Project overview

Solitaire Castle is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000009688. Solitaire Castle is located at 54 B/1. This is a Ongoing being developed by Pam Infrastructure.

Solitaire Castle has Resi cum comm Apartments with carpet areas ranging from 0 to 0 Sq.ft. Carpet. The Project has total 519 of which 344 are currently available for sale.

Solitaire Castle is being developed on a total land area of 288475 Sq.ft. out of which 29658 Sq.ft. i.e 10% is reserved for recreational purposes. Solitaire Castle has 6 Wings / Towers Building No 1 Coral,Building No 2 Pearl,Building No 3 Emerald,Building No 4,Building No 5,Building No 6

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Solitaire Castle
  • Location:
  • 54 B/1
  • Const. Stage:
    Ongoing
  • Possession:
    30 Nov 2018
Developer Details

  • Developer:
    Pam Infrastructure
  • Phone:
  • Address:
  • Kashinjali Commercial Complex
Project RERA Details
MAHA REARA No: P99000009688
Project Type Others
RERA Project Status Ongoing
Architect Sanjay
Funding Bank BASSEIN CATHOLIC COOPERATIVE BANK LIMITED
Proposed Possession 30 Nov 2018
Revised Possession 30 Dec 2026
Extended Possession
Litigations No Litigations
Last Modified 22 Aug 2017
Last Retrived 28 Jul 2025
Solitaire Castle QR Code
Solitaire Castle
MahaRERA - P99000009688
Apartment Details & Configuration
TypeArea
1 BHK40 Sq.mts. ( 431 Sq.ft. )
2 BHK62.28 Sq.mts. ( 670 Sq.ft. )
2 BHK66.52 Sq.mts. ( 716 Sq.ft. )
2 BHK67 Sq.mts. ( 721 Sq.ft. )
2 BHK70.41 Sq.mts. ( 758 Sq.ft. )
2 BHK72.26 Sq.mts. ( 778 Sq.ft. )
3 BHK84.24 Sq.mts. ( 907 Sq.ft. )
3 BHK108.46 Sq.mts. ( 1167 Sq.ft. )
4 BHK143.12 Sq.mts. ( 1541 Sq.ft. )
DUPELEX FLATS85 Sq.mts. ( 915 Sq.ft. )
Shop11 Sq.mts. ( 118 Sq.ft. )
SHOWROOM91 Sq.mts. ( 980 Sq.ft. )
Resi Cum Comm4591.14 Sq.mts. ( 49419 Sq.ft. )
Resi Cum Comm6336.5 Sq.mts. ( 68206 Sq.ft. )
Resi cum Comm881.38 Sq.mts. ( 9487 Sq.ft. )
Commercial590.46 Sq.mts. ( 6356 Sq.ft. )
Resi cum comm0 Sq.mts. ( 0 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Solitaire Castlelast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space100% completed
95% Complete
Done
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Done
Energy management100% completed
95% Complete
Done
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Done
Landscaping & Tree Planting100% completed
95% Complete
Done
Open Parking100% completed
95% Complete
Done
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Done
Solid Waste Management And Disposal100% completed
95% Complete
Done
Storm Water Drains100% completed
95% Complete
Done
Street Lighting100% completed
95% Complete
Done
Treatment And Disposal Of Sewage And Sullage Water100% completed
95% Complete
Done
Water Conservation, Rain water Harvesting100% completed
95% Complete
Done
Water Supply100% completed
95% Complete
Done
Buildings / Wings in Solitaire Castle
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Solitaire Castle by Pam Infrastructurelast updated on 28 Jul 2025 as per information obtained from MARA RERA.

288475 Sq. ft.

Project Area

29658 Sq. ft.

Recreational Open Space

Total 6

Wings / Towers in Project

Apartments Statistics

519 apartments in total
Total
519
Booked
175
Available
344

Saleable Area Statistics (Sq. ft.)

11368502 Total
Total
11368502
Booked
10383737
Available
984764
Total 519 apartments in project. 175 apartments booked. 33% apartments booked.
Total 11368502 Sq.ft. saleable area. 10383737 saleable area booked.
91% area booked.

Building No 1 Coral

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 1 CoralJun 202621101630495
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK40 Sq.mts. ( 431 Sq.ft. )58
None Booked0% Booked
0% Booked
2 BHK62.28 Sq.mts. ( 670 Sq.ft. )16
None Booked0% Booked
0% Booked
2 BHK66.52 Sq.mts. ( 716 Sq.ft. )15
None Booked0% Booked
0% Booked
2 BHK67 Sq.mts. ( 721 Sq.ft. )47
None Booked0% Booked
0% Booked
2 BHK70.41 Sq.mts. ( 758 Sq.ft. )29
None Booked0% Booked
0% Booked
2 BHK72.26 Sq.mts. ( 778 Sq.ft. )50
None Booked0% Booked
0% Booked
3 BHK84.24 Sq.mts. ( 907 Sq.ft. )3
None Booked0% Booked
0% Booked
3 BHK108.46 Sq.mts. ( 1167 Sq.ft. )26
None Booked0% Booked
0% Booked
4 BHK143.12 Sq.mts. ( 1541 Sq.ft. )24
None Booked0% Booked
0% Booked
DUPELEX FLATS85 Sq.mts. ( 915 Sq.ft. )6
None Booked0% Booked
0% Booked
Shop11 Sq.mts. ( 118 Sq.ft. )31
None Booked0% Booked
0% Booked
SHOWROOM91 Sq.mts. ( 980 Sq.ft. )5
None Booked0% Booked
0% Booked
310 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 1 CoralCompletion
Basement (if any)
Excavation
work-in-progress20% done
20% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 2 Pearl

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 PearlJun 2026810112035
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Resi Cum Comm4591.14 Sq.mts. ( 49419 Sq.ft. )74
67 Booked90% Booked
90% Booked
74 total apartments / 67 apartments booked. 90% apartments booked.
Work Description in Building Building No 2 PearlCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 3 Emerald

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 3 EmeraldJun 2026810113740
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Resi Cum Comm6336.5 Sq.mts. ( 68206 Sq.ft. )106
103 Booked97% Booked
97% Booked
106 total apartments / 103 apartments booked. 97% apartments booked.
Work Description in Building Building No 3 EmeraldCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
Completed 100% done
100% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Completed 100% done
100% Booked
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
Completed 100% done
100% Booked
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 4

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 4Jan 19003101061
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Resi cum Comm881.38 Sq.mts. ( 9487 Sq.ft. )23
5 Booked21% Booked
21% Booked
23 total apartments / 5 apartments booked. 21% apartments booked.
Work Description in Building Building No 4Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 5

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 5Jan 19001111071
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Commercial590.46 Sq.mts. ( 6356 Sq.ft. )6
None Booked0% Booked
0% Booked
6 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Building No 5Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Building No 6

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 6Jan 19005101000
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Resi cum comm0 Sq.mts. ( 0 Sq.ft. )0
None Booked0% Booked
0% Booked
Work Description in Building Building No 6Completion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Pam Infrastructure
for Project
Solitaire Castle
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation