALA124.62 Sq.mts. ( 1341 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA165.71 Sq.mts. ( 1784 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA181.52 Sq.mts. ( 1954 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA190.93 Sq.mts. ( 2055 Sq.ft. )1
1 Booked100% Booked
100% Booked
GALA196.31 Sq.mts. ( 2113 Sq.ft. )1
1 Booked100% Booked
100% Booked
20 total apartments / 20 apartments booked. 100% apartments booked.
Work Description in Building SapphireCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress80% done
80% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Aakar Realtors
for Project
Solitaire Highway