Project overview
Siddhagiri Residency is a MahaRERA Registered Project bearing MahaRERA Registration Number P52000014294. Siddhagiri Residency is located at 223, Sector-17. This is a New being developed by Ss Engineering.
Siddhagiri Residency has 1 BHK & 1RK Apartments with carpet areas ranging from 195 to 315 Sq.ft. Carpet. The Project has total 17 of which 12 are currently available for sale.
Siddhagiri Residency is being developed on a total land area of 3223 Sq.ft. Siddhagiri Residency has 1 Wings / Towers Siddhagiri Residency
| Project | Developer | Location | Possession |
-
Project:
Siddhagiri Residency
-
Location:
-
223, Sector-17
-
Const. Stage:
New
-
Possession:
01 Nov 2020
-
Developer:
Ss Engineering
-
Phone:
-
Address:
-
Today Housing
| MAHA REARA No: |
P52000014294 |
| Project Type |
Residential / Group Housing |
| RERA Project Status |
New |
| Architect |
Pioneer Architect |
| Funding Bank |
APNA SAHAKARI BANK LIMITED |
| Proposed Possession |
01 Nov 2020 |
| Revised Possession |
|
| Extended Possession |
|
| Litigations |
No Litigations |
| Last Modified |
17 Nov 2022 |
| Last Retrived |
28 Jul 2025 |
Siddhagiri Residency QR Code
Siddhagiri Residency
MahaRERA - P52000014294
| Type | Area |
| 1 BHK | 27.87 Sq.mts. ( 300 Sq.ft. ) |
| 1 BHK | 29.17 Sq.mts. ( 314 Sq.ft. ) |
| 1 BHK | 29.26 Sq.mts. ( 315 Sq.ft. ) |
| 1RK | 18.11 Sq.mts. ( 195 Sq.ft. ) |
Facilities & Amenities
Facilities, Amenities & Common areas details of Siddhagiri Residencylast updated on 28 Jul 2025 as per information obtained from MARA RERA.
| Project Facilities & Amenities |
Available |
Details |
Aggregate area of recreational Open Space
|
|
Na |
|
|
|
Na |
Electrical Meter Room, Sub-Station, Receiving Station100% completed
|
|
As Per Schedule |
|
|
|
Na |
Fire Protection And Fire Safety
Requirements
|
|
Na |
Landscaping & Tree Planting100% completed
|
|
As Per Schedule |
|
|
|
As Per Schedule |
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
|
|
As Per Schedule |
Solid Waste Management And Disposal
|
|
Na |
|
|
|
As Per Schedule |
Street Lighting100% completed
|
|
Completed |
Treatment And Disposal Of Sewage And Sullage Water
|
|
Na |
Water Conservation, Rain water Harvesting
|
|
Na |
|
|
|
As Per Schedule |
Buildings / Wings in Siddhagiri Residency
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Siddhagiri Residency by Ss Engineeringlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Apartments Statistics
17
apartments in total
Saleable Area Statistics (Sq. ft.)
5167
Total
Total 17 apartments in project. 5 apartments booked. 29% apartments booked.
Total 5167 Sq.ft. saleable area. 1558 saleable area booked.
30% area booked.
| Wing | Proposed Date of Completion | Number of Slabs | Plinth | Basement's | Stilts | Podium's | Open Parkings | Closed Parkings |
| Siddhagiri Residency | Jan 2020 | 5 | 1 | 0 | 0 | 0 | 0 | 0 |
| Apartment Type | Carpet Area | Number of Apartments | Booked Apartments |
| 1 BHK | 27.87 Sq.mts. ( 300 Sq.ft. ) | 4 | |
| 1 BHK | 29.17 Sq.mts. ( 314 Sq.ft. ) | 8 | |
| 1 BHK | 29.26 Sq.mts. ( 315 Sq.ft. ) | 4 | |
| 1RK | 18.11 Sq.mts. ( 195 Sq.ft. ) | 1 | |
17 total apartments / 5 apartments booked. 29% apartments booked. |
| Work Description in Building Siddhagiri Residency | Completion |
| Basement (if any) | |
| Excavation | |
| External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing. | |
| Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale. | |
| Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises | |
| Plinth | |
| Podiums (if any) | |
| Sanitary Fittings within the flats / premises | |
| Slabs of Super Structure | |
| Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks | |
| Stilt Floor | |
Channel Partners Registered by Developer
Ss Engineering
for Project
Siddhagiri Residency
last updated on
28 Jul 2025 as per information obtained from MARA RERA.
| Name |
Company |
Location |
Mobile |
Designation |