Project overview

Sky City Phase I is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000045278. Sky City Phase I is located at S No 220 H No 6 And S No 224/B/1 And 224/B/2 And 224/B/3. This is a New being developed by Uniquepoonam Homes Llp.

Sky City Phase I has 1 BHK Apartments with carpet areas ranging from 281 to 363 Sq.ft. Carpet. The Project has total 692 of which 183 are currently available for sale.

Sky City Phase I is being developed on a total land area of 41909 Sq.ft. out of which 4769 Sq.ft. i.e 11% is reserved for recreational purposes. Sky City Phase I has 4 Wings / Towers Building No 2 Wing F,Building No 2 Wing G,Building No 2 Wing H,Building No 2 Wing I

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Sky City Phase I
  • Location:
  • S No 220 H No 6 And S No 224/B/1 And 224/B/2 And 224/B/3
  • Const. Stage:
    New
  • Possession:
    31 Dec 2028
Developer Details

  • Developer:
    Uniquepoonam Homes Llp
  • Phone:
  • Address:
  • Saheb Building
Project RERA Details
MAHA REARA No: P99000045278
Project Type Residential / Group Housing
RERA Project Status New
Architect Abhay Raut
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2028
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 08 Oct 2022
Last Retrived 28 Jul 2025
Sky City Phase I QR Code
Sky City Phase I
MahaRERA - P99000045278
Apartment Details & Configuration
TypeArea
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )
1 BHK26.15 Sq.mts. ( 281 Sq.ft. )
1 BHK33.75 Sq.mts. ( 363 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sky City Phase Ilast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Will Be Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
As Per Fire Noc Given By Vvcmc
Landscaping & Tree Planting
As Per Tree Noc Given By Vvcmc
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Will Be Provided
Street Lighting
Will Be Provided
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Will Be Provided
Water Supply
Will Start Once Vvcmc Water Supply Commence
Buildings / Wings in Sky City Phase I
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sky City Phase I by Uniquepoonam Homes Llplast updated on 28 Jul 2025 as per information obtained from MARA RERA.

41909 Sq. ft.

Project Area

4769 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

692 apartments in total
Total
692
Booked
509
Available
183

Saleable Area Statistics (Sq. ft.)

204092 Total
Total
204092
Booked
151907
Available
52185
Total 692 apartments in project. 509 apartments booked. 73% apartments booked.
Total 204092 Sq.ft. saleable area. 151907 saleable area booked.
74% area booked.

Building No 2 Wing F

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 Wing FDec 20282210100198
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )173
119 Booked68% Booked
68% Booked
173 total apartments / 119 apartments booked. 68% apartments booked.
Work Description in Building Building No 2 Wing FCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress20% done
20% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress98% done
98% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
work-in-progress98% done
98% Booked

Building No 2 Wing G

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 Wing GDec 20282210100198
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )173
101 Booked58% Booked
58% Booked
173 total apartments / 101 apartments booked. 58% apartments booked.
Work Description in Building Building No 2 Wing GCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress23% done
23% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress47% done
47% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress47% done
47% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress53% done
53% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress70% done
70% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress23% done
23% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2 Wing H

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 Wing HDec 20282210100198
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )173
136 Booked78% Booked
78% Booked
173 total apartments / 136 apartments booked. 78% apartments booked.
Work Description in Building Building No 2 Wing HCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress23% done
23% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress47% done
47% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress47% done
47% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress53% done
53% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress70% done
70% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress23% done
23% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Building No 2 Wing I

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Building No 2 Wing IDec 2028221010067
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.15 Sq.mts. ( 281 Sq.ft. )44
40 Booked90% Booked
90% Booked
1 BHK26.5 Sq.mts. ( 285 Sq.ft. )41
25 Booked60% Booked
60% Booked
1 BHK33.75 Sq.mts. ( 363 Sq.ft. )88
88 Booked100% Booked
100% Booked
173 total apartments / 153 apartments booked. 88% apartments booked.
Work Description in Building Building No 2 Wing ICompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress23% done
23% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress47% done
47% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress47% done
47% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress53% done
53% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
work-in-progress70% done
70% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
work-in-progress70% done
70% Booked
Stilt Floor
work-in-progress90% done
90% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress23% done
23% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Uniquepoonam Homes Llp
for Project
Sky City Phase I
last updated on 28 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation