Project overview

Snehadeep Co-Operative Housing Society Ltd is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700013473. Snehadeep Co-Operative Housing Society Ltd is located at Survey No.8, Tikka No.2 Part Corresponding Totikka No.16, Cts No. 60. This is a Ongoing being developed by Joshi Enterprises.

Snehadeep Co-Operative Housing Society Ltd has 2.5 BHK, 65.05 & Godown Apartments with carpet areas ranging from 1174 to 700 Sq.ft. Carpet. The Project has total 31 of which 4 are currently available for sale.

Snehadeep Co-Operative Housing Society Ltd is being developed on a total land area of 9000 Sq.ft. Snehadeep Co-Operative Housing Society Ltd has 1 Wings / Towers Snehadeep Co-Operative Society Ltd

ProjectDeveloperLocationPossession
Sai ApartmentsGajanan Kotkar & Nandini Kotkar5931-12-2018 00:00:00
New Kirtikar ProposedChaturthi Developers40060201-07-2025 00:00:00
Shanti KunjShreyas Enterprises616,617,61831-12-2017 00:00:00
Project Details
  • Project:
    Snehadeep Co-Operative Housing Society Ltd
  • Location:
  • Survey No.8, Tikka No.2 Part Corresponding Totikka No.16, Cts No. 60
  • Const. Stage:
    Ongoing
  • Possession:
    31 Dec 2017
Developer Details

  • Developer:
    Joshi Enterprises
  • Phone:
  • Address:
  • New Era Tropical Building
Project RERA Details
MAHA REARA No: P51700013473
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect M/S Archetype Consultants (I) Pvt. Ltd.
Funding Bank TJSB SAHAKARI BANK LTD
Proposed Possession 31 Dec 2017
Revised Possession 31 Dec 2017
Extended Possession 31 Jul 2018
Litigations No Litigations
Last Modified 26 Feb 2018
Last Retrived 26 Jul 2025
Snehadeep Co-Operative Housing Society Ltd QR Code
Snehadeep Co-Operative Housing Society Ltd
MahaRERA - P51700013473
Apartment Details & Configuration
TypeArea
2.5 BHK60.24 Sq.mts. ( 648 Sq.ft. )
2.5 BHK60.44 Sq.mts. ( 651 Sq.ft. )
2.5 BHK60.68 Sq.mts. ( 653 Sq.ft. )
2.5 BHK60.85 Sq.mts. ( 655 Sq.ft. )
2.5 BHK62.56 Sq.mts. ( 673 Sq.ft. )
2.5 BHK62.59 Sq.mts. ( 674 Sq.ft. )
2.5 BHK62.6 Sq.mts. ( 674 Sq.ft. )
2.5 BHK62.61 Sq.mts. ( 674 Sq.ft. )
2.5 BHK62.7 Sq.mts. ( 675 Sq.ft. )
2.5 BHK63.01 Sq.mts. ( 678 Sq.ft. )
2.5 BHK63.11 Sq.mts. ( 679 Sq.ft. )
2.5 BHK35.33 Sq.mts. ( 380 Sq.ft. )
65.0565.05 Sq.mts. ( 700 Sq.ft. )
Godown109.09 Sq.mts. ( 1174 Sq.ft. )
Godown46.82 Sq.mts. ( 504 Sq.ft. )
Godown58.7 Sq.mts. ( 632 Sq.ft. )
Godown29.42 Sq.mts. ( 317 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Snehadeep Co-Operative Housing Society Ltdlast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station100% completed
95% Complete
Completed
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Completed
Landscaping & Tree Planting100% completed
95% Complete
Completed
Open Parking100% completed
95% Complete
Provided
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Provided
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
Provided
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
Completed
Water Supply100% completed
95% Complete
Provided
Buildings / Wings in Snehadeep Co-Operative Housing Society Ltd
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Snehadeep Co-Operative Housing Society Ltd by Joshi Enterpriseslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

9000 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 1

Wings / Towers in Project

Apartments Statistics

31 apartments in total
Total
31
Booked
27
Available
4

Saleable Area Statistics (Sq. ft.)

20531 Total
Total
20531
Booked
18128
Available
2403
Total 31 apartments in project. 27 apartments booked. 87% apartments booked.
Total 20531 Sq.ft. saleable area. 18128 saleable area booked.
88% area booked.

Snehadeep Co-Operative Society Ltd

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Snehadeep Co-Operative Society LtdJul 201881010126
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2.5 BHK60.24 Sq.mts. ( 648 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK60.44 Sq.mts. ( 651 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK60.68 Sq.mts. ( 653 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK60.85 Sq.mts. ( 655 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK62.56 Sq.mts. ( 673 Sq.ft. )5
4 Booked80% Booked
80% Booked
2.5 BHK62.59 Sq.mts. ( 674 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK62.6 Sq.mts. ( 674 Sq.ft. )1
1 Booked100% Booked
100% Booked
2.5 BHK62.61 Sq.mts. ( 674 Sq.ft. )1
None Booked0% Booked
0% Booked
2.5 BHK62.7 Sq.mts. ( 675 Sq.ft. )5
4 Booked80% Booked
80% Booked
2.5 BHK63.01 Sq.mts. ( 678 Sq.ft. )2
2 Booked100% Booked
100% Booked
2.5 BHK63.11 Sq.mts. ( 679 Sq.ft. )5
5 Booked100% Booked
100% Booked
2.5 BHK35.33 Sq.mts. ( 380 Sq.ft. )1
None Booked0% Booked
0% Booked
65.0565.05 Sq.mts. ( 700 Sq.ft. )2
2 Booked100% Booked
100% Booked
Godown109.09 Sq.mts. ( 1174 Sq.ft. )1
1 Booked100% Booked
100% Booked
Godown46.82 Sq.mts. ( 504 Sq.ft. )1
1 Booked100% Booked
100% Booked
Godown58.7 Sq.mts. ( 632 Sq.ft. )1
1 Booked100% Booked
100% Booked
Godown29.42 Sq.mts. ( 317 Sq.ft. )1
1 Booked100% Booked
100% Booked
31 total apartments / 27 apartments booked. 87% apartments booked.
Work Description in Building Snehadeep Co-Operative Society LtdCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Joshi Enterprises
for Project
Snehadeep Co-Operative Housing Society Ltd
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation