Project overview

Shreeji Landmark Phase Ii is a MahaRERA Registered Project bearing MahaRERA Registration Number P51700052645. Shreeji Landmark Phase Ii is located at Survey No 136, Hissa No 3. This is a New being developed by Shubh Housing.

Shreeji Landmark Phase Ii has 2 BHK Apartments with carpet areas ranging from 508 to 508 Sq.ft. Carpet. The Project has total 111 of which 94 are currently available for sale.

Shreeji Landmark Phase Ii is being developed on a total land area of 33681 Sq.ft. out of which 5076 Sq.ft. i.e 15% is reserved for recreational purposes. Shreeji Landmark Phase Ii has 4 Wings / Towers Wing B,Wing C,Wing D,Wing E

ProjectDeveloperLocationPossession
Project Details
  • Project:
    Shreeji Landmark Phase Ii
  • Location:
  • Survey No 136, Hissa No 3
  • Const. Stage:
    New
  • Possession:
    31 Dec 2026
Developer Details

  • Developer:
    Shubh Housing
  • Phone:
  • Address:
  • Shree Sai Homes, Sai Paradise
Project RERA Details
MAHA REARA No: P51700052645
Project Type Others
RERA Project Status New
Architect Raj Associates
Funding Bank HDFC BANK
Proposed Possession 31 Dec 2026
Revised Possession
Extended Possession
Litigations No Litigations
Last Modified 21 May 2024
Last Retrived 26 Jul 2025
Shreeji Landmark Phase Ii QR Code
Shreeji Landmark Phase Ii
MahaRERA - P51700052645
Apartment Details & Configuration
TypeArea
1 BHK30 Sq.mts. ( 323 Sq.ft. )
1 BHK33.31 Sq.mts. ( 359 Sq.ft. )
2 BHK42.86 Sq.mts. ( 461 Sq.ft. )
2 BHK43.07 Sq.mts. ( 464 Sq.ft. )
1 BHK28.24 Sq.mts. ( 304 Sq.ft. )
1 BHK34.78 Sq.mts. ( 374 Sq.ft. )
2 BHK47.18 Sq.mts. ( 508 Sq.ft. )
Facilities & Amenities
Facilities, Amenities & Common areas details of Shreeji Landmark Phase Iilast updated on 26 Jul 2025 as per information obtained from MARA RERA.
Project Facilities & Amenities Available Details
Aggregate area of recreational Open Space
-
Community Buildings
Na
Electrical Meter Room, Sub-Station, Receiving Station
Meter Room Provided
Energy management
Na
Fire Protection And Fire Safety Requirements
Fire Protection And Fire Safety Requirements
Landscaping & Tree Planting
Tree Planting
Open Parking
As Per Plan
Sewerage (Chamber, Lines, Septic Tank , STP)
Septic Tank
Solid Waste Management And Disposal
Na
Storm Water Drains
Storm Water Drains
Street Lighting
Na
Treatment And Disposal Of Sewage And Sullage Water
Na
Water Conservation, Rain water Harvesting
Rain Water Harvesting Work
Water Supply
M.J.P Will Provided Water Connection After Oc
Buildings / Wings in Shreeji Landmark Phase Ii
Apartments Statistics, Saleable Area Statistics and available inventory snapshot of Shreeji Landmark Phase Ii by Shubh Housinglast updated on 26 Jul 2025 as per information obtained from MARA RERA.

33681 Sq. ft.

Project Area

5076 Sq. ft.

Recreational Open Space

Total 4

Wings / Towers in Project

Apartments Statistics

111 apartments in total
Total
111
Booked
17
Available
94

Saleable Area Statistics (Sq. ft.)

41317 Total
Total
41317
Booked
6709
Available
34608
Total 111 apartments in project. 17 apartments booked. 15% apartments booked.
Total 41317 Sq.ft. saleable area. 6709 saleable area booked.
16% area booked.

Wing B

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing BDec 202671010600
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30 Sq.mts. ( 323 Sq.ft. )13
1 BHK33.31 Sq.mts. ( 359 Sq.ft. )7
4 Booked57% Booked
57% Booked
2 BHK42.86 Sq.mts. ( 461 Sq.ft. )14
5 Booked35% Booked
35% Booked
2 BHK43.07 Sq.mts. ( 464 Sq.ft. )6
2 Booked33% Booked
33% Booked
40 total apartments / 13 apartments booked. 32% apartments booked.
Work Description in Building Wing BCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Completed 100% done
100% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
work-in-progress20% done
20% Booked
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
work-in-progress30% done
30% Booked
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress85% done
85% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress70% done
70% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress68% done
68% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress20% done
20% Booked
Sanitary Fittings within the flats / premises
work-in-progress90% done
90% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress70% done
70% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing C

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing CDec 202671010610
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK30 Sq.mts. ( 323 Sq.ft. )27
1 BHK33.31 Sq.mts. ( 359 Sq.ft. )7
None Booked0% Booked
0% Booked
2 BHK43.07 Sq.mts. ( 464 Sq.ft. )7
None Booked0% Booked
0% Booked
41 total apartments / 2 apartments booked. 4% apartments booked.
Work Description in Building Wing CCompletion
Basement (if any)
Completed 100% done
100% Booked
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
work-in-progress90% done
90% Booked
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
work-in-progress70% done
70% Booked
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
work-in-progress60% done
60% Booked
Overall Percentage of Completion of the work done For the entire Building /Wing
work-in-progress64% done
64% Booked
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
work-in-progress20% done
20% Booked
Sanitary Fittings within the flats / premises
work-in-progress40% done
40% Booked
Slabs of Super Structure
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Completed 100% done
100% Booked
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Completed 100% done
100% Booked
Stilt Floor
Completed 100% done
100% Booked
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
work-in-progress60% done
60% Booked
X number of Basement(s) and Plinth
Completed 100% done
100% Booked
X number of Podiums
X number of Slabs of Super Structure
Completed 100% done
100% Booked

Wing D

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing DDec 202671010420
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
1 BHK28.24 Sq.mts. ( 304 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK33.31 Sq.mts. ( 359 Sq.ft. )7
None Booked0% Booked
0% Booked
1 BHK34.78 Sq.mts. ( 374 Sq.ft. )14
28 total apartments / 2 apartments booked. 7% apartments booked.
Work Description in Building Wing DCompletion
Basement (if any)
Excavation
Completed 100% done
100% Booked
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Completed 100% done
100% Booked
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure

Wing E

WingProposed Date of CompletionNumber of SlabsPlinthBasement'sStiltsPodium'sOpen ParkingsClosed Parkings
Wing EDec 20261101030
Apartment TypeCarpet AreaNumber of ApartmentsBooked Apartments
2 BHK47.18 Sq.mts. ( 508 Sq.ft. )2
None Booked0% Booked
0% Booked
2 total apartments / 0 apartments booked. 0% apartments booked.
Work Description in Building Wing ECompletion
Basement (if any)
Excavation
External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate
Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.
Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises
Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises
Overall Percentage of Completion of the work done For the entire Building /Wing
Plinth
Podiums (if any)
Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises
Sanitary Fittings within the flats / premises
Slabs of Super Structure
Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.
Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks
Stilt Floor
The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing
X number of Basement(s) and Plinth
X number of Podiums
X number of Slabs of Super Structure
Channel Partners
Channel Partners Registered by Developer
Shubh Housing
for Project
Shreeji Landmark Phase Ii
last updated on 26 Jul 2025 as per information obtained from MARA RERA.
Name Company Location Mobile Designation