Project overview

Shubhada Co-Operative Housing Society Ltd. is a MahaRERA Registered Project bearing MahaRERA Registration Number P51800001693. Shubhada Co-Operative Housing Society Ltd. is located at 253 253 1 To 8. This is a Ongoing being developed by Bhoomivijay Properties Private Limited.

Shubhada Co-Operative Housing Society Ltd. has 3 BHK & 3 BHK Tenant Apartments with carpet areas ranging from 1230 to 1004 Sq.ft. Carpet. The Project has total 43 of which 12 are currently available for sale.

Shubhada Co-Operative Housing Society Ltd. is being developed on a total land area of 32024 Sq.ft. out of which 6296 Sq.ft. i.e 20% is reserved for recreational purposes. Shubhada Co-Operative Housing Society Ltd. has 3 Wings / Towers Shubhada Wing - A,Shubhada Wing - B,Shubhada Wing - C

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shubhada Co-Operative Housing Society Ltd.
  • Location:
  • 253 253 1 To 8
  • Const. Stage:
    Ongoing
  • Possession:
    30 Jun 2021
Developer Details

  • Developer:
    Bhoomivijay Properties Private Limited
  • Phone:
  • Address:
  • Bajaj Bhawan
Project RERA Details
MAHA REARA No: P51800001693
Project Type Residential / Group Housing
RERA Project Status Ongoing
Architect Vartak Consultants Pvt Ltd
Funding Bank KOTAK MAHINDRA BANK LIMITED
Proposed Possession 30 Jun 2021
Revised Possession 30 Jun 2021
Extended Possession 30 Jun 2026
Litigations No Litigations
Last Modified 07 Jan 2025
Last Retrived 26 Jul 2025
Shubhada Co-Operative Housing Society Ltd. QR Code
Shubhada Co-Operative Housing Society Ltd.
MahaRERA - P51800001693
Apartment Details & Configuration
TypeArea
2 BHK70.46 Sq.mts. ( 758 Sq.ft. )
3 BHK96.57 Sq.mts. ( 1039 Sq.ft. )
2 BHK59.43 Sq.mts. ( 640 Sq.ft. )
3 BHK90.05 Sq.mts. ( 969 Sq.ft. )
3 BHK102.45 Sq.mts. ( 1103 Sq.ft. )
3 BHK118.51 Sq.mts. ( 1276 Sq.ft. )
3 BHK114.3 Sq.mts. ( 1230 Sq.ft. )
3 BHK Tenant93.3 Sq.mts. ( 1004 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shubhada Co-Operative Housing Society Ltd.last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Na
Energy management
Na
Fire Protection And Fire Safety Requirements100% completed
95% Complete
Yet To Begin
Fitness Center
Na
Landscaping & Tree Planting90% completed
90% Complete
As Per Approval
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)100% completed
95% Complete
Chamber And Sewer Line
Solid Waste Management And Disposal
Na
Storm Water Drains100% completed
95% Complete
As Per Approval
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting100% completed
95% Complete
As Per Approval
Water Supply100% completed
95% Complete
Municipal Connection; Yet To Be Connected
Buildings / Wings in Shubhada Co-Operative Housing Society Ltd.
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shubhada Co-Operative Housing Society Ltd. by Bhoomivijay Properties Private Limitedlast updated on 26 Jul 2025 as per information obtained from MARA RERA.

32024 Sq. ft.

Project Area

6296 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

43 apartments in total
Total
43
Booked
31
Available
12

Saleable Area Statistics (Sq. ft.)

46201 Total
Total
46201
Booked
33271
Available
12930
Total 43 apartments in project. 31 apartments booked. 72% apartments booked.
Total 46201 Sq.ft. saleable area. 33271 saleable area booked.
72% area booked.

Shubhada Wing - A

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shubhada Wing - ADec 202081110349
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK70.46 Sq.mts. ( 758 Sq.ft. )3
2 Booked66% Booked
66% Booked
2 BHK Tenant70.46 Sq.mts. ( 758 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK96.57 Sq.mts. ( 1039 Sq.ft. )5
1 Booked20% Booked
20% Booked
3 BHK Tenant96.57 Sq.mts. ( 1039 Sq.ft. )2
2 Booked100% Booked
100% Booked
11 total apartments / 6 apartments booked. 54% apartments booked.
Work Description in Building Shubhada Wing - ACompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Shubhada Wing - B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shubhada Wing - BDec 202081110549
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK59.43 Sq.mts. ( 640 Sq.ft. )2
2 Booked100% Booked
100% Booked
3 BHK90.05 Sq.mts. ( 969 Sq.ft. )1
None Booked0% Booked
0% Booked
3 BHK102.45 Sq.mts. ( 1103 Sq.ft. )6
3 Booked50% Booked
50% Booked
3 BHK118.51 Sq.mts. ( 1276 Sq.ft. )4
3 Booked75% Booked
75% Booked
3 BHK Tenant118.51 Sq.mts. ( 1276 Sq.ft. )3
3 Booked100% Booked
100% Booked
3 BHK Tenant102.45 Sq.mts. ( 1103 Sq.ft. )1
1 Booked100% Booked
100% Booked
3 BHK Tenant90.05 Sq.mts. ( 969 Sq.ft. )3
3 Booked100% Booked
100% Booked
20 total apartments / 15 apartments booked. 75% apartments booked.
Work Description in Building Shubhada Wing - BCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Shubhada Wing - C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Shubhada Wing - CDec 202081110042
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
3 BHK114.3 Sq.mts. ( 1230 Sq.ft. )5
3 Booked60% Booked
60% Booked
3 BHK Tenant114.3 Sq.mts. ( 1230 Sq.ft. )4
4 Booked100% Booked
100% Booked
3 BHK Tenant93.3 Sq.mts. ( 1004 Sq.ft. )3
3 Booked100% Booked
100% Booked
12 total apartments / 10 apartments booked. 83% apartments booked.
Work Description in Building Shubhada Wing - CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Completed 100% done
100% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Completed 100% done
100% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Completed 100% done
100% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Completed 100% done
100% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress90% done
90% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Completed 100% done
100% Booked
Sanitary Fittings within the flats / premises
Completed 100% done
100% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
Completed 100% done
100% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked
Channel Partners
Channel Partners Registered by Developer
Bhoomivijay Properties Private Limited
for Project
Shubhada Co-Operative Housing Society Ltd.
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation