Project overview

Sky City is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700024337. Sky City is located at 121/2, 121/3, 162/1. This is a New being developed by Sunrise Realtors.

Sky City has 1RK, 2 BHK & 3 BHK Apartments with carpet areas ranging from 1181 to 1034 Sq.ft. Carpet. The Project has total 197 of which 102 are currently available for sale.

Sky City is being developed on a total land area of 84435 Sq.ft. out of which 12665 Sq.ft. i.e 15% is reserved for recreational purposes. Sky City has 5 Wings / Towers Dream Villa - A,Dream Villa - B,Dream Villa - C,Galaxy - D,Magnum - E

ProjectDeveloperLocationPossession
Ramkrushna ResidencyRamkrishna DevelopersThane31-12-2019 00:00:00
M/S Simco JyotiSuresh Mithalal Jain164/630-09-2019 00:00:00
Avd AvadhAvd Infra India Private LimitedThane, 421302, Kamatghar30-09-2020 00:00:00
Vardhaman Bhoomi ResidencyGandhi & Samani AssociatesS.No 16 Hissa No 3Paiki,4A Paiki 6Paiki30-12-2023 00:00:00
Varad HeightsSharad Raghunath Mhatre49/4830-12-2022 00:00:00
Silver Park Residency AsterSuyash Enterprises49/22 P,49/23 P,143/2 P01-12-2023 00:00:00
Munisuvrat Arc - Building 1 Plot 1 And Munisuvrat Royal - Building 2 On Plot 2Shree Munisuvrat Realty126/3P31-03-2019 00:00:00
NirmaldharaHazel Enterprise49/47/1, 49/40, 118/230-12-2021 00:00:00
Atlanta Residency Phase ISri Balaji Developer124/5/6/7/9/1031-03-2018 00:00:00
Project Details
  • Project:
    Sky City
  • Location:
  • 121/2, 121/3, 162/1
  • Const. Stage:
    New
  • Possession:
    30 Dec 2026
Developer Details

  • Developer:
    Sunrise Realtors
  • Phone:
  • Address:
  • Suncity,
Project RERA Details
MAHA REARA No: P51700024337
Project Type Residential / Group Housing
RERA Project Status New
Architect Wasiq Nisar Ahmed
Funding Bank BHARAT COOPERATIVE BANK MUMBAI LIMITED
Proposed Possession 30 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 27 Jun 2025
Last Retrived 26 Jul 2025
Sky City QR Code
Sky City
MahaRERA - P51700024337
Apartment Details & Configuration
TypeArea
Bungalow124.43 Sq.mts. ( 1339 Sq.ft. )
Bungalow180.2 Sq.mts. ( 1940 Sq.ft. )
Bungalow140.61 Sq.mts. ( 1514 Sq.ft. )
Bungalow148.59 Sq.mts. ( 1599 Sq.ft. )
Bungalow248.47 Sq.mts. ( 2675 Sq.ft. )
1RK30.15 Sq.mts. ( 325 Sq.ft. )
1RK32 Sq.mts. ( 344 Sq.ft. )
2 BHK62.82 Sq.mts. ( 676 Sq.ft. )
2 BHK72.91 Sq.mts. ( 785 Sq.ft. )
2 BHK75.92 Sq.mts. ( 817 Sq.ft. )
3 BHK96.09 Sq.mts. ( 1034 Sq.ft. )
1RK29.74 Sq.mts. ( 320 Sq.ft. )
1RK29.97 Sq.mts. ( 323 Sq.ft. )
2 BHK71.2 Sq.mts. ( 766 Sq.ft. )
3 BHK109.73 Sq.mts. ( 1181 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Sky Citylast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Solar Water Heater
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Open Space
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Na
Solid Waste Management And Disposal
Na
Storm Water Drains
Na
Street Lighting
Na
SWIMMING POOL
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Na
Water Supply
Borewell
Buildings / Wings in Sky City
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Sky City by Sunrise Realtorslast updated on 26 Jul 2025 as per information obtained from MARA RERA.

84435 Sq. ft.

Project Area

12665 Sq. ft.

Recreational Open Space

Total 5

Wings / Towers in Project

Apartments Statistics

197 apartments in total
Total
197
Booked
95
Available
102

Saleable Area Statistics (Sq. ft.)

151381 Total
Total
151381
Booked
69529
Available
81852
Total 197 apartments in project. 95 apartments booked. 48% apartments booked.
Total 151381 Sq.ft. saleable area. 69529 saleable area booked.
46% area booked.

Dream Villa - A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dream Villa - ADec 20253100010
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow124.43 Sq.mts. ( 1339 Sq.ft. )1
None Booked0% Booked
0% Booked
1 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Dream Villa - ACompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Dream Villa - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dream Villa - BDec 20253100060
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow180.2 Sq.mts. ( 1940 Sq.ft. )4
None Booked0% Booked
0% Booked
4 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Dream Villa - BCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Dream Villa - C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Dream Villa - CDec 20253100060
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
Bungalow140.61 Sq.mts. ( 1514 Sq.ft. )2
None Booked0% Booked
0% Booked
Bungalow148.59 Sq.mts. ( 1599 Sq.ft. )2
2 Booked100% Booked
100% Booked
Bungalow248.47 Sq.mts. ( 2675 Sq.ft. )1
1 Booked100% Booked
100% Booked
5 total apartments / 3 apartments booked. 60% apartments booked.
Work Description in Building Dream Villa - CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress75% done
75% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked

Galaxy - D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Galaxy - DDec 20251510104540
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK30.15 Sq.mts. ( 325 Sq.ft. )13
5 Booked38% Booked
38% Booked
1RK32 Sq.mts. ( 344 Sq.ft. )13
10 Booked76% Booked
76% Booked
2 BHK62.82 Sq.mts. ( 676 Sq.ft. )15
12 Booked80% Booked
80% Booked
2 BHK72.91 Sq.mts. ( 785 Sq.ft. )15
8 Booked53% Booked
53% Booked
2 BHK75.92 Sq.mts. ( 817 Sq.ft. )15
11 Booked73% Booked
73% Booked
3 BHK96.09 Sq.mts. ( 1034 Sq.ft. )15
3 Booked20% Booked
20% Booked
86 total apartments / 49 apartments booked. 56% apartments booked.
Work Description in Building Galaxy - DCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress45% done
45% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress40% done
40% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress90% done
90% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor

Magnum - E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Magnum - EDec 20251510104540
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1RK29.74 Sq.mts. ( 320 Sq.ft. )13
7 Booked53% Booked
53% Booked
1RK29.97 Sq.mts. ( 323 Sq.ft. )13
3 Booked23% Booked
23% Booked
2 BHK62.82 Sq.mts. ( 676 Sq.ft. )15
9 Booked60% Booked
60% Booked
2 BHK71.2 Sq.mts. ( 766 Sq.ft. )15
5 Booked33% Booked
33% Booked
2 BHK72.91 Sq.mts. ( 785 Sq.ft. )15
8 Booked53% Booked
53% Booked
3 BHK96.09 Sq.mts. ( 1034 Sq.ft. )15
3 BHK109.73 Sq.mts. ( 1181 Sq.ft. )15
9 Booked60% Booked
60% Booked
101 total apartments / 43 apartments booked. 42% apartments booked.
Work Description in Building Magnum - ECompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress40% done
40% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress45% done
45% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the flats / premises
Slabs of Super Structure
work-in-progress85% done
85% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Channel Partners
Channel Partners Registered by Developer
Sunrise Realtors
for Project
Sky City
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation