Project overview

Shreeram Complex is a MahaRERA Registered Project bearing MahaRERA Registration Number P99000049212. Shreeram Complex is located at Gut No 189. This is a New being developed by Zinal Builders And Developers.

Shreeram Complex has 1 BHK & 1RK Apartments with carpet areas ranging from 233 to 313 Sq.ft. Carpet. The Project has total 171 of which 148 are currently available for sale.

Shreeram Complex is being developed on a total land area of 32292 Sq.ft. Shreeram Complex has 3 Wings / Towers Bldg No 1 A Wing,Bldg No 2 A And B Wing,Bldg No 3 A And B Wing

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shreeram Complex
  • Location:
  • Gut No 189
  • Const. Stage:
    New
  • Possession:
    31 Dec 2027
Developer Details

  • Developer:
    Zinal Builders And Developers
  • Phone:
  • Address:
  • Shiv Sagar Residency
Project RERA Details
MAHA REARA No: P99000049212
Project Type Residential / Group Housing
RERA Project Status New
Architect Chirag Mistry And Associates
Funding Bank IDBI BANK
Proposed Possession 31 Dec 2027
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 03 Feb 2023
Last Retrived 28 Jul 2025
Shreeram Complex QR Code
Shreeram Complex
MahaRERA - P99000049212
Apartment Details & Configuration
TypeArea
1 BHK29.58 Sq.mts. ( 318 Sq.ft. )
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )
1 BHK31.25 Sq.mts. ( 336 Sq.ft. )
1 BHK31.8 Sq.mts. ( 342 Sq.ft. )
1RK25.61 Sq.mts. ( 276 Sq.ft. )
Shop29.9 Sq.mts. ( 322 Sq.ft. )
Shop20.53 Sq.mts. ( 221 Sq.ft. )
Shop23.18 Sq.mts. ( 250 Sq.ft. )
1 BHK26.49 Sq.mts. ( 285 Sq.ft. )
1 BHK29.06 Sq.mts. ( 313 Sq.ft. )
1 BHK29.1 Sq.mts. ( 313 Sq.ft. )
1RK21.6 Sq.mts. ( 233 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shreeram Complexlast updated on 28 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
Na
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Not Yet Started
Energy management
Na
Fire Protection And Fire Safety Requirements
Na
Landscaping & Tree Planting
Na
Open Parking
Na
Sewerage (Chamber, Lines, Septic Tank , STP)
Not Yet Started
Solid Waste Management And Disposal
Na
Storm Water Drains
Not Yet Started
Street Lighting
Not Yet Started
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Not Yet Started
Water Supply
Not Yet Statred
Buildings / Wings in Shreeram Complex
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shreeram Complex by Zinal Builders And Developerslast updated on 28 Jul 2025 as per information obtained from MARA RERA.

32292 Sq. ft.

Project Area

0 Sq. ft.

Recreational Open Space

Total 3

Wings / Towers in Project

Apartments Statistics

171 apartments in total
Total
171
Booked
23
Available
148

Saleable Area Statistics (Sq. ft.)

51581 Total
Total
51581
Booked
6790
Available
44790
Total 171 apartments in project. 23 apartments booked. 13% apartments booked.
Total 51581 Sq.ft. saleable area. 6790 saleable area booked.
13% area booked.

Bldg No 1 A Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 1 A WingDec 2027710003313
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.58 Sq.mts. ( 318 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK30.13 Sq.mts. ( 324 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK31.25 Sq.mts. ( 336 Sq.ft. )1
None Booked0% Booked
0% Booked
1 BHK31.8 Sq.mts. ( 342 Sq.ft. )49
None Booked0% Booked
0% Booked
1RK25.61 Sq.mts. ( 276 Sq.ft. )7
None Booked0% Booked
0% Booked
Shop29.9 Sq.mts. ( 322 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop20.53 Sq.mts. ( 221 Sq.ft. )1
None Booked0% Booked
0% Booked
Shop23.18 Sq.mts. ( 250 Sq.ft. )1
None Booked0% Booked
0% Booked
68 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Bldg No 1 A WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress20% done
20% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Bldg No 2 A And B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 2 A And B WingDec 202751000460
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK26.49 Sq.mts. ( 285 Sq.ft. )12
3 Booked25% Booked
25% Booked
1 BHK29.06 Sq.mts. ( 313 Sq.ft. )23
11 Booked47% Booked
47% Booked
1 BHK29.1 Sq.mts. ( 313 Sq.ft. )11
None Booked0% Booked
0% Booked
1RK21.6 Sq.mts. ( 233 Sq.ft. )11
57 total apartments / 16 apartments booked. 28% apartments booked.
Work Description in Building Bldg No 2 A And B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure

Bldg No 3 A And B Wing

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Bldg No 3 A And B WingDec 202751000380
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK29.06 Sq.mts. ( 313 Sq.ft. )23
5 Booked21% Booked
21% Booked
1RK21.6 Sq.mts. ( 233 Sq.ft. )23
46 total apartments / 7 apartments booked. 15% apartments booked.
Work Description in Building Bldg No 3 A And B WingCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Zinal Builders And Developers
for Project
Shreeram Complex
last updated on 28 Jul 2025 as per information obtained from MARA RERA.